Estanzo

Timeline Bar

Registered17 Apr 2024
Today3 Aug 2026
Promised15 Feb 2029

Timeline

Promised completion15 Feb 2029
Revised completion15 Feb 2029
Actual completion
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹1,45,500
Project cost (in ₹ Lakhs)₹58,922 Lakhs
Project duration59 months
Project categoryResidential
LocalitySector No. 6, Aditya World City, Integrated Township, Shahpur Bamheta, Pargana Dasna,
Original start date
Proposed start date1 Apr 2024

Inventory

Total units428
Unit TypeUnitsCarpet Area (sqm)
3 BHK428156.47–200.44

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9899992222
Emailaurealestateservices@gmail.com
Coordinator9871032222
Helpline9899992222
Address10, Vikas Marg, Bharat Bhawan, New Rajdhani Enclave, East Delhi, Delhi 110092

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q227.0%
2025-Q331.8%
2025-Q443.8%
2026-Q149.7%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
GDA/BP/23-24/129816 Feb 202415 Feb 202915 Feb 202915 Feb 2029

Land Parcels

Khasra No.AreaPlot Type
GH-728077Plot

Approved Unit Plan

Unit plan rows on file428
Total flats (sum of rows)428
BlocksTOWER-C, TOWER-D, TOWER-E, TOWER-F, TOWER-G
Floor types3 BHK

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of THE SUNFLOWER - PHASE 1?

The RERA registration number of THE SUNFLOWER - PHASE 1 is UPRERAPRJ448904, as recorded on the UP-RERA portal.

What is the RERA status of THE SUNFLOWER - PHASE 1?

As reported by UP-RERA, the status of THE SUNFLOWER - PHASE 1 is "Registered".

Where is THE SUNFLOWER - PHASE 1 located?

As reported to UP-RERA, THE SUNFLOWER - PHASE 1 is located at Plot No. GH-7,, Sector No. 6, Aditya World City, Integrated Township, Shahpur Bamheta, Pargana Dasna,, Ghaziabad, Ghaziabad, Uttar Pradesh.

When will THE SUNFLOWER - PHASE 1 be completed?

The latest completion date reported to UP-RERA for THE SUNFLOWER - PHASE 1 is 15 Feb 2029.

Is THE SUNFLOWER - PHASE 1 delayed?

Measured against the latest completion date reported to UP-RERA, THE SUNFLOWER - PHASE 1 is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026