Estanzo

Timeline Bar

Registered10 Aug 2017
Promised30 Sept 2021
Today3 Aug 2026

Timeline

Promised completion30 Sept 2021
Revised completion30 Sept 2021
Actual completion
Possession delay58 mo delay

Registration & Cost Details

Registration fee (in ₹)₹46,000
Project cost (in ₹ Lakhs)₹5,918 Lakhs
Project duration109 months
Project categoryResidential
Locality
Original start date10 Dec 2010
Proposed start date16 Mar 2013

Inventory

Total units108
Unit TypeUnitsCarpet Area (sqm)
2 BHK6678.416–100.944
3 BHK37118.45–152.88
4 BHK5170.297–223.91

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9810658227
Emailsushantaquapolisrera@gmail.com
Coordinator9560377433
Address115, Ansal Bhawan, 16, KG Marg, New Delhi - 110001

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
487/ZONE5/GH/201628 Mar 201727 Mar 202230 Sept 202127 Mar 2025

Land Parcels

Khasra No.AreaPlot Type
10433261Khasra
17041715.3Khasra
17031225.20Khasra
1658735.10Khasra
1264490.1Khasra
1265735.30Khasra

Approved Unit Plan

Unit plan rows on file94
Total flats (sum of rows)108
BlocksB2A, D01
Floor types2 BHK, 3 BHK, 4 BHK

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of SUSHANT AQUAPOLIS, GROUP HOUSING, PHASE-2 (D1, B2A?

The RERA registration number of SUSHANT AQUAPOLIS, GROUP HOUSING, PHASE-2 (D1, B2A is UPRERAPRJ5465, as recorded on the UP-RERA portal.

What is the RERA status of SUSHANT AQUAPOLIS, GROUP HOUSING, PHASE-2 (D1, B2A?

As reported by UP-RERA, the status of SUSHANT AQUAPOLIS, GROUP HOUSING, PHASE-2 (D1, B2A is "Registered".

Where is SUSHANT AQUAPOLIS, GROUP HOUSING, PHASE-2 (D1, B2A located?

As reported to UP-RERA, SUSHANT AQUAPOLIS, GROUP HOUSING, PHASE-2 (D1, B2A is located at Ghaziabad, Ghaziabad, Uttar Pradesh.

When will SUSHANT AQUAPOLIS, GROUP HOUSING, PHASE-2 (D1, B2A be completed?

The latest completion date reported to UP-RERA for SUSHANT AQUAPOLIS, GROUP HOUSING, PHASE-2 (D1, B2A is 30 Sept 2021.

Is SUSHANT AQUAPOLIS, GROUP HOUSING, PHASE-2 (D1, B2A delayed?

Measured against the latest completion date reported to UP-RERA, SUSHANT AQUAPOLIS, GROUP HOUSING, PHASE-2 (D1, B2A is 58 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026