Estanzo

Timeline Bar

Registered20 Mar 2020
Promised19 Aug 2024
Today4 Aug 2026

Timeline

Promised completion19 Aug 2024
Revised completion19 Aug 2024
Actual completion
Possession delay23 mo delay

Registration & Cost Details

Registration fee (in ₹)₹39,500
Project cost (in ₹ Lakhs)₹5,711 Lakhs
Project duration65 months
Project categoryResidential
Locality
Original start date
Proposed start date1 Oct 2020

Inventory

Total units208
Unit TypeUnitsCarpet Area (sqm)
2 BHK18250.6–53.4
3 BHK2668.08

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile7571811111
Emailinfo@excellainfra.in
Coordinator7570000125
AddressB-2/345, Vikas Khand, Gomti Nagar, Lucknow-226010

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q290.5%
2025-Q360.0%
2025-Q470.0%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
4090020 Aug 201619 Aug 202119 Aug 202419 Aug 2024
40900

Revalidated: 40900 (20 Aug 2021)

20 Aug 202119 Aug 2024

Revalidated upto: 9 Aug 2028

19 Aug 20249 Aug 2028

Land Parcels

Khasra No.AreaPlot Type
2695/1, 2693, 26946860Khasra

Approved Unit Plan

Unit plan rows on file208
Total flats (sum of rows)208
BlocksA-1, A-2
Floor types2 BHK, 3 BHK

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Excella Kutumb Phase-III?

The RERA registration number of Excella Kutumb Phase-III is UPRERAPRJ367744, as recorded on the UP-RERA portal.

What is the RERA status of Excella Kutumb Phase-III?

As reported by UP-RERA, the status of Excella Kutumb Phase-III is "Registered".

Where is Excella Kutumb Phase-III located?

As reported to UP-RERA, Excella Kutumb Phase-III is located at Mohanlalganj, Lucknow, Uttar Pradesh.

When will Excella Kutumb Phase-III be completed?

The latest completion date reported to UP-RERA for Excella Kutumb Phase-III is 19 Aug 2024.

Is Excella Kutumb Phase-III delayed?

Measured against the latest completion date reported to UP-RERA, Excella Kutumb Phase-III is 23 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026