The Rivulet Phase-1

UPRERARegistered

The Rivulet Phase-1 is a RERA-registered residential project by Grand Realtech Limited in Gautam Budh Nagar (RERA ID UPRERAPRJ145736). Registered with a completion deadline of 3 Apr 2030.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
63%Q3'25
63%Q4'25
69%Q1'26
74%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ145736
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGreater Noida Authority
Proposed start1 May 2023
Project duration84 months
AddressDadri, Gautam Budh Nagar
TehsilDadri
Applicant typeCompany
Applicant addressA-6, Ground Floor, Yojana Vihar, Delhi-110092
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    SM-27-Sep-2022/15677

  2. Registered with RERA

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered25 Apr 2023
Original completion3 Apr 2030
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹1,55,000
Sanctioning authorityGreater Noida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors847 · 7 · 25 (units from plan)
Homes · commercial units816 · 31 (shops and offices filed in the same plan)
  • 3 BHK716 85%
  • 4 BHK95 11%
  • SHOP31 4%
  • 2 BHK5 1%
ConfigurationUnitsCarpet area
4 BHK9599
3 BHK71665-82
2 BHK549
SHOP3117-58
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
K · 3 BHK, 2 BHK2414449-77
L · 3 BHK, 2 BHK2414449-77
M · 4 BHK, 3 BHK249682-99
Rivulet Plaza · SHOP13117-58
S · 3 BHK, 2 BHK2414449-77
T · 3 BHK, 2 BHK2414449-77
U · 3 BHK, 2 BHK2414449-77
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Anand Sharma- Design Forum International
License CA/95/17838
K-47, Kailash colony, New Delhi
Engineer
Syed Tajuddin Ashraf
H-53, First Floor, Sector-63, Noida
Contractor
Kamal And Associates Pvt Ltd
Plot No.1, 3rd Floor, LSC Market Mayur Vihar-II, Delhi
Sr.Development work declared to RERA
1Demarcation of Plots
The project is demarcated with two roads each of 24 mtr running along south west side and south east side of the plot. On the North East side the project shares its boundary with plot 4A and on the north west side the project shares its boundary with plot No. 3C plot No. 3B.
2Boundary Wall
The Boundary wall will consist of brickwork upto a height of 5 ft. with iron grill on top
3Road Work
The project will consist of 8mtr wide roads to facilitate vehicle and pedastrian movement
4Footpaths
The project will have footpaths for pedestrians running along the towers
5Water Supply Including Drinking Water Facilities
The Drinking water will be supplied by Greater Noida Industrial Development Authority
6Sewer System
The project will have its own sewage treatment plan installed withn the premises
7Drain
The sewage water (after treatment by STP) will flow in the main drain provided by GNIDA
8Parks
The project will have a central park having a fragrance garden and other decorative and aesthetic plants
9Tree Planting
The project will be having trees to comply with the norms of GNIDA
10Design For Electric Supply Including Street Lighting
The company will draw its electricity from the Grid provided by UPPCL or NPCl. The company will install solar lights to make the project energy efficient
11Community Buildings
The project will have a community hall, club, gymnasium, swimming pool, et.
12Treatment and Disposal System of Sewage and Sullage water
The project will have its own sewage treatment plan within the premises
13Solid Waste Management And Disposal System
The solid waste will be disposed through stp and dried blocks will be disposed through municipality trucks by GNIDA
14Water Conservation System
The company will be using rain water harvesting to meet its common area water requirements
15Energy Management System Including Use of Renewable Energy
The project will be having energy efficient LED at all common facilities and areas including parking and club
16Fire Protection And Fire Safety System
The Company will be having Fire Fighting system in place and Fire NOC is already taken
17Social Infrastructure And Other Public Amenities Including Public Health Services
The company will be having club with Gymnasium and swimming pool alongwith dedicated space for Yoga
18Emergency Evacuation Services
The company will be having staircase and fire doors with emergency exits marked within the project
19Other Miscellaneous Work
As per Building sanction plans
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

6 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1360 DEGREE VENTURES PRIVATE LIMITEDUPRERAAGT18728
2BULLMEN REALTY INDIA PRIVATE LIMITEDUPRERAAGT10138
3INVESTOR HOMEZUPRERAAGT15046
4INVESTORS CLINIC INFRATECH PRIVATE LIMITEDUPRERAAGT10052
5PROP- KEYS CONSULTING PRIVATE LIMITEDUPRERAAGT23188
6WEALTH CLINIC PRIVATE LIMITEDUPRERAAGT10521
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 2 Feb 2028.

Sanctioned by Greater Noida Authority · 30,000 sqm of land · an approved plan of 7 blocks and 847 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
SM-27-Sep-2022/156773 Feb 20232 Feb 20283 Apr 20303 Apr 2030
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

17 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
GH-04B30000Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · I-10911
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Water supply plan
How the project proposed to supply water, as filed at registration.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New21 Apr 2023 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New8 Apr 2023 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New10 Apr 2023 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New19 Apr 2023 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New8 Apr 2023 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New8 Apr 2023 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New19 Apr 2023 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New8 Apr 2023 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New8 Apr 2023 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New19 Apr 2023 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New19 Apr 2023 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New19 Apr 2023 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New19 Apr 2023 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New8 Apr 2023 ↗

Quarterly progress reports

13 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

13 quarterly progress reports are on file with UPRERA, covering 2023-Q1 to 2026-Q1.

QuarterConstructionCertificates
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q263%CA ↗ · Arch ↗ · Eng ↗
2025-Q363%CA ↗ · Arch ↗ · Eng ↗
2025-Q469%CA ↗ · Arch ↗ · Eng ↗
2026-Q174%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameGrand Realtech Limited
RolePromoter · current
RERA IDUPRERAPRM229118
PANAAFCG1435P
CIN / TANU70102HR2013PTC048894
Name of chairmanBrijesh Kumar
Registered addressA-6, Ground Floor, Yojana Vihar, Delhi-110092
RERA contact
Registered since2023
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
Grand Realtech Ltd Rera Collection Account for The Rivulet Phase-1BankICICI BankBranchCherry County, Greater Noida WestBranch addressShop No. 9A-9B, GH-05B, Techzone-4, Greater Noida WestBranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCICIC0004146
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
Grand Realtech Limited Rera Seperate Account for The Rivulet Phase-1BankICICI Bank LtdBranchCherry County Greater Noida WestBranch addressShop No 9A-9B, GH-05B, Techzone-4, Greater Noida WestBranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCICIC0004146
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
Grand Realtech Ltd Rera Transaction Account For The Rivulet Phase-1BankICICI Bank LtdBranchCherry County Greater Noida WestBranch addressShop No. 9A-9B, GH-05B, Techzone-4, Greater Noida WestBranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCICIC0004146
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about The Rivulet Phase-1

Is The Rivulet Phase-1 RERA registered?

Yes. The Rivulet Phase-1 is registered with UPRERA under registration number UPRERAPRJ145736, registered on 25 Apr 2023. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for The Rivulet Phase-1?

The completion date filed with UPRERA is 3 Apr 2030. No completion certificate is on record yet.

Who is the builder of The Rivulet Phase-1?

Grand Realtech Limited is the promoter entity that filed The Rivulet Phase-1 with UPRERA (promoter RERA ID UPRERAPRM229118). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does The Rivulet Phase-1 have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is The Rivulet Phase-1 located?

The Rivulet Phase-1 is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in The Rivulet Phase-1?

The unit plan filed with UPRERA lists 4 BHK, 3 BHK, 2 BHK and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in The Rivulet Phase-1?

The approved unit plan filed with UPRERA runs from 17 to 99 m² of carpet area (about 181 to 1,064 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in The Rivulet Phase-1?

The approved unit plan describes 7 blocks and 847 units of which 816 are homes and 31 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is The Rivulet Phase-1?

About 114 units per acre: 847 planned units across 7.41 acres (30,000 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗