Taj Heights is a RERA-registered residential project by Maliha Realtors.Pvt. Ltd. in Ghaziabad (RERA ID UPRERAPRJ6272). RERA status: Abeyance.
RERA status as reported: Abeyance.Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ6272 |
| Project category | Residential |
| Registration type | Ongoing |
| RERA status | AbeyanceAbeyance“Held in suspension.” UP-RERA lists projects whose registration it has placed in abeyance.Read the full entry in the glossary |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Ghaziabad Development Authority |
| Proposed start | 1 Dec 2015 |
| Original start | 1 Dec 2015 |
| Project duration | 76 months |
| Address | Ghaziabad, Ghaziabad |
| Tehsil | Ghaziabad |
| Applicant type | Company |
| Applicant address | 676, Chitla Gate Chawari Bazar, Delhi |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Registered with RERA
- to
Extension granted
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
- to
Extension granted
“Six months extension in view of force majeure caused by covid-19 pandemic”
- to
Extension granted
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 13 Oct 2017 |
| Original completion | 31 Dec 2019 |
| Revised completion | 28 Mar 2022 |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹74,500 |
| Sanctioning authority | Ghaziabad Development Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
- 2 BHK112 51%
- 3 BHK108 49%
| Configuration | Units | Carpet area |
|---|---|---|
| 3 BHK | 108 | 84-112 |
| 2 BHK | 112 | 58-70 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| A1 & A2 · 2 BHK | 1 | 56 | 58 |
| B1 & B2 · 2 BHK | 1 | 56 | 70 |
| B3 & B4 · 3 BHK | 1 | 56 | 84 |
| C1 · 3 BHK | 1 | 16 | 112 |
| C2 · 3 BHK | 1 | 36 | 108 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots yes |
| 2 | Boundary Wall yes |
| 3 | Road Work yes |
| 4 | Footpaths yes |
| 5 | Water Supply Including Drinking Water Facilities yes |
| 6 | Sewer System yes |
| 7 | Drain yes |
| 8 | Parks yes |
| 9 | Tree Planting yes |
| 10 | Design For Electric Supply Including Street Lighting yes |
| 11 | Community Buildings yes |
| 12 | Treatment and Disposal System of Sewage and Sullage water yes |
| 13 | Solid Waste Management And Disposal System yes |
| 14 | Water Conservation System yes |
| 15 | Energy Management System Including Use of Renewable Energy yes |
| 16 | Fire Protection And Fire Safety System yes |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services proposed stp |
| 18 | Emergency Evacuation Services yes |
| 19 | Other Miscellaneous Work yes |
Permits & extensions
0 permits
An approval and the date it runs to - not proof the work matching it was done.
Sanctioned by Ghaziabad Development Authority · 13,826 sqm of land · an approved plan of 5 blocks and 220 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Document | File |
|---|---|
| Project approval The approval the promoter filed as the basis for registering the project. | PDF ↗ |
| Sanctioned layout plan The approved layout of the whole site: where the towers, roads and open areas sit on the plot. | PDF ↗ |
UPRERA’s record carries 3 completion extensions for this project, the latest running to 28 Mar 2022.
| # | Granted from | Extended upto | Note |
|---|---|---|---|
| 1 | 31 Dec 2019 | 30 Dec 2020 | — |
| 2 | 30 Dec 2020 | 29 Jun 2021 | Six months extension in view of force majeure caused by covid-19 pandemic |
| 3 | 29 Jun 2021 | 28 Mar 2022 | — |
Land & documents
11 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 61 | 6670.84 | — |
| 70 | 9484.68 | — |
| 72 | 2883.30 | — |
| 74 | 1770.44 | — |
| 61 | 6670.84 | Khasra |
| 70 | 9484.68 | Khasra |
| 72 | 2883.30 | Khasra |
| 74 | 1770.44 | Khasra |
1 registry or lease-deed filing is on this project’s record with UPRERA, dated 28 Oct 2013.
| Registry no. | Date | Type | Area |
|---|---|---|---|
| 1115 | 28 Oct 2013 | other | — |
| Sale deed · 600641 The registered deed by which the promoter bought the land. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Agreement for other land The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title. | Old | 29 Jan 2018 ↗ |
| Agreement for other land The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title. | Old | 29 Jan 2018 ↗ |
| Agreement for other land The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title. | Old | 29 Jan 2018 ↗ |
Facilities
as declared to RERA
Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.
| Drinking water | yes |
| Fire safety (as filed with RERA) | yes |
| Health service | proposed stp |
| Renewable energy | yes |
| Other facilities | park |
The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.
Quarterly progress reports
2 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
2 quarterly progress reports are on file with UPRERA, covering 2021-Q3 to 2021-Q4.
| Quarter | Construction | Certificates |
|---|---|---|
| 2021-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | Maliha Realtors.Pvt. Ltd. |
| Role | Promoter · current |
| RERA ID | UPRERAPRM11912 |
| PAN | AAFCM5934K |
| CIN / TAN | U70109DL2008PTC178745 |
| Name of chairman | ABDUL SAMI |
| Registered address | 676, Chitla Gate Chawari Bazar, Delhi |
| RERA contact | |
| Registered since | 2017 |
Nearby projects
Ghaziabad
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | MALIHA REALTORS PVT. LTD.BankAxis Bank Ltd.BranchKARKARDOOMAA/C no.IFSCUTIB0000372 |
What has changed on this record
nothing recorded yet
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.What to verify and what to ask
1 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No sanctioning permit is published for this project.Ask which authority sanctioned the plans, for the permit number, and for the date it is valid to.
Common questions about Taj Heights
Is Taj Heights RERA registered?
Yes. Taj Heights is registered with UPRERA under registration number UPRERAPRJ6272, registered on 13 Oct 2017. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for Taj Heights?
The completion date filed with UPRERA is 28 Mar 2022. No completion certificate is on record yet.
Who is the builder of Taj Heights?
Maliha Realtors.Pvt. Ltd. is the promoter entity that filed Taj Heights with UPRERA (promoter RERA ID UPRERAPRM11912). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Has UPRERA granted Taj Heights more time to complete?
UPRERA's record carries 3 completion extensions for Taj Heights, the latest running to 28 Mar 2022. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.
Does Taj Heights have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is Taj Heights located?
Taj Heights is registered in Ghaziabad, as filed with UPRERA.
What configurations are available in Taj Heights?
The unit plan filed with UPRERA lists 3 BHK and 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in Taj Heights?
The approved unit plan filed with UPRERA runs from 58 to 112 m² of carpet area (about 619 to 1,208 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in Taj Heights?
The approved unit plan describes 5 blocks and 220 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is Taj Heights?
About 64 units per acre: 220 planned units across 3.42 acres (13,826 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗