Construction of 226 Nos Different Types Of Semifinished Houses in Sector-5A Mandola Vihar Yojna Ghaziabad
Construction of 226 Nos Different Types Of Semifinished Houses in Sector-5A Mandola Vihar Yojna Ghaziabad is a RERA-registered residential project by U.P. Awas Evam Vikas Parishad in 5A, Ghaziabad (RERA ID UPRERAPRJ166089). Registered with a completion deadline of 30 Sept 2029.
RERA status as reported: Registered.Construction progress
Construction stayed at 0% across 5 consecutive filed quarters (Apr–Jun 2025 to Apr–Jun 2026). The promoter filed the same figure each time. Quarters with no percentage filed are not counted either way.
Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ166089 |
| Project category | Residential |
| Registration type | New |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | U.P. Awas Evam Vikas Parishad |
| Proposed start | 1 Feb 2025 |
| Project duration | 56 months |
| Address | Mandola Vihar Yojna Ghaziabad, 5A, Ghaziabad, Ghaziabad |
| Tehsil | Ghaziabad |
| Applicant type | Competent authority |
| Applicant address | 104 Mahatma Gandhi Marg, Lucknow |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Building permit sanctioned
3394/YN-5/Baghpat/S-5/92
Registered with RERA
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 28 Oct 2024 |
| Original completion | 30 Sept 2029 |
| Revised completion | — none granted |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹2,11,500 |
| Sanctioning authority | U.P. Awas Evam Vikas Parishad |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots As per Approved Layout Plan |
| 2 | Boundary Wall No Provision of Boundary Wall in the Sector |
| 3 | Road Work Bituminous Trunk Roads are already constructed in Mandola Vihar Yojna. Internal Roads of 9m and 12m are proposed which will be constructed by UPAVP as per parishad specification |
| 4 | Footpaths As per Roads Specification of UPAVP |
| 5 | Water Supply Including Drinking Water Facilities Internal Water Supply Line of PVC pipe of 100mm dia will be laid as per design approved by the competent authority of UPAVP. Water Supply will be given by Over Head Tank already constructed by Parishad. |
| 6 | Sewer System Internal Sewer Line of 250mm Dia RCC NP2 and NP3 Pipe will laid as per Design Approved by the Competent Authority of UPAVP. |
| 7 | Drain Internal Storm Water Drain of CK and C type will be provided as per design approved by the competent authority of UPAVP. |
| 8 | Parks Open/Green will be provided as per approved layout |
| 9 | Tree Planting Different type of plants will be planted in parks and other areas as per UPAVP Specification |
| 10 | Design For Electric Supply Including Street Lighting Electrification work and street light work will be done by UPAVP as per design and drawing approved by the competent authority of UPAVP. Electricity Supply Line will be Handed Over to UP Power Corporation after Completing and testing of line |
| 11 | Community Buildings No Provision of Community Building |
| 12 | Treatment and Disposal System of Sewage and Sullage water Treatment of Sewage will be done by proposed STP to be constructed in sector 3 Mandola Vihar Yojna Ghaziabad. |
| 13 | Solid Waste Management And Disposal System Parishad Vehicles will collect the solid waste and transfer to the disposal center |
| 14 | Water Conservation System N/A |
| 15 | Energy Management System Including Use of Renewable Energy N/A |
| 16 | Fire Protection And Fire Safety System N/A |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services N/A |
| 18 | Emergency Evacuation Services N/A |
| 19 | Other Miscellaneous Work N/A |
Permits & extensions
1 permit
An approval and the date it runs to - not proof the work matching it was done.
1 sanctioning permit is on record with UPRERA, valid to 3 Oct 2029.
Sanctioned by U.P. Awas Evam Vikas Parishad · 41,276 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| 3394/YN-5/Baghpat/S-5/92 | 7 Oct 2024 | 3 Oct 2029 | 2 Oct 2031 | 30 Sept 2029 |
| Document | File |
|---|---|
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
Land & documents
56 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 115 | 6260 | Khasra |
| 117P | 3080 | Khasra |
| 119P | 3010 | Khasra |
| 112 | 5390 | Khasra |
| 110 | 0890 | Khasra |
| 109 | 14130 | Khasra |
| 111 | 2730 | Khasra |
| 108P | 2730 | Khasra |
| 94P | 3450 | Khasra |
| 95P | 2240 | Khasra |
| 96P | 3690 | Khasra |
| 92P | 2800 | Khasra |
| 97P | 3240 | Khasra |
| 100P | 6420 | Khasra |
| 101P | 5710 | Khasra |
| 1033 | 6230 | Khasra |
| 1053 | 6210 | Khasra |
| 1052 | 5190 | Khasra |
| 1054 | 3320 | Khasra |
| 1050 | 2780 | Khasra |
| 1049 | 3040 | Khasra |
| 1046P | 3410 | Khasra |
| 1045P | 4040 | Khasra |
| 1044 | 4680 | Khasra |
| 1042 | 5190 | Khasra |
| 1041 | 2400 | Khasra |
| 1028 | 3290 | Khasra |
| 1037 | 1640 | Khasra |
| 1036 | 2780 | Khasra |
| 1034 | 1930 | Khasra |
| 1040 | 2780 | Khasra |
| 1039 | 2400 | Khasra |
| 1051 | 2020 | Khasra |
| 1043 | 1770 | Khasra |
| 106P | 3070 | Khasra |
| 116P | 8240 | Khasra |
| 1047P | 5477 | Khasra |
| 1038 | 1390 | Khasra |
| Khatauni extract · 1427-1432 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1426-1431 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1426-1431 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1426-1431 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1426-1431 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1426-1431 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | not reported | — |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | not reported | — |
| Other A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is. | not reported | — |
| Agreement for sale (proforma) The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind. | not reported | — |
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | New | 4 Oct 2024 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 12 Sept 2024 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 12 Sept 2024 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | New | 12 Sept 2024 ↗ |
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | New | 12 Sept 2024 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 12 Sept 2024 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 12 Sept 2024 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 12 Sept 2024 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 12 Sept 2024 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 8 Oct 2024 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 8 Oct 2024 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 12 Sept 2024 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 12 Sept 2024 ↗ |
| Agreement for sale (proforma) The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind. | New | 4 Oct 2024 ↗ |
Quarterly progress reports
6 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
6 quarterly progress reports are on file with UPRERA, covering 2024-Q4 to 2026-Q1.
| Quarter | Construction | Certificates |
|---|---|---|
| 2024-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q1 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q2 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q3 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q4 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2026-Q1 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | U.P. Awas Evam Vikas Parishad |
| Role | Promoter · current |
| RERA ID | UPRERAPRM4243 |
| PAN | AAAJU0103A |
| CIN / TAN | LKNU05017F |
| Registered address | 104 Mahatma Gandhi Marg, Lucknow |
| RERA contact | |
| Registered since | 2017 |
Nearby projects
Ghaziabad
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary | UPAVP-Collection Account for 226 No. Different Type Single Story Semi-finished Houses in sector-5A of Mandola Vihar Yojna, Ghaziabad.BankPunjab National BankBranchKaushambiBranch addressK.M Trade Tower Kaushambi, Near Hotel Radisson Hotel GhaziabadBranch districtGhaziabad, Uttar PradeshA/C no.IFSCPUNB0300000Branch emailbo3000@pnb.co.in |
| SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary | UPAVP-Separate Account for 226 No. Different Type Single Story Semi-finished Houses in sector-5A of Mandola Vihar Yojna, GhaziabadBankPunjab National BankBranchKaushambi GhaziabadBranch addressK.M Trade Tower Kaushambi Near Hotel Radisson Blue GhaziabadBranch districtGhaziabad, Uttar PradeshA/C no.IFSCPUNB0300000 |
| TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary | UPAVP-Transaction Account for 226 No. Different Type Single Story Semi-finished Houses in sector-5A of Mandola Vihar Yojna GhaziabadBankPunjab National BankBranchKaushambi GhaziabadBranch addressK.M Trade Tower Kaushambi Near Hotel Radission Blue, GhaziabadBranch districtGhaziabad, Uttar PradeshA/C no.IFSCPUNB0300000 |
What has changed on this record
14 movements
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026.
| Field | What moved | Observed |
|---|---|---|
| Promoter’s complaints tally (all their projects) | 761 (Under Registration - 10 ) → 762 (Under Registration - 11 ) changed in Estanzo’s record | 19 Oct 2026 |
| Promoter’s complaints tally (all their projects) | 760 (Under Registration - 9 ) → 761 (Under Registration - 10 ) changed in Estanzo’s record | 18 Oct 2026 |
| Promoter’s complaints tally (all their projects) | 759 (Under Registration - 8 ) → 760 (Under Registration - 9 ) changed in Estanzo’s record | 15 Oct 2026 |
| Promoter’s complaints tally (all their projects) | 758 (Under Registration - 7 ) → 759 (Under Registration - 8 ) changed in Estanzo’s record | 13 Oct 2026 |
| Promoter’s complaints tally (all their projects) | 757 (Under Registration - 6 ) → 758 (Under Registration - 7 ) changed in Estanzo’s record | 9 Oct 2026 |
| Promoter’s complaints tally (all their projects) | 755 (Under Registration - 4 ) → 757 (Under Registration - 6 ) changed in Estanzo’s record | 7 Oct 2026 |
| Promoter’s complaints tally (all their projects) | 753 (Under Registration - 2 ) → 755 (Under Registration - 4 ) changed in Estanzo’s record | 5 Oct 2026 |
| Promoter’s complaints tally (all their projects) | 753 (Under Registration - 6 ) → 753 (Under Registration - 2 ) changed in Estanzo’s record | 1 Oct 2026 |
| Promoter’s complaints tally (all their projects) | 752 (Under Registration - 5 ) → 753 (Under Registration - 6 ) changed in Estanzo’s record | 29 Sept 2026 |
| Promoter’s complaints tally (all their projects) | 751 (Under Registration - 4 ) → 752 (Under Registration - 5 ) changed in Estanzo’s record | 25 Sept 2026 |
| Promoter’s complaints tally (all their projects) | 750 (Under Registration - 3 ) → 751 (Under Registration - 4 ) changed in Estanzo’s record | 17 Sept 2026 |
| Promoter’s complaints tally (all their projects) | 748 (Under Registration - 1 ) → 750 (Under Registration - 3 ) changed in Estanzo’s record | 3 Sept 2026 |
| Promoter’s complaints tally (all their projects) | 747 (Under Registration - 0 ) → 748 (Under Registration - 1 ) changed in Estanzo’s record | 1 Sept 2026 |
| Promoter’s complaints tally (all their projects) | 746 (Under Registration - 2 ) → 747 (Under Registration - 0 ) changed in Estanzo’s record | 23 Aug 2026 |
| Promoter’s complaints tally (all their projects) | changed in Estanzo’s record · 19 Oct 2026 · 14 movements on record |
What to verify and what to ask
2 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
- No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.
Common questions about Construction of 226 Nos Different Types Of Semifinished Houses in Sector-5A Mandola Vihar Yojna Ghaziabad
Is Construction of 226 Nos Different Types Of Semifinished Houses in Sector-5A Mandola Vihar Yojna Ghaziabad RERA registered?
Yes. Construction of 226 Nos Different Types Of Semifinished Houses in Sector-5A Mandola Vihar Yojna Ghaziabad is registered with UPRERA under registration number UPRERAPRJ166089, registered on 28 Oct 2024. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for Construction of 226 Nos Different Types Of Semifinished Houses in Sector-5A Mandola Vihar Yojna Ghaziabad?
The completion date filed with UPRERA is 30 Sept 2029. No completion certificate is on record yet.
Who is the builder of Construction of 226 Nos Different Types Of Semifinished Houses in Sector-5A Mandola Vihar Yojna Ghaziabad?
U.P. Awas Evam Vikas Parishad is the promoter entity that filed Construction of 226 Nos Different Types Of Semifinished Houses in Sector-5A Mandola Vihar Yojna Ghaziabad with UPRERA (promoter RERA ID UPRERAPRM4243). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Does Construction of 226 Nos Different Types Of Semifinished Houses in Sector-5A Mandola Vihar Yojna Ghaziabad have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is Construction of 226 Nos Different Types Of Semifinished Houses in Sector-5A Mandola Vihar Yojna Ghaziabad located?
Construction of 226 Nos Different Types Of Semifinished Houses in Sector-5A Mandola Vihar Yojna Ghaziabad is registered in 5A, Ghaziabad, as filed with UPRERA.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗