Estanzo

Timeline Bar

Registered12 Feb 2020
Promised12 Sept 2023
Completed11 Mar 2024

Timeline

Promised completion12 Sept 2023
Revised completion12 Sept 2023
Actual completion11 Mar 2024
Possession delay6 mo delay

Registration & Cost Details

Registration fee (in ₹)₹18,200
Project cost (in ₹ Lakhs)₹200 Lakhs
Project duration51 months
Project categoryCommercial
Locality
Original start date
Proposed start date1 Jan 2020

Inventory

Total units40
Unit TypeUnitsCarpet Area (sqm)
SHOP368.9–18.7
OTHER441.55–56.53

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9670222298
Emailehil@eldecohousing.co.in
Coordinator9670222298
AddressShop No S-16, Second Floor, Eldeco Station 1, Site No.1, Faridabad sector 12, Faridabad 121007, Haryana India

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
4294613 Sept 201812 Sept 202312 Sept 202311 Sept 2026

Land Parcels

Khasra No.AreaPlot Type
4004150Khasra

Approved Unit Plan

Unit plan rows on file14
Total flats (sum of rows)40
Total shops36
BlocksCITY PLAZA
Floor typesSHOP, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Eldeco City Plaza?

The RERA registration number of Eldeco City Plaza is UPRERAPRJ138660, as recorded on the UP-RERA portal.

What is the RERA status of Eldeco City Plaza?

As reported by UP-RERA, the status of Eldeco City Plaza is "Registered".

Where is Eldeco City Plaza located?

As reported to UP-RERA, Eldeco City Plaza is located at Bakshi Ka Talab**, Lucknow, Uttar Pradesh.

Is Eldeco City Plaza completed?

As reported to UP-RERA, Eldeco City Plaza was completed on 11 Mar 2024.

Is Eldeco City Plaza delayed?

Measured against the latest completion date reported to UP-RERA, Eldeco City Plaza is 6 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026