Golf Links EWS & LIG

UPRERARegistered

Golf Links EWS & LIG is a RERA-registered residential project by Landcraft Developers Private Limited in Ghaziabad (RERA ID UPRERAPRJ5995). Registered with a completion deadline of 10 Jan 2024. UP-RERA flags this project "Default on QPR": it has not filed its mandatory quarterly progress report(s).

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ5995
Project categoryResidential
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGhaziabad Development Authority
Proposed start1 Aug 2017
Original start1 Aug 2017
Project duration78 months
AddressGhaziabad, Ghaziabad
TehsilGhaziabad
Applicant typeCompany
Applicant addressParmesh Corporate Towers 309, 3rd Floor, Plot No. 13 Karkardooma Community Centre Delhi
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. 2 building permits sanctioned

  2. Registered with RERA

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. to

    Extension granted

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  7. to

    Extension granted

  8. to

    Extension granted

  9. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly reports are in default on this project’s record.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered30 Jul 2017
Original completion31 Oct 2019
Revised completion10 Jan 2024
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹35,500
Sanctioning authorityGhaziabad Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors341 · 3 · 6 (units from plan)
  • OTHER225 66%
  • 1 BHK116 34%
ConfigurationUnitsCarpet area
OTHER22520
1 BHK11630
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Tower-1 · OTHER, 1 BHK69620-30
Tower-2 · OTHER, 1 BHK514620-30
Tower-3 · OTHER, 1 BHK69920-30
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Shilpa Agrawal
License CA/97/21784
Shilp Kriti Architects, GC-34, 3rd Floor, Aditya Gold Crest Mall, Vaibhav Khand, Indirapuram, Ghaziabad
Engineer
VD Sharma
Optimum Design Pvt. Ltd., Noida
Contractor
NRS Buildcraft Pvt. Ltd.
302, 3rd Floor, Devika Chambers, A-14, RDC, Raj Nagar, Ghaziabad
Sr.Development work declared to RERA
1Demarcation of Plots
As per sanction map
2Boundary Wall
As per sanction map
3Road Work
As per sanction map
4Footpaths
As per sanction map
5Water Supply Including Drinking Water Facilities
As per sanction map
6Sewer System
As per sanction map
7Drain
As per sanction map
8Parks
As per sanction map
9Tree Planting
As per sanction map
10Design For Electric Supply Including Street Lighting
As per sanction map
11Community Buildings
As per sanction map
12Treatment and Disposal System of Sewage and Sullage water
As per sanction map
13Solid Waste Management And Disposal System
As per sanction map
14Water Conservation System
As per sanction map
15Energy Management System Including Use of Renewable Energy
As per sanction map
16Fire Protection And Fire Safety System
As per sanction map
17Social Infrastructure And Other Public Amenities Including Public Health Services
As per sanction map
18Emergency Evacuation Services
As per sanction map
19Other Miscellaneous Work
As per sanction map
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 3 Sept 2018.

Sanctioned by Ghaziabad Development Authority · 6,096 sqm of land · an approved plan of 3 blocks and 341 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
223/Zone-4/2013-144 Sept 20133 Sept 201831 Oct 201910 Jan 2024
223/Zone-4/2013-144 Sept 20133 Sept 201829 Apr 202110 Jan 2024
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 4 completion extensions for this project, the latest running to 10 Jan 2024.

#Granted fromExtended uptoNote
131 Oct 201930 Oct 2020—
230 Oct 202029 Apr 2021Six months extension in view of force majeure caused by covid-19 pandemic
329 Apr 202128 Jan 2022—
428 Jan 202210 Jan 2024—

Land & documents

25 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
231503.98Khasra
2331611.48Khasra
2322061.38Khasra
2381919.57Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · 2972
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 7163 (part-1)
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 7163 (part-2)
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 2231
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 3884
The registered deed by which the promoter bought the land.
PDF ↗
Registry document · 3835
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New1 Jul 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New29 Jun 2018 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New4 Jul 2018 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New29 Jun 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New29 Jun 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New29 Jun 2018 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New4 Jul 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New5 Jul 2018 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New6 Jul 2018 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New1 Jul 2018 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New5 Jul 2018 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
Old12 Oct 2017 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
Old12 Oct 2017 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
Old12 Oct 2017 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
Old12 Oct 2017 ↗
Registry document (own land)
The registered deed for land the promoter holds itself, rather than under an agreement with a landowner.
Old17 Oct 2017 ↗
Registry document (own land)
The registered deed for land the promoter holds itself, rather than under an agreement with a landowner.
Old17 Oct 2017 ↗
Registry document (own land)
The registered deed for land the promoter holds itself, rather than under an agreement with a landowner.
Old23 Oct 2017 ↗
Registry document (own land)
The registered deed for land the promoter holds itself, rather than under an agreement with a landowner.
Old23 Oct 2017 ↗

Quarterly progress reports

13 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

13 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2023-Q1.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameLandcraft Developers Private Limited
RolePromoter · current
RERA IDUPRERAPRM11777
PANAABCL1391F
CIN / TANU45201DL2005PTC132131
Name of chairman1) Mr. Rakesh Garg 2) Mr. Lalit Kumar Jaiswal 3) Mr. Rakesh Kumar Goel 4) Mr. Manu Garg
Registered addressParmesh Corporate Towers 309, 3rd Floor, Plot No. 13 Karkardooma Community Centre Delhi
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Ghaziabad

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
Landcraft Developers Private LimitedBankHDFC BANK LIMITEDBranchRDC,RAJ NAGAR, GHAZIABADA/C no.IFSCHDFC000153
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Golf Links EWS & LIG

Is Golf Links EWS & LIG RERA registered?

Yes. Golf Links EWS & LIG is registered with UPRERA under registration number UPRERAPRJ5995, registered on 30 Jul 2017. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Golf Links EWS & LIG?

The completion date filed with UPRERA is 10 Jan 2024. No completion certificate is on record yet.

Who is the builder of Golf Links EWS & LIG?

Landcraft Developers Private Limited is the promoter entity that filed Golf Links EWS & LIG with UPRERA (promoter RERA ID UPRERAPRM11777). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Why does Golf Links EWS & LIG show "default on QPR"?

UPRERA flags this project as in default on quarterly progress reporting - the promoter has not filed one or more mandatory quarterly progress reports. The flag is the authority's, not Estanzo's.

Has UPRERA granted Golf Links EWS & LIG more time to complete?

UPRERA's record carries 4 completion extensions for Golf Links EWS & LIG, the latest running to 10 Jan 2024. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Golf Links EWS & LIG have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Golf Links EWS & LIG located?

Golf Links EWS & LIG is registered in Ghaziabad, as filed with UPRERA.

What configurations are available in Golf Links EWS & LIG?

The unit plan filed with UPRERA lists OTHER and 1 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Golf Links EWS & LIG?

The approved unit plan filed with UPRERA runs from 20 to 30 m² of carpet area (about 211 to 318 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Golf Links EWS & LIG?

The approved unit plan describes 3 blocks and 341 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Golf Links EWS & LIG?

About 226 units per acre: 341 planned units across 1.51 acres (6,096 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗