Page 3 Noida

UPRERARegistered

Page 3 Noida is a RERA-registered residential project by PAGE3 BUILDTECH PRIVATE LIMITED in SECTOR-128, NOIDA, Gautam Budh Nagar (RERA ID UPRERAPRJ819615). Registered with a completion deadline of 27 Feb 2027.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
19.14%Q4'24
30.88%Q1'25
50.27%Q2'25
71.65%Q3'25
82.84%Q4'25
91.07%Q1'26
92.63%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ819615
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryNoida Authority
Proposed start1 Jan 2022
Project duration62 months
AddressB-56, SECTOR-128, NOIDA, Gautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressA2/0701, 7TH Floor, Tower- Aspire- 2, Supertech Emarald Court, Noida Sector 93A Noida Gautam Buddha Nagar UP 201301 IN
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    2021/04/07/4285

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. to

    Extension granted

    “Extension of validity on account of Force Majeure as per MoHUA advisory dated 31-07-2026”

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered28 Jan 2026
Original completion31 Oct 2026
Revised completion27 Feb 2027
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹25,500
Sanctioning authorityNoida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors30 · 1 · 10 (units from plan)
ConfigurationUnitsCarpet area
4 BHK30179-249
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
A · OTHER, 4 BHK1030179-249
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
VISHAL SHARMA
License CA/1998/23261
F-1, FIRST FLOOR, MIRA CORPORATE SUITES, ISHWAR NAGAR, DELHI-110065
Engineer
SADANAND OJHA
503, SACHDEVA CORPORATE TOWER, SECTOR-08, ROHINI, DELHI-110085
Contractor
ANGEL PARK PROMOTERS LLP
SHAKTI KHAN III/50/1 GF, INDIRAPURAM, GHAZIABAD, U.P.-201011I
Sr.Development work declared to RERA
1Demarcation of Plots
Numbers of plots -1, size per plot- 4028 Sqm, total area demarcated; method of demarcation, survey accuracy- As Per Site Plan and Possession Plan
2Boundary Wall
Length- 226 mtr, height- 7mtr+, material used; type (brick, RCC, fencing) - RCC and MS FENCE, apperance- Stonewall, safety features- CCTV and Additional Height of MS Fence
3Road Work
Total road length- 57 mtr and Motorable Green and width- 6 mtr -7.5 mtr, number of lanes- 1 and 2 on the Ramp/Road in Slope; type of pavement- PAVERS, drainage- As per Fire Tender Movement
4Footpaths
Length- 160 mtr, width- 1.35m, number of crossings- None; material used- Stone and Pavers, accessibility- Ramp, safety design- Compilance with Safety Standards
5Water Supply Including Drinking Water Facilities
Number of water connections- 2 (Treatment Water + Domestic), tank capicity- UGT (215 KL including Fire Tank) + Overhead Tank (33 KL including Fire, Flushing and Domestic), hydrants Yard hydrants (5 nos); source of water- Township, treatment method- Township STP will be used for Treatment, compilance with quality standards - YES
6Sewer System
Length of sewer lines- 25 mtr External, pipe size- 250mm dia, manholes- 3; type (gravity/pressure) - Gravity, material used- DWC HDPE Pipes, network design- Piping Design Network connected to External Sewerage System of Township
7Drain
Length- 480 MTR [Storm Drain 280 running meter and Surface Drain 200 running mtr], width- 150mm and 250mm dia pipe in External Storm Drain and Internal 160mm dia, number of open/covered drains- ALL COVERED DRAINS; type (storm/surface)- BOTH - Storm Drain in External Area and Surface Drain in Basement, material- STORM in Brickworks with waterproofing and Surface in RCC with Tiling, disposal method- RWH and Drain Connecting to Township
8Parks
Area- 1102 sqm, number of parks- 3, number of trees/plants- 32; landscaping features- Water Body, Gezebo, Green wall, types od parks- Childrens Park, Celebration lawn, Gazebo Park, public amenities- Swings, Seating Area, Lighting
9Tree Planting
Number of trees- 32, type/species, spacing; native/exotic trees - Mainly Native with a couple of Exotic Trees, maintenance plan- Gardening AMC- (Details As per Landscape Plan)
10Design For Electric Supply Including Street Lighting
Number of poles- 21, lights- 180 approx, tranformer units- 2; type of lighting (LED/solar) - LED, illumination design- Bollard, Street Poles, Uplighter and Wall washer Lights.
11Community Buildings
No- Ground Floor of Tower Area , area per building- 1024 sqm, capicity; purpose- Club/Community Centre and Lift Lobby for Towers, construction type- RCC (Ground floor of Tower Area) , facilities Gymnasium, Cafetaria, Indoor Games, Soft Play Area, Swimming Pool and Health Spa
12Treatment and Disposal System of Sewage and Sullage water
STP capacity (KLD), number of treatment units; type of STP, treated water use, regulatory compilance- WILL BE USING OF TOWNSHIP
13Solid Waste Management And Disposal System
Estimated waste (kg/day) , number of bins/collection points- 30; segregation- Inside Flat, composting/recycling- Encouraging Residents, collection method- Conventional
14Water Conservation System
Number and size of harvesting pits- , recharge wells; water-efficient fixtures, reuse/recharge strategy, system efficiency. - Independent Rainwater collecting System from roofs/terrace/balconies and connecting to Township
15Energy Management System Including Use of Renewable Energy
(Renewable Energy) Solar capacity (kW) , number of pannels; type of renewable energy used, grid integration, backup provision - 1 Percent of TOTAL DEMAND LOAD SHALL BE GENERATED AND FED BY SOLAR PV SYSTEM as per ENVIORNMENT MANDATORY REQUIREMENT
16Fire Protection And Fire Safety System
Number of hydrants - 5 , fire exits- 2 (One in each Tower), sprinklers- Automatic Sprinkler System in Basement; system type (manual/automatic)- AUTOMATIC, NBC compilance- YES, fir safety training - YES
17Social Infrastructure And Other Public Amenities Including Public Health Services
Number/area of amenities- 4 toilets (toilets, health units); type of services offered- TOILET, inclusiveness, accessibility.
18Emergency Evacuation Services
Number of evacuation points- 2, road widths- 6 mtr, signage count; route plan- Escape Route with Emergency Backed up Lighting, safety measures- Hooters, Manual Call Points, Talk Back System with telephone Jacks, public awareness system- Signages, Drills and Regular Updates.
19Other Miscellaneous Work
Work based on the nature of work (e.g., number of CCTV units, benches); beautification efforts, signage, aesthetic and utility elements - CCTV- 40 approx; Benches, Water Body along Front Tower Profile to enhance beauty of Landscape, Aesthetic Lighting, Green wall with Creepers/Climbers to enrich the Boundary wall.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 24 Nov 2026.

Sanctioned by Noida Authority · 4,028 sqm of land · an approved plan of 1 block and 30 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
2021/04/07/428525 Nov 202124 Nov 202623 Nov 202931 Oct 2026
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 27 Feb 2027.

#Granted fromExtended uptoNote
131 Oct 202627 Feb 2027Extension of validity on account of Force Majeure as per MoHUA advisory dated 31-07-2026

Land & documents

16 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
B-56, SECTOR-128, NOIDA4028Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 3658
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 4960
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 968
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New18 Nov 2025 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New13 Oct 2025 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New13 Oct 2025 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New13 Oct 2025 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New13 Oct 2025 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New13 Oct 2025 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New13 Oct 2025 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New13 Oct 2025 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New13 Oct 2025 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New13 Oct 2025 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New13 Oct 2025 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New13 Oct 2025 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New13 Oct 2025 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New13 Oct 2025 ↗

Quarterly progress reports

19 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

19 quarterly progress reports are on file with UPRERA, covering 2021-Q4 to 2026-Q2.

QuarterConstructionCertificates
2021-Q40%CA ↗ · Arch ↗ · Eng ↗
2022-Q10%CA ↗ · Arch ↗ · Eng ↗
2022-Q20%CA ↗ · Arch ↗ · Eng ↗
2022-Q30.34%CA ↗ · Arch ↗ · Eng ↗
2022-Q41.81%CA ↗ · Arch ↗ · Eng ↗
2023-Q15.68%CA ↗ · Arch ↗ · Eng ↗
2023-Q25.83%CA ↗ · Arch ↗ · Eng ↗
2023-Q315.35%CA ↗ · Arch ↗ · Eng ↗
2023-Q419.14%CA ↗ · Arch ↗ · Eng ↗
2024-Q119.14%CA ↗ · Arch ↗ · Eng ↗
2024-Q219.14%CA ↗ · Arch ↗ · Eng ↗
2024-Q319.14%CA ↗ · Arch ↗ · Eng ↗
2024-Q430.88%CA ↗ · Arch ↗ · Eng ↗
2025-Q150.27%CA ↗ · Arch ↗ · Eng ↗
2025-Q271.65%CA ↗ · Arch ↗ · Eng ↗
2025-Q382.84%CA ↗ · Arch ↗ · Eng ↗
2025-Q491.07%CA ↗ · Arch ↗ · Eng ↗
2026-Q192.63%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal namePAGE3 BUILDTECH PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM162275
PANAAJCP2658C
CIN / TANDELP29592D
Name of chairmanRahul Rastogi
Registered addressA2/0701, 7TH Floor, Tower- Aspire- 2, Supertech Emarald Court, Noida Sector 93A Noida Gautam Buddha Nagar UP 201301 IN
RERA contact
Registered since2022
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
PAGE3 BUILDTECH PVT LTD COLLECTION A/C FOR PAGE3 NOIDABankIDFC FIRST BANKBranchNOIDA SECTOR 144Branch addressGROUND FLOOR, UNIT NO.106 & 107, TOWER-A, GULSHAN DYNASTY, PLOT NO. GH-03-D, SECTOR-144, NOIDA G B NAGAR, U.P.Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCIDFB0021336Branch emailnoida.sc144.21336@idfcfirstbank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
PAGE3 BUILDTECH PVT LTD SEPARATE BANK A/C FOR PAGE3 NOIDABankIDFC FIRST BANK LIMITEDBranchNOIDA SECTOR 144Branch addressGROUND FLOOR, UNIT NO. 106, 107, TOWER-A, GULSHAN DYNASTY, PLOT NO. GH-03-D, SECTOR-144, NOIDA, G B NAGAR, U.P.Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCIDFB0021336
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
PAGE3 BUILDTECH PVT LTD RERA TRANSACTION BANK AC PAGE3 NOIDABankIDFC FIRST BANK LIMITEDBranchNOIDA SECTOR 144Branch addressGROUND FLOOR, UNIT NO. 106,107, TOWER-A, GULSHAN DYNASTY, PLOT NO.GH-03-D, SECTOR-144, NOIDA, G B NAGAR, U.P.Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCIDFB0021336
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

20 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
13 Oct 2026
Revised completion date on file2027-02-28 → 2027-02-27
changed in Estanzo’s record
7 Sept 2026
Completion extension
no. 1 — extended upto
2027-02-28 → 2027-02-27
changed in Estanzo’s record
7 Sept 2026
Filed document
viewprojects · 18
Proforma of Agreement for Sale
newly filed with RERA
5 Sept 2026
Filed document
viewprojects · 17
Other
newly filed with RERA
5 Sept 2026
Filed document
viewprojects · 16
ENGINEERS CERTIFICATE
newly filed with RERA
5 Sept 2026
Filed document
viewprojects · 15
ARCHITECT CERTIFICATE
newly filed with RERA
5 Sept 2026
Filed document
viewprojects · 14
CA CERTIFICATE
newly filed with RERA
5 Sept 2026
Filed document
viewprojects · 13
Affidavit (Form-B)
newly filed with RERA
5 Sept 2026
Filed document
viewprojects · 12
Development Work Plan
newly filed with RERA
5 Sept 2026
Filed document
viewprojects · 11
Electricity Supply Plan
newly filed with RERA
5 Sept 2026
Filed document
viewprojects · 10
Water Supply Plan
newly filed with RERA
5 Sept 2026
Filed document
viewprojects · 9
Waste Disposal Plan
newly filed with RERA
5 Sept 2026
Filed document
viewprojects · 8
Proforma of Conveyance Deed
newly filed with RERA
5 Sept 2026
Filed document
viewprojects · 7
Proforma of Allotment Letter
newly filed with RERA
5 Sept 2026
Filed document
viewprojects · 6
Proforma of Application Form
newly filed with RERA
5 Sept 2026
Filed document
viewprojects · 5
Other Plan(If Any)
newly filed with RERA
5 Sept 2026
Filed document
viewprojects · 4
Commencement Certificate
newly filed with RERA
5 Sept 2026
Filed document
viewprojects · 3
Details of Encumbrances
newly filed with RERA
5 Sept 2026
Filed document
viewprojects · 2
Proforma of Completion Certificate(Occupancy)
newly filed with RERA
5 Sept 2026
When these facts last moved
Revised completion date on filechanged in Estanzo’s record · 7 Sept 2026 · 2 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Page 3 Noida

Is Page 3 Noida RERA registered?

Yes. Page 3 Noida is registered with UPRERA under registration number UPRERAPRJ819615, registered on 28 Jan 2026. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Page 3 Noida?

The completion date filed with UPRERA is 27 Feb 2027. No completion certificate is on record yet.

Who is the builder of Page 3 Noida?

PAGE3 BUILDTECH PRIVATE LIMITED is the promoter entity that filed Page 3 Noida with UPRERA (promoter RERA ID UPRERAPRM162275). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Page 3 Noida more time to complete?

UPRERA's record carries 1 completion extension for Page 3 Noida, the latest running to 27 Feb 2027. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Page 3 Noida have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Page 3 Noida located?

Page 3 Noida is registered in SECTOR-128, NOIDA, Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in Page 3 Noida?

The unit plan filed with UPRERA lists OTHER and 4 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Page 3 Noida?

The approved unit plan filed with UPRERA runs from 179 to 249 m² of carpet area (about 1,929 to 2,681 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Page 3 Noida?

The approved unit plan describes 1 block and 30 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Page 3 Noida?

About 30 units per acre: 30 planned units across 1.00 acres (4,028 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗