ORION ONE 32

UPRERARegistered

ORION ONE 32 is a RERA-registered mixed project by WELLGROW INFOTECH PRIVATE LIMITED in Gautam Budh Nagar (RERA ID UPRERAPRJ960554). Registered with a completion deadline of 31 Dec 2026.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
53%Q3'25
65.5%Q4'25
66.47%Q1'26
72.87%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ960554
Project categoryMixed
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryNoida Authority
Proposed start20 Jun 2021
Project duration67 months
AddressGautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressH-340, L-G/F, NEW RAJINDER NAGAR, NEW DELHI- 110060
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Permit revalidated (3)

  2. 9 building permits sanctioned

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Registered with RERA

  5. Permit revalidated (5)

  6. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  7. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered8 Jul 2021
Original completion31 Dec 2026
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹3,12,000
Sanctioning authorityNoida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors193 · 3 · 10 (units from plan)
  • OTHER118 61%
  • 1 BHK75 39%
ConfigurationUnitsCarpet area
OTHER11884-863
1 BHK7548-82
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Tower A · OTHER, 1 BHK68548-163
Tower B · OTHER1058145-333
Tower C · OTHER105084-434
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Atwin
License MCA 2003/31212
F-89 Ground Floor Green Park New Delhi 110016
Engineer
Ramkrishna Dongar Chaudhary
B-1102 Dosti Vihar Kores Road Pokharan Road 1, Varak Nagar Thane
Contractor
Ajay Arora -Director SGN Universal Constructions Company Ltd
R 529 New Rajinder Nagar Shankar Road New Delhi 110060
Sr.Development work declared to RERA
1Demarcation of Plots
Plot boundaries as per given by Noida Authority already demarcated
2Boundary Wall
Combination of brickwork and MS Grill boundary wall of 8 ft. height all around the periphery
3Road Work
Roads will be provided
4Footpaths
Interlock pavers to be used
5Water Supply Including Drinking Water Facilities
The Plot is allotted by Noida Development Authority and drinking water will be supplied by them. Hence NOC for supply of water is not required. Water will be stored in the underground tank. This stored water will be processed in water treatment plant and than it will be stored in tanks.
6Sewer System
Under ground system. Feeder pipeline of UPVC and final discharge through RCC pipes.
7Drain
Storm water will go to harvesting recharge pits. Excess water if any, will be discharge t authority drain.
8Parks
Parks/Green area will be provided in the proposed development. Green area will have facilities of jogging track, parks, Landscapped garden ext. Total area shall be provided as per approval plan, approx 17,819 sqmtr.
9Tree Planting
334 No.s of tree planting will be done.
10Design For Electric Supply Including Street Lighting
HT line shall be taken from NPCL, converted to LT supply with in house transformers and switching system. Street light shall be LED based.
11Community Buildings
NA. IT/ITES Building
12Treatment and Disposal System of Sewage and Sullage water
Raw sewerage will be processed through STP of six hundred capacity. Treated water shall be used for flushing, irrigation and cleaning purpose as much as feasible. Excess treated water shall be discharge in the authority drain.
13Solid Waste Management And Disposal System
Kitchen waste collection will be collected thorough processed in a plant to make manure . Other waste shall be manually handled for disposal.
14Water Conservation System
Harvesting recharge pits shall be used. Treated water shall be used for flushing, irrigation and cleaning purpose as much as feasible.
15Energy Management System Including Use of Renewable Energy
Solar power to be used
16Fire Protection And Fire Safety System
Fire hydrant shall be provided. Fire alarm system, sprinkler, smoke detector and fire extinguisher shall be provided as required.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Retail shops, banking and financial services, utilities etc provided for end users.
18Emergency Evacuation Services
Fire tender route and refuse area shall be provided. Emergency stairs shall be provided as approved by fire department
19Other Miscellaneous Work
Large open spaces upto 70percent . Open land use for hardscape and softscape. Shading devices /projections given on south side to reduce power load to 60 percent.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

9 permits

An approval and the date it runs to - not proof the work matching it was done.

9 sanctioning permits are on record with UPRERA, the latest valid to 6 Jan 2026. 8 of them carry a revalidation, the latest valid to 21 Feb 2029.

Sanctioned by Noida Authority · 40,508 sqm of land · an approved plan of 3 blocks and 193 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
V-8297 Dec 20206 Dec 20256 Dec 203031 Dec 2026—
Noida/CTP/2020/V-829/6877 Dec 20207 Dec 20255 May 203131 Dec 20267 Dec 2020
valid to 5 May 2027
V-8297 Dec 20207 Dec 20255 May 203131 Dec 20267 Dec 2020
valid to 5 May 2027
V-829/6877 Dec 20207 Dec 20255 May 203031 Dec 20267 Dec 2020
valid to 5 May 2027
V-829/6877 Dec 20206 Jan 202621 Feb 202931 Dec 202622 Feb 2024
valid to 21 Feb 2029
as 2023/03/30/8669
V-829/6877 Dec 20206 Jan 202631 Dec 202631 Dec 202622 Feb 2024
valid to 31 Dec 2026
as 2023/03/30/8669
V-829/6877 Dec 20206 Jan 202631 Dec 202631 Dec 202622 Feb 2024
valid to 31 Dec 2026
as 2023/03/30/8669
V-829/6877 Dec 20206 Jan 202615 Jan 202731 Dec 202622 Feb 2024
valid to 15 Jan 2027
as 2003/03/30/8669
V-829/6877 Dec 20206 Jan 202631 Dec 20266 Dec 202522 Feb 2024
valid to 31 Dec 2026
as nil
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

16 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
A-0940508Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 7017
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Lease deed · 1/1419/169-200/7017
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New29 Jun 2021 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New13 Jun 2021 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New13 Jun 2021 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New29 Jun 2021 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New29 Jun 2021 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New29 Jun 2021 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New29 Jun 2021 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New29 Jun 2021 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New29 Jun 2021 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New13 Jun 2021 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New13 Jun 2021 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New13 Jun 2021 ↗

Quarterly progress reports

21 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

21 quarterly progress reports are on file with UPRERA, covering 2021-Q1 to 2026-Q1.

QuarterConstructionCertificates
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q253%CA ↗ · Arch ↗ · Eng ↗
2025-Q365.5%CA ↗ · Arch ↗ · Eng ↗
2025-Q466.47%CA ↗ · Arch ↗ · Eng ↗
2026-Q172.87%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameWELLGROW INFOTECH PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM143035
PANAAACW5772A
CIN / TANU72200DL2005PTC134554
Name of chairmanAJIT SINGH
Registered addressH-340, L-G/F, NEW RAJINDER NAGAR, NEW DELHI- 110060
RERA contact
Registered since2021
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
Wellgrow Infotech Pvt Ltd RERA Collection Account for Orion One 32 Account forBankPunjab and Sind BankBranchIndralok New DelhiBranch address129 Ground Floor Indra LokBranch districtCentral Delhi, DelhiA/C no.IFSCPSIB0021216
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
Wellgrow Infotech Pvt Ltd RERA Project Account for Orion One Thirty TwoBankPunjab and Sind BankBranchInderlok New DelhiBranch address129 Ground Floor Anand Nagar IndarlokBranch districtCentral Delhi, DelhiA/C no.IFSCPSIB0021216
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
Wellgrow Infotech Pvt Ltd RERA Project Account for Orion One 32BankPunjab and Sind BankBranchIndralok New DelhiBranch address129, Ground Floor IndralokBranch districtCentral Delhi, DelhiA/C no.IFSCPSIB0021216
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about ORION ONE 32

Is ORION ONE 32 RERA registered?

Yes. ORION ONE 32 is registered with UPRERA under registration number UPRERAPRJ960554, registered on 8 Jul 2021. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for ORION ONE 32?

The completion date filed with UPRERA is 31 Dec 2026. No completion certificate is on record yet.

Who is the builder of ORION ONE 32?

WELLGROW INFOTECH PRIVATE LIMITED is the promoter entity that filed ORION ONE 32 with UPRERA (promoter RERA ID UPRERAPRM143035). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does ORION ONE 32 have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is ORION ONE 32 located?

ORION ONE 32 is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in ORION ONE 32?

The unit plan filed with UPRERA lists OTHER and 1 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in ORION ONE 32?

The approved unit plan filed with UPRERA runs from 48 to 863 m² of carpet area (about 518 to 9,285 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in ORION ONE 32?

The approved unit plan describes 3 blocks and 193 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is ORION ONE 32?

About 19 units per acre: 193 planned units across 10.01 acres (40,508 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗