estanzo
Projects
estanzo
The builder-reliability record for Indian real estate.
Explore
ProjectsPromotersDistrictsDirectors
About
How it worksData sourcesReport an error
Legal
DisclaimerPrivacyContact
Data as reported by UP-RERA. Estanzo reproduces public filings as-is with source links and does not verify, rate or endorse any builder or project.
Home › Projects

Projects

3,839 RERA-registered projects · as reported by UPRERA

Cards Table
District: Any ▾
AnyAgraAligarhAmrohaAyodhyaBahraichBandaBarabankiBareillyBastiBijnorBudaunBulandshahrChandauliEtahEtawahFirozabadGautam Budh NagarGhaziabadGondaGorakhpurHapurHardoiHathrasJaunpurJhansiKanpur NagarKushinagarLalitpurLucknowMathuraMauMeerutMirzapurMoradabadMuzaffarnagarPrayagrajRampurSaharanpurSambhalShahjahanpurSitapurSultanpurUnnaoVaranasi
Status: Any ▾
AnyRegisteredCompletedDe-registeredAbeyanceNCLTLapsedWithdrawn
Sort: Default ▾
DefaultMost delayedNewest registeredName A–Z
Showing 2,361–2,380 of 3,839
Registered
ORO Elements
ORO CONSTRUCTIONS PVT LTD·Lucknow
Units (plan)288
DeadlineOct 2024
Delay▲ 22 mo
Registered
ORO Utsav
ORO REAL INFRA LLP·Lucknow
Units (plan)80
DeadlineSept 2027
Delay—
Registered
OXIRICH AVENUE
Oxirich Construction Pvt. Ltd.
‹1…118119120…192›
·
Ghaziabad
Units—
DeadlineMar 2018
Delay▲ 8 yr
Registered
OXIRICH SQUARE ONE
OXIRICH CONSTRUCTION PVT LTD·Ghaziabad
Units (plan)203
DeadlineMar 2025
Delay▲ 16 mo
Registered
OXY HI STREET
Oxy Heightz Infra LLP·Ghaziabad
Units (plan)282
DeadlineApr 2028
Delay—
Registered
OXY HOMEZ (BLOCK- O, X & Y)
SUPER REALTECH PVT. LTD·Ghaziabad
Units—
DeadlineMar 2018
Delay▲ 8 yr
Registered
OYSTER WALK
SRSD INFRASTRUCTURE VENTURE LLP·SECTOR- 1, WAVE CITY, GHAZIABAD
Units (plan)568
DeadlineJan 2031
Delay—
Registered
OZONE CITY PHASE-4
OZONE BUILDERS & DEVELOPERS PVT LIMITED·Aligarh
Units—
DeadlineMay 2021
Delay▲ 5 yr
Registered
Ozone City Phase-7 The Golden Estate
OZONE BUILDERS & DEVELOPERS PVT LIMITED·Aligarh
Units—
DeadlineDec 2027
Delay—
Registered
Ozone City Phase-VI The Golden Estate
OZONE INFRAHEIGHT PRIVATE LIMITED·Aligarh
Units—
DeadlineJul 2028
Delay—
Registered
OZONE CLASSIK
Promoter not reported·Ghaziabad
Units (plan)1,310
DeadlineMay 2027
Delay—
Registered
Paalm Paradise Phase-1
Aisshpra Lifespaces·Gorakhpur
Units (plan)417
DeadlineJun 2021
Delay▲ 5 yr
Registered
Paalm Paradise Phase II
Aisshpra Lifespaces·Gorakhpur
Units (plan)308
DeadlineMay 2024
Delay▲ 2 yr
Registered
Paalm Paradise Phase-III
Aisshpra Lifespaces·Gorakhpur
Units—
DeadlineJun 2023
Delay▲ 3 yr
Registered
Paalm Paradise Phase-IV
Aisshpra Lifespaces·Gorakhpur
Units (plan)224
DeadlineMay 2025
Delay▲ 15 mo
Registered
Paalm Paradise Phase-V
Aisshpra Lifespaces·Gorakhpur
Units (plan)88
DeadlineMay 2027
Delay—
Registered
Paalm Paradise Phase-VI
Aisshpra Lifespaces·Gorakhpur
Units (plan)168
DeadlineMay 2027
Delay—
Registered
Paarth Republic - EWS/LIG
Paarth Infrabuild Private Limited·Lucknow
Units (plan)920
DeadlineApr 2024
Delay▲ 2 yr
Registered
Paarth - Victory Walk Arcade
Paarth Infrabuild Private Limited·Lucknow
Units (plan)57
DeadlineNov 2025
Delay▲ 8 mo
Default on QPR
Padam Corporate Park
SHREE RIDDHI SIDDHI BUILDWELL LIMITED·Agra
Units (plan)64
DeadlineDec 2022
Delay▲ 3 yr