Timeline Bar

Registered15 Jul 2022
Today4 Aug 2026
Promised5 Jun 2029

Timeline

Promised completion5 Jun 2029
Revised completion5 Jun 2029
Actual completion
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹1,05,000
Project cost (in ₹ Lakhs)₹19,500 Lakhs
Project duration84 months
Project categoryResidential
Locality
Original start date
Proposed start date7 Jun 2022

Inventory

Total units417
Unit TypeUnitsCarpet Area (sqm)
1 BHK144.779
2 BHK4846.581–53.849
3 BHK24059.885–81.828
4 BHK9598.819
SHOP339.61–32.49

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9810663363
Emailaccounts@fusionbuildtech.com
Coordinator8527561116
AddressA-6, Ground Floor, Yojana Vihar, Delhi-110092

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q297.0%
2025-Q388.0%
2025-Q488.0%
2026-Q189.0%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
PLG/BP SM-01-NOV-2021 125576 Jun 20225 Jun 20275 Jun 20295 Jun 2029

Land Parcels

Khasra No.AreaPlot Type
GH-03C, Sector-12, Greater Noida West20000Plot

Approved Unit Plan

Unit plan rows on file173
Total flats (sum of rows)417
Total shops33
BlocksA, B, Brook Arcade, C
Floor types1 BHK, 2 BHK, 3 BHK, 4 BHK, SHOP

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of The Brook- Phase 1?

The RERA registration number of The Brook- Phase 1 is UPRERAPRJ228846, as recorded on the UP-RERA portal.

What is the RERA status of The Brook- Phase 1?

As reported by UP-RERA, the status of The Brook- Phase 1 is "Registered".

Where is The Brook- Phase 1 located?

As reported to UP-RERA, The Brook- Phase 1 is located at Dadri, Gautam Budh Nagar, Uttar Pradesh.

When will The Brook- Phase 1 be completed?

The latest completion date reported to UP-RERA for The Brook- Phase 1 is 5 Jun 2029.

Is The Brook- Phase 1 delayed?

Measured against the latest completion date reported to UP-RERA, The Brook- Phase 1 is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026