VVD-BLOOM is a RERA-registered commercial project by VANSHIKA VEDANT DEVELOPERS LLP in Ghaziabad (RERA ID UPRERAPRJ165336). Registered with a completion deadline of 26 Dec 2027.
RERA status as reported: Registered.Construction progress
Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ165336 |
| Project category | Commercial |
| Registration type | New |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Ghaziabad Development Authority |
| Proposed start | 1 May 2023 |
| Project duration | 56 months |
| Address | Ghaziabad, Ghaziabad |
| Tehsil | Ghaziabad |
| Applicant type | Partnership Firm |
| Applicant address | 401, Noor Nagar, Sihani, Ghazibabad, Uttar Pradesh- 201001 |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Building permit sanctioned
Hotel/03212/GDA/BP/21-22/1062/01062022
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Registered with RERA
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 10 Jun 2023 |
| Original completion | 26 Dec 2027 |
| Revised completion | — none granted |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹23,000 |
| Sanctioning authority | Ghaziabad Development Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
- SHOP14 44%
- STUDIO12 38%
- OTHER6 19%
| Configuration | Units | Carpet area |
|---|---|---|
| SHOP | 14 | 28-34 |
| OTHER | 6 | 24-74 |
| STUDIO | 12 | 24-71 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| Hotel · SHOP, OTHER, STUDIO | 6 | 32 | 24-74 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots Covered by the temporary sheets on the point given by the patwari. |
| 2 | Boundary Wall 7 ft. height boundary wall of RCC wall/column and brickwork as per drawings. |
| 3 | Road Work Cement concrete road over the subbase 200mm thick GSB+ 2 layer of WSM. |
| 4 | Footpaths 75 mm high from the road level with cc interlocking tiles over the subbase of 100 mm thick P.C.C and 50 mm thick bed of fine sand. |
| 5 | Water Supply Including Drinking Water Facilities Water connection for commercial uses will be provided by the Ghaziabad Development Authority and storage will be done under a groundwater tank of the capacity super the norms. |
| 6 | Sewer System The main sewer line has been designed as per norms and a PVC pipe of 10 KG pressure will be used in the vertical stags in the shafts partial sewer line will be laid in the basement ceiling and will finally connect to STP. |
| 7 | Drain An underground pipeline drain will be laid in the slope as per norms and collecting chambers as per the norms will be provided to collect the surface rainwater. |
| 8 | Parks The soft landscape will be done in the park with sufficient electrical lighting. |
| 9 | Tree Planting Tree plantation of the different variables of trees as per the site conditions is planned which follows the authority guidelines. |
| 10 | Design For Electric Supply Including Street Lighting M.S. Street light designer poles with energy-saving LED lighting fixtures will be used. Partial light will be operated from the solar panel which will be installed on the terrace. |
| 11 | Community Buildings Not Applicable |
| 12 | Treatment and Disposal System of Sewage and Sullage water STP will be installed in the basement for treating the sewer and treated water will be recycled for use in flushing and gardening. |
| 13 | Solid Waste Management And Disposal System Solid waste management and disposal system will be done by an external vendor by collecting the garbage from the dustbin./shops and segregating the same for recycling the dry waste and preparing the compost from the wet waste. |
| 14 | Water Conservation System Rain water harvesting pit has been planned in the open area for recharging the groundwater by collecting the rainwater from the terrace and road surface area. |
| 15 | Energy Management System Including Use of Renewable Energy Solar panels will be installed on the terrace for the conservation of electricity as per the norms of MOE. |
| 16 | Fire Protection And Fire Safety System Fire protection and fire safety system will be provided as per the fire department guidelines by fulfilling the fire norms as per NBC. |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services Not Applicable |
| 18 | Emergency Evacuation Services A separate fire staircase is designed for evacuation service in the building. |
| 19 | Other Miscellaneous Work As per the requirement on the period of time. |
Permits & extensions
1 permit
An approval and the date it runs to - not proof the work matching it was done.
1 sanctioning permit is on record with UPRERA, valid to 26 Dec 2027.
Sanctioned by Ghaziabad Development Authority · 1,221 sqm of land · an approved plan of 1 block and 32 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| Hotel/03212/GDA/BP/21-22/1062/01062022 | 27 Dec 2022 | 26 Dec 2027 | 26 Dec 2030 | 26 Dec 2027 |
| Document | File |
|---|---|
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
Land & documents
15 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 527m | 1221.64 | Khasra |
| Khatauni extract · 1427-1432 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Registry document · 237 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | not reported | — |
| Other A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is. | not reported | — |
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | New | 1 May 2023 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 1 May 2023 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 1 May 2023 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | New | 1 May 2023 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 1 May 2023 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 1 May 2023 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 1 May 2023 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 1 May 2023 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 3 May 2023 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 1 May 2023 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 3 May 2023 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 1 May 2023 ↗ |
Quarterly progress reports
13 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
13 quarterly progress reports are on file with UPRERA, covering 2023-Q1 to 2026-Q1.
| Quarter | Construction | Certificates |
|---|---|---|
| 2023-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q2 | 98% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q3 | 99.06% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q4 | 99% | CA ↗ · Arch ↗ · Eng ↗ |
| 2026-Q1 | 99% | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | VANSHIKA VEDANT DEVELOPERS LLP |
| Role | Promoter · current |
| RERA ID | UPRERAPRM225372 |
| PAN | AAUFV8486F |
| CIN / TAN | MRTV07212C |
| Registered address | 401, Noor Nagar, Sihani, Ghazibabad, Uttar Pradesh- 201001 |
| RERA contact | |
| Registered since | 2023 |
| Legal name | BALA DEVI |
| Role | Co-promoter |
| Applicant type | Individual |
| Address | House No.- 8/111 Sector-8, Chiranjeev Vihar, Ghaziabad, Uttar Pradesh- 201002 |
| RERA contact |
Nearby projects
Ghaziabad
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary | VANSHIKA VEDANT DEVELOPERS LLP- COLLECTION ACCOUNT FOR VVD-BLOOMBankBank of IndiaBranchRaj Nagar extensionBranch addressKhasra No. 839, Main road Raj Nagar ExtensionBranch districtGhaziabad, Uttar PradeshA/C no.IFSCBKID0007143 |
| SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary | VANSHIKA VEDANT DEVELOPERS LLP- SEPARATE BANK ACCOUNT FOR VVD-BLOOMBankBank of IndiaBranchRaj Nagar ExtensionBranch addressKhasra No. 839, Main Road, Raj Nagar ExtensionBranch districtGhaziabad, Uttar PradeshA/C no.IFSCBKID0007143 |
| TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary | VANSHIKA VEDANT DEVELOPERS LLP- RERA TRANSACTION ACCOUNT FOR VVD- BLOOMBankBank of IndiaBranchRaj Nagar ExtensionBranch addressKhasra No. 839, Main Road, Raj Nagar ExtensionBranch districtGhaziabad, Uttar PradeshA/C no.IFSCBKID0007143 |
What has changed on this record
nothing recorded yet
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.What to verify and what to ask
1 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.
Common questions about VVD-BLOOM
Is VVD-BLOOM RERA registered?
Yes. VVD-BLOOM is registered with UPRERA under registration number UPRERAPRJ165336, registered on 10 Jun 2023. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for VVD-BLOOM?
The completion date filed with UPRERA is 26 Dec 2027. No completion certificate is on record yet.
Who is the builder of VVD-BLOOM?
VANSHIKA VEDANT DEVELOPERS LLP is the promoter entity that filed VVD-BLOOM with UPRERA (promoter RERA ID UPRERAPRM225372). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Does VVD-BLOOM have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is VVD-BLOOM located?
VVD-BLOOM is registered in Ghaziabad, as filed with UPRERA.
What configurations are available in VVD-BLOOM?
The unit plan filed with UPRERA lists SHOP, OTHER and STUDIO. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in VVD-BLOOM?
The approved unit plan filed with UPRERA runs from 24 to 74 m² of carpet area (about 255 to 799 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in VVD-BLOOM?
The approved unit plan describes 1 block and 32 units of which 18 are homes and 14 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is VVD-BLOOM?
About 106 units per acre: 32 planned units across 0.30 acres (1,221 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗