Timeline Bar
Registered5 Dec 2023
Today4 Aug 2026
Promised4 Aug 2028
Timeline
Promised completion4 Aug 2028
Revised completion4 Aug 2028
Actual completion—
Possession delayOn time
Registration & Cost Details
Registration fee (in ₹)₹56,000
Project cost (in ₹ Lakhs)₹783 Lakhs
Project duration61 months
Project categoryResidential
Locality—
Original start date—
Proposed start date4 Aug 2023
Inventory
Total units—
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile9889222226
Emailavinash9889222226@gmail.com
Coordinator9889222229
Address3/191, Vipul Khand, Gomti Nagar Lucknow Lucknow UP 226010 IN
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| Plotted Resi development / Plotted Housing/01311/VDA/LD/22-23/0047/19042022 | 5 Aug 2023 | 4 Aug 2028 | 4 Aug 2028 | 4 Aug 2031 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 832 | 9750 | Khasra |
| 830mi | 530 | Khasra |
Frequently Asked Questions
What is the RERA registration number of RUDRAKSH PARADISE?
The RERA registration number of RUDRAKSH PARADISE is UPRERAPRJ625587, as recorded on the UP-RERA portal.
What is the RERA status of RUDRAKSH PARADISE?
As reported by UP-RERA, the status of RUDRAKSH PARADISE is "Registered".
Where is RUDRAKSH PARADISE located?
As reported to UP-RERA, RUDRAKSH PARADISE is located at Pindra **, Varanasi, Uttar Pradesh.
When will RUDRAKSH PARADISE be completed?
The latest completion date reported to UP-RERA for RUDRAKSH PARADISE is 4 Aug 2028.
Is RUDRAKSH PARADISE delayed?
Measured against the latest completion date reported to UP-RERA, RUDRAKSH PARADISE is on time.