Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ16612
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGreater Noida Authority
Proposed start1 Jul 2018
Project duration78 months
AddressGautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressC-2, MAHALUXMI MALL, 5TH FLOOR, RAJ NAGAR, GHAZIABAD.
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. valid to

    Permit revalidated

    BP4143/3914

  2. 2 building permits sanctioned

  3. Registered with RERA

  4. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  5. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  6. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  7. to

    Extension granted

  8. Completion certificate filed

  9. 3 completion certificates filed

  10. Completion certificate filed

  11. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

  12. Completion certificate filed

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered19 Jun 2018
Original completion12 Jun 2023
Revised completion10 Dec 2024
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary3 Jun 2024
Registration fee₹1,21,000
Sanctioning authorityGreater Noida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors1,311 · 7 · 26 (units from plan)
Homes · commercial units1,263 · 48 (shops and offices filed in the same plan)
  • 2 BHK706 54%
  • 3 BHK335 26%
  • 4 BHK212 16%
  • SHOP48 4%
  • 1 BHK10 1%
ConfigurationUnitsCarpet area
2 BHK70637-48
3 BHK3355-147
1 BHK1024-43
4 BHK21284-146
SHOP4811
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
SUN - 2 · 3 BHK, 1 BHK, 2 BHK, 4 BHK2623025-103
SUN - 3 · 2 BHK, 3 BHK2620837-58
SUN - 4 · 1 BHK, 2 BHK, 3 BHK, 4 BHK241875-95
SUN - 5 · 2 BHK, 3 BHK, 4 BHK2419137-95
SUN - 6 · 2 BHK, 1 BHK, 3 BHK, 4 BHK2621724-146
Sun - 1 · 3 BHK, 1 BHK, 2 BHK, 4 BHK2623025-103
VILAASA WALK · SHOP24811
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
VISHAL MITTAL
License CA/98/23185
B-34, SECTOR 67, NOIDA.
Engineer
NNC DESIGN INTERNATIONAL
G-70, 2nd Floor, Jaswant Plaza, Near Kalindi Kunj, Main Sarita Vihar Road, Okhla, New Delhi.
Contractor
HARSH CONSTRUCTION
212, HARSH MALL, COMMERCIAL BELT, ALPHA-1, GREATER NOIDA.
Sr.Development work declared to RERA
1Demarcation of Plots
ALREADY DONE ON SITE
2Boundary Wall
TO BE EXCUTED ON SITE AS PER SANCTION PLAN
3Road Work
TO BE EXCUTED ON SITE AS PER SANCTION PLAN
4Footpaths
TO BE EXCUTED ON SITE AS PER SANCTION PLAN
5Water Supply Including Drinking Water Facilities
TO BE EXCUTED ON SITE DRAWINGS UPLOADED
6Sewer System
TO BE EXCUTED ON SITE DRAWINGS UPLOADED
7Drain
TO BE EXCUTED ON SITE DRAWINGS UPLOADED
8Parks
TO BE EXCUTED ON SITE AS PER SANCTION PLAN
9Tree Planting
TO BE EXCUTED ON SITE AS PER SANCTION PLAN
10Design For Electric Supply Including Street Lighting
TO BE EXCUTED ON SITE DRAWINGS UPLOADED
11Community Buildings
TO BE EXCUTED ON SITE AS PER SANCTION PLAN
12Treatment and Disposal System of Sewage and Sullage water
TO BE EXCUTED ON SITE DRAWINGS UPLOADED
13Solid Waste Management And Disposal System
TO BE EXCUTED ON SITE DRAWINGS UPLOADED
14Water Conservation System
TO BE EXCUTED ON SITE DRAWINGS UPLOADED
15Energy Management System Including Use of Renewable Energy
NOT APPLICABLE
16Fire Protection And Fire Safety System
TO BE EXCUTED ON SITE DRAWINGS UPLOADED
17Social Infrastructure And Other Public Amenities Including Public Health Services
TO BE EXCUTED ON SITE AS PER SANCTION PLAN
18Emergency Evacuation Services
TO BE EXCUTED ON SITE DRAWINGS UPLOADED
19Other Miscellaneous Work
TO BE EXCUTED ON SITE AS PER SANCTION PLAN
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

1 agent

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1BOP REALTY PRIVATE LIMITEDUPRERAAGT10206
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 13 Jun 2023. 1 of them carries a revalidation, valid to 12 Jun 2028.

Sanctioned by Greater Noida Authority · 23,200 sqm of land · an approved plan of 7 blocks and 1311 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
BP4143/391414 Jun 201813 Jun 202312 Jun 202612 Jun 2023—
BP4143/391414 Jun 201813 Jun 202313 Jun 202811 Dec 202314 Jun 2018
valid to 12 Jun 2028
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 2 completion extensions for this project, the latest running to 10 Dec 2024.

#Granted fromExtended uptoNote
112 Jun 202311 Dec 2023Six months extension in view of force majeure caused by covid-19 pandemic
211 Dec 202310 Dec 2024—

Land & documents

14 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
GH 1B(2), Sector ETA-2, Greater Noida, U.P.23200Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 10817
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
not reported—
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New18 Jun 2018 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New18 Jun 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New18 Jun 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New18 Jun 2018 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New18 Jun 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New18 Jun 2018 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New18 Jun 2018 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New18 Jun 2018 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New18 Jun 2018 ↗

Quarterly progress reports

19 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

19 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2024-Q3.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameYAMUNA BUILTECH PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM48529
PANAAACY8912E
CIN / TANU70200UP2017PTC092923
Name of chairmanSUNIL MIGLANI
Registered addressC-2, MAHALUXMI MALL, 5TH FLOOR, RAJ NAGAR, GHAZIABAD.
RERA contact
Registered since2018
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
YAMUNA BUILTECH PRIVATE LIMITED-RERA ACCOUNTBankINDUSLND BANK LIMITEDBranchINDUSLND BANK LIMITED BARAKHAMBA ROAD ,NEW DELHI-110001A/C no.IFSCINDB0000005
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

6 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)97 (Under Registration - 3 ) → 98 (Under Registration - 4 )
changed in Estanzo’s record
18 Oct 2026
Promoter’s complaints tally (all their projects)96 (Under Registration - 2 ) → 97 (Under Registration - 3 )
changed in Estanzo’s record
3 Oct 2026
Promoter’s complaints tally (all their projects)96 (Under Registration - 3 ) → 96 (Under Registration - 2 )
changed in Estanzo’s record
21 Sept 2026
Promoter’s complaints tally (all their projects)95 (Under Registration - 2 ) → 96 (Under Registration - 3 )
changed in Estanzo’s record
17 Sept 2026
Promoter’s complaints tally (all their projects)95 (Under Registration - 3 ) → 95 (Under Registration - 2 )
changed in Estanzo’s record
9 Sept 2026
Promoter’s complaints tally (all their projects)93 (Under Registration - 1 ) → 95 (Under Registration - 3 )
changed in Estanzo’s record
31 Aug 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 18 Oct 2026 · 6 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about MIGSUN VILAASA

Is MIGSUN VILAASA RERA registered?

Yes. MIGSUN VILAASA is registered with UPRERA under registration number UPRERAPRJ16612, registered on 19 Jun 2018. Estanzo reproduces that filing; it does not verify the work behind it.

Has MIGSUN VILAASA been completed?

UPRERA still lists MIGSUN VILAASA as Registered, so it is not shown as completed here. A completion certificate dated 3 Jun 2024 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of MIGSUN VILAASA?

YAMUNA BUILTECH PRIVATE LIMITED is the promoter entity that filed MIGSUN VILAASA with UPRERA (promoter RERA ID UPRERAPRM48529). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted MIGSUN VILAASA more time to complete?

UPRERA's record carries 2 completion extensions for MIGSUN VILAASA, the latest running to 10 Dec 2024. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does MIGSUN VILAASA have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is MIGSUN VILAASA located?

MIGSUN VILAASA is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in MIGSUN VILAASA?

The unit plan filed with UPRERA lists 2 BHK, 3 BHK, 1 BHK, 4 BHK and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in MIGSUN VILAASA?

The approved unit plan filed with UPRERA runs from 5 to 147 m² of carpet area (about 58 to 1,578 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in MIGSUN VILAASA?

The approved unit plan describes 7 blocks and 1,311 units of which 1,263 are homes and 48 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is MIGSUN VILAASA?

About 229 units per acre: 1,311 planned units across 5.73 acres (23,200 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗