Nirmal Residency

UPRERARegistered

Nirmal Residency is a RERA-registered residential project by Yogda InfraCity LLP in Jhansi (RERA ID UPRERAPRJ637837). Registered with a completion deadline of 16 Jan 2026.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Jan–Mar 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q2'24
—Q3'24
—Q4'24
—Q1'25
—Q2'25
109%Q3'25
114%Q4'25
118%Q1'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ637837
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryJhansi Development Authority
Proposed start10 Oct 2021
Project duration52 months
AddressJhansi, Jhansi
TehsilJhansi
Applicant typePartnership Firm
Applicant address36, Shivaji Path, Cantt, Sadar Bazaar, Jhansi-284001
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    MAP20191118134858250

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

  6. Completion certificate filed

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered12 Oct 2021
Original completion16 Jan 2026
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary16 Apr 2026
Registration fee₹68,500
Sanctioning authorityJhansi Development Authority

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Jyoti singhal
License CA/93/16250
Space Combine, Safdurjung enclave, New Delhi
Engineer
Sanjay Vithalkar
Space Combine, Safdurjung enclave, New Delhi
Contractor
Bhawandas
Khati baba Jhansi
Sr.Development work declared to RERA
1Demarcation of Plots
All Plots are demarcated as per the layout plan being attached having duplex no A1 to A35 of 1180 sq. ft each and B1 to B31 of 1058 sq. ft each. The plot would be demarcated as per the plot area above mentioned for each block
2Boundary Wall
All plots are covered by separate boundary walls of atleast 1.5 metres. The colony would be having the boundary wall at the boundary of the colony of height of atleast 2.5 metres.
3Road Work
Black top road is being proposed to be laid down in the colony. The roads in front of villas in Block A is of 40 Feets broad whereas road infront of villas in Block B is of 25 Feets broad. The road would be laid out across the colony for the comfort of the residents.
4Footpaths
Paved block with footpath as per approved layout being attached. Footpath would be made across the blocks for the walking residents. The footpath would be of 2 feet wide out side the units .
5Water Supply Including Drinking Water Facilities
Water for general utility and drinking water purpose will be provided by the laid pipeline. The water supply would be provided through the underground water and the water line laid by the government authority. The water supply would be through the pipeline laid from the master tanker to the plot demarcated.
6Sewer System
Sewer system would be made for the cleanliness of the colony. The sewerage plan would be made for the flow of sullage water easily through the sewer system. Proposed Sewer Treatment plant will be installed for the treatment of the sewer.
7Drain
Drain would be constructed in the blocks for the removal of residual waste out of the residency through sewage. The same would be constructed as per service layout approved and attached. The drain would be made under the paved pathway. The plan would be made such a way that the water at the road would be flown down in drain.
8Parks
Park area of 1962.62 sq. mt will be developed as per the approved layout plan. 2 parks would be constructed within the colony. Park would containing temple, meditation centre, badminton court and other facilities for the kids to play games in the colony.
9Tree Planting
132 trees will be planted all over the residency. The trees would be planted for the beauty of the colony. The horticulture department of the company would be planting trees of different heights as per the requirements.
10Design For Electric Supply Including Street Lighting
Electric Pole and separate electricity connection will be taken from concerned electricity department of Jhansi. Electricity department of Jhansi would be the supplier of electricity and the line for electricity would be laid underground.
11Community Buildings
A clubhouse of 100 sq. mt. has been proposed on the first floor of the commercial area as proposed in the layout. The community hall would be constructed at the entrance of the colony.
12Treatment and Disposal System of Sewage and Sullage water
Sewage Treatment Plant has been proposed in the amenities of the colony and the same would be made as per the approved plan. The sullage water would be treated for the further use.
13Solid Waste Management And Disposal System
Solid waste will be collected regularly by the cleaning department of the city i.e. Nagar Palika. Dsutbins would be placed in the colony in order to keep the colony clean. The dustbin will be placed at regular distance for the comfort of residents
14Water Conservation System
Water Harvesting plan has been proposed and the same would be implemented for the water conservation.
15Energy Management System Including Use of Renewable Energy
The residents will follow the Government norms .
16Fire Protection And Fire Safety System
Government norms for the fire safety system would be followed.
17Social Infrastructure And Other Public Amenities Including Public Health Services
As per the approved layout being attached.
18Emergency Evacuation Services
As per the approved layout being attached
19Other Miscellaneous Work
All other amenities, works and services would be performed as per the approved service layout plan being attached.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 16 Jul 2026.

Sanctioned by Jhansi Development Authority · 12,671 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
MAP2019111813485825017 Jul 202116 Jul 202616 Jul 202916 Jan 2026
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
no file published
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published

Land & documents

16 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
557/1 , 558/2 , 561/212671.47Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · 4289
The registered deed by which the promoter bought the land.
PDF ↗
Khatauni extract · 1423-1428
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New18 Sept 2021 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New30 Aug 2021 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New30 Aug 2021 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New30 Aug 2021 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New18 Sept 2021 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New30 Aug 2021 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New30 Aug 2021 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New30 Aug 2021 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New18 Sept 2021 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New30 Aug 2021 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New30 Aug 2021 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New18 Sept 2021 ↗

Quarterly progress reports

18 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

18 quarterly progress reports are on file with UPRERA, covering 2021-Q3 to 2025-Q4.

QuarterConstructionCertificates
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q2109%CA ↗ · Arch ↗ · Eng ↗
2025-Q3114%CA ↗ · Arch ↗ · Eng ↗
2025-Q4118%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2025-Q4. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameYogda InfraCity LLP
RolePromoter · current
RERA IDUPRERAPRM150391
PANAACFY5308F
CIN / TANAGRY10330F
Registered address36, Shivaji Path, Cantt, Sadar Bazaar, Jhansi-284001
RERA contact
Registered since2021
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Jhansi

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
RERA Seperate AccountBankState Bank of IndiaBranchJhansi- Uttar PradeshA/C no.IFSCSBIN0017628
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

2 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Nirmal Residency

Is Nirmal Residency RERA registered?

Yes. Nirmal Residency is registered with UPRERA under registration number UPRERAPRJ637837, registered on 12 Oct 2021. Estanzo reproduces that filing; it does not verify the work behind it.

Has Nirmal Residency been completed?

UPRERA still lists Nirmal Residency as Registered, so it is not shown as completed here. A completion certificate dated 16 Apr 2026 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of Nirmal Residency?

Yogda InfraCity LLP is the promoter entity that filed Nirmal Residency with UPRERA (promoter RERA ID UPRERAPRM150391). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Nirmal Residency have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Nirmal Residency located?

Nirmal Residency is registered in Jhansi, as filed with UPRERA.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗