Timeline Bar

Registered29 Jan 2022
Promised31 Dec 2024
Completed29 May 2026

Timeline

Promised completion31 Dec 2024
Revised completion31 Dec 2024
Actual completion29 May 2026
Possession delay17 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,80,500
Project cost (in ₹ Lakhs)₹1,325 Lakhs
Project duration36 months
Project categoryResidential
Locality
Original start date
Proposed start date10 Jan 2022

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile8449715510
Emailparasenclaveasj@gmail.com
Coordinator9632529441
AddressD-8 LAXMINAGAR,NEW DELHI

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
18/202130 Sept 202130 Sept 202631 Dec 202430 Sept 2029

Land Parcels

Khasra No.AreaPlot Type
217190Khasra
21419124Khasra
2147571Khasra
2148202Khasra

Frequently Asked Questions

What is the RERA registration number of PARAS ENCLAVE PHASE 1?

The RERA registration number of PARAS ENCLAVE PHASE 1 is UPRERAPRJ109607, as recorded on the UP-RERA portal.

What is the RERA status of PARAS ENCLAVE PHASE 1?

As reported by UP-RERA, the status of PARAS ENCLAVE PHASE 1 is "Registered".

Where is PARAS ENCLAVE PHASE 1 located?

As reported to UP-RERA, PARAS ENCLAVE PHASE 1 is located at Muzaffarnagar, Muzaffarnagar, Uttar Pradesh.

Is PARAS ENCLAVE PHASE 1 completed?

As reported to UP-RERA, PARAS ENCLAVE PHASE 1 was completed on 29 May 2026.

Is PARAS ENCLAVE PHASE 1 delayed?

Measured against the latest completion date reported to UP-RERA, PARAS ENCLAVE PHASE 1 is 17 months beyond that date.