GH-1 Grand Omaxe Regent

UPRERARegistered

GH-1 Grand Omaxe Regent is a RERA-registered residential project by Omaxe Limited in Lucknow (RERA ID UPRERAPRJ537348). Registered with a completion deadline of 28 Feb 2030.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q1'25
—Q2'25
0.89%Q3'25
5.37%Q4'25
6.88%Q1'26
10.75%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ537348
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryLucknow Development Authority
Proposed start1 Mar 2025
Project duration60 months
AddressOmaxe Integrated Township at Sultanpur Road , Lucknow , UP, Lucknow, Lucknow, Lucknow
TehsilLucknow
Applicant typeCompany
Applicant addressSHOP No-19-B, FIRST FLOOR, OMAXE CELEBRATION MALL, SOHNA ROAD, GURGAON-122001
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. valid to

    Permit revalidated

    Group Housing/14188/LDA/BP/24-25/2254/06122024

  2. 2 building permits sanctioned

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Registered with RERA

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered29 Apr 2025
Original completion28 Feb 2030
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹24,500
Sanctioning authorityLucknow Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors48 · 1 · 24 (units from plan)
ConfigurationUnitsCarpet area
4 BHK48131-158
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Tower-1, 4BHK+ Servent · 4 BHK2448131-158
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Apurba Borah
License CA/2013/61618
Flat No. 3A, Himgiri Apartments, pocket-14, Kalkaji Extension, New Delhi-110017
Engineer
Mr. Sanjeev Jain
Chordia Engineering Consultancy Services, I- 1738, Chittranjan Park, Lower Ground Floor, New Delhi-19
Contractor
Omaxe Ltd
7,LSC Kalkaji, New Delhi
Sr.Development work declared to RERA
1Demarcation of Plots
Demarcation of Project to be done at site.
2Boundary Wall
Boundary wall will be constructed by Brickwork/ MS Railing as per requirement and designed by promoter.
3Road Work
Internal drive way 6 mtr wide, will be developed by RCC/ Interlocking Pavers / Bitumen as per approved layout , as per Requirement and designed by promoter
4Footpaths
Both sides of road , Footpath will be developed ,width 1.0 to 1.5 mtr. as per requirement and designed by promoter.
5Water Supply Including Drinking Water Facilities
Water supply including drinking water facilities will be provided by promoter through Roof tank / Bore well.
6Sewer System
Common S.T.P. will be constructed for GH-1 , at site for Sewer Disposal.
7Drain
Drainage system will be developed and connected with RWH and over flow will be constructed with Existing Drains.
8Parks
Common Parks /Green area approx 5000 sqm will be developed in Gh-1 . And will be developed as per approved plan and requirements.
9Tree Planting
Required Tree approx225 nos , will be planted in Gh-1 within parks , road side and boundary, as per requirement and norms.
10Design For Electric Supply Including Street Lighting
Electric Supply will be provided fromm ESS. Street Lights will be fixed at road berms as per requirement norms.
11Community Buildings
Common Community Building as per Approved layout, will be provided for GH-1.
12Treatment and Disposal System of Sewage and Sullage water
S.T.P. will be constructed for Gh-1 , and treated water will be use in irrigation of green areas and as per govt. norms.
13Solid Waste Management And Disposal System
Solid waste management and disposal system will be provided as per requirement and Govt. Norms
14Water Conservation System
Water Conservation System will be provided as per Govt. Norms.
15Energy Management System Including Use of Renewable Energy
Energy management system will be provided as per Govt. Norms
16Fire Protection And Fire Safety System
Fire Safety System will be provided as per approval , Design and Norms.
17Social Infrastructure And Other Public Amenities Including Public Health Services
As per integrated township policy.
18Emergency Evacuation Services
As per fire norms 6 metre and above road proposed.
19Other Miscellaneous Work
As per specification finalize by the approved map all works will be developed.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

39 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1AKASH DEEP SRIVASTAVAUPRERAAGT15712
2ANYA PROPERTIESUPRERAAGT15969
3Arvind Kumar VermaUPRERAAGT12382
4BASECAMP INFRA CONSULTANTS (OPC) PRIVATE LIMITEDUPRERAAGT14759
5BRIXWELL REALTY & CONSTRUCTION LLPUPRERAAGT15068
6CHANDRA PRAKASHUPRERAAGT13704
7CITYMAX PROPMART PRIVATE LIMITEDUPRERAAGT13792
8DAIWIK REALTORSUPRERAAGT12075
9GOLDEN ESTATEUPRERAAGT10397
10HITESH KHANNAUPRERAAGT13833
11INVESTORS CARE INFRATECH PVT LTDUPRERAAGT13542
12INVESTORS CLINIC INFRATECH PRIVATE LIMITEDUPRERAAGT10052
13KAUSHTUBH REALTY PRIVET LIMITEDUPRERAAGT13025
14KONRAI OVERSEASUPRERAAGT14764
15LINK PROPERTIESUPRERAAGT10081
16Mahima SinghUPRERAAGT17171
17MONISHA BUDHRAJAUPRERAAGT16694
18PIXEL GLOBAL INFRA PRIVATE LIMITEDUPRERAAGT13936
19PRIYANK SHEKHARUPRERAAGT13933
20RADHESH CHANDRAUPRERAAGT10484
21RAJNI NIGAMUPRERAAGT10897
22RAMJI SINGHUPRERAAGT23922
23RANI SHUKLAUPRERAAGT15652
24Regrob Infrastructure Pvt LtdUPRERAAGT12681
25RELIVE SOLUTIONS PVT. LTD.UPRERAAGT10078
26Sakshi GuptaUPRERAAGT16025
27SHAH MOHSIN KAMALUPRERAAGT14208
28Shalini VermaUPRERAAGT15031
29SHALINI WADHWAUPRERAAGT15032
30SHRI RUDRA REAL ESTATESUPRERAAGT14251
31SILVER EDGE REAL ESTATE SOLUTIONUPRERAAGT12168
32SILVEREDGE REALTECHUPRERAAGT21807
33SOURABH NIGAMUPRERAAGT10900
34STRAIGHTEDGE REAL ESTATE PRIVATE LIMITEDUPRERAAGT10067
35SUSHILA DEVI SRIVASTAVAUPRERAAGT15738
36Unnisis Infrratech Private LimitedUPRERAAGT15300
37Varun Properties Inc.UPRERAAGT11985
38Vinod DawraUPRERAAGT19609
39VISHAL KUMARUPRERAAGT14798
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 20 Dec 2029. 1 of them carries a revalidation, valid to 18 Mar 2032.

Sanctioned by Lucknow Development Authority · 3,855 sqm of land · an approved plan of 1 block and 48 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
Group Housing/14188/LDA/BP/24-25/2254/0612202420 Dec 202420 Dec 202918 Mar 203328 Feb 2030—
Group Housing/14188/LDA/BP/24-25/2254/0612202420 Dec 202420 Dec 202918 Mar 203528 Feb 203020 Dec 2024
valid to 18 Mar 2032
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

19 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
403, 4056191.69Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · 11160
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 5385
The registered deed by which the promoter bought the land.
PDF ↗
Khatauni extract · 1426- 1431 (01 /07/2018 to 30/06/2024)
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1426-1431 (01/07/2018 to 30/06/2024)
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Registry document · consodium
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Sale deed · 7029/25
The registered deed by which the promoter bought the land.
PDF ↗
Document checklist
DocumentStatusUploaded
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New17 Apr 2025 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New21 Feb 2025 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New21 Feb 2025 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New3 Apr 2025 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New21 Feb 2025 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New21 Feb 2025 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New21 Feb 2025 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New21 Feb 2025 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New17 Apr 2025 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New6 Mar 2025 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New3 Apr 2025 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New2 Apr 2025 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New7 Mar 2025 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New21 Feb 2025 ↗

Quarterly progress reports

6 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

6 quarterly progress reports are on file with UPRERA, covering 2024-Q4 to 2026-Q1.

QuarterConstructionCertificates
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q20.89%CA ↗ · Arch ↗ · Eng ↗
2025-Q35.37%CA ↗ · Arch ↗ · Eng ↗
2025-Q46.88%CA ↗ · Arch ↗ · Eng ↗
2026-Q110.75%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameOmaxe Limited
RolePromoter · current
RERA IDUPRERAPRM2386
PANAAACO0171H
CIN / TANDELO01861G
Name of chairmanMr. Rohtash Goel
Registered addressSHOP No-19-B, FIRST FLOOR, OMAXE CELEBRATION MALL, SOHNA ROAD, GURGAON-122001
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameADVAY PROPERTIES PRIVATE LIMITED
RoleCo-promoter
Applicant typeCompany
AddressGROUND FLOOR, 22 OMAXE VALUE MALL AJNARA ROAD AMRITSAR Amritsar PB 143001 IN
RERA contact

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
OMAXE LTD COLL A/C GH-1 REGENTBankHDFC BANKBranchHDFC BANK , INDRA NAGAR, LUCKNOWBranch addressHDFC BANK , INDRA NAGAR , LUCKNOWBranch districtLucknowA/C no.IFSCHDFC000917Branch emailruchi.aggarwal@hdfcbank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
OMAXE LTD SEPERATE BANK A/C GH-1 REGENTBankHDFC BANKBranchHDFC BANK, INDIRA NAGAR, LUCKNOWBranch addressHDFC BANK, INDIRA NAGAR, LUCKNOWBranch districtLucknow, Uttar PradeshA/C no.IFSCHDFC000917
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
OMAXE LTD TRANSACTION A/C GH-1 REGENTBankHDFC BANKBranchHDFC BANK , INDIRA NAGAR, LUCKNOWBranch addressHDFC BANK, INDIRA NAGAR, LUCKNOWBranch districtLucknow, Uttar PradeshA/C no.IFSCHDFC000917
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

5 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)224 (Under Registration - 4 ) → 225 (Under Registration - 4 )
changed in Estanzo’s record
18 Oct 2026
Promoter’s complaints tally (all their projects)224 (Under Registration - 5 ) → 224 (Under Registration - 4 )
changed in Estanzo’s record
23 Sept 2026
Promoter’s complaints tally (all their projects)223 (Under Registration - 4 ) → 224 (Under Registration - 5 )
changed in Estanzo’s record
11 Sept 2026
Promoter’s complaints tally (all their projects)223 (Under Registration - 5 ) → 223 (Under Registration - 4 )
changed in Estanzo’s record
7 Sept 2026
Promoter’s complaints tally (all their projects)220 (Under Registration - 3 ) → 223 (Under Registration - 5 )
changed in Estanzo’s record
23 Aug 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 18 Oct 2026 · 5 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about GH-1 Grand Omaxe Regent

Is GH-1 Grand Omaxe Regent RERA registered?

Yes. GH-1 Grand Omaxe Regent is registered with UPRERA under registration number UPRERAPRJ537348, registered on 29 Apr 2025. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for GH-1 Grand Omaxe Regent?

The completion date filed with UPRERA is 28 Feb 2030. No completion certificate is on record yet.

Who is the builder of GH-1 Grand Omaxe Regent?

Omaxe Limited is the promoter entity that filed GH-1 Grand Omaxe Regent with UPRERA (promoter RERA ID UPRERAPRM2386). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does GH-1 Grand Omaxe Regent have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is GH-1 Grand Omaxe Regent located?

GH-1 Grand Omaxe Regent is registered in Lucknow, Lucknow, as filed with UPRERA.

What configurations are available in GH-1 Grand Omaxe Regent?

The unit plan filed with UPRERA lists 4 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in GH-1 Grand Omaxe Regent?

The approved unit plan filed with UPRERA runs from 131 to 158 m² of carpet area (about 1,415 to 1,705 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in GH-1 Grand Omaxe Regent?

The approved unit plan describes 1 block and 48 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is GH-1 Grand Omaxe Regent?

About 50 units per acre: 48 planned units across 0.95 acres (3,855 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗