Jaypee Infratech Limited

UPRERACompany

Jaypee Infratech Limited (RERA ID: UPRERAPRM6253) is a company registered with UP-RERA since 2017. It has 27 projects on record with Estanzo, of which 9 are in abeyance with RERA.

Summarize this record with:ChatGPTPerplexityClaudeGrok

One legal entity’s record; a brand may register through several. Complaint counts are allegations, with no outcome attached.

Projects by this promoter

27 on record
Registered18Abeyance9each project counted once, under the authority’s own step
Jaypee Greens Aman -III, Mirzapur UPRERA
UPRERAPRJ4895 · Gautam Budh Nagar
Promised completion 29 Dec 2022 · Extended
Abeyance
Jaypee Greens Aman, Noida UPRERA
UPRERAPRJ3824 · Gautam Budh Nagar
Promised completion 30 Jun 2019
Registered
Jaypee Greens Buddh Circuit Studios - II, Mirzapur UPRERA
UPRERAPRJ4848 · Gautam Budh Nagar
Promised completion 30 Sept 2022 · Extended
Abeyance
Jaypee Greens Garden Isles, Noida UPRERA
UPRERAPRJ3784 · Gautam Budh Nagar
Promised completion 31 Dec 2025 · Extended
Registered
Jaypee Greens Kasa Isles, Noida UPRERA
UPRERAPRJ3843 · Gautam Budh Nagar
Promised completion 9 Oct 2027 · Extended
Registered
Jaypee Greens Kensignton Boulevard Apartments, Noi UPRERA
UPRERAPRJ4668 · Gautam Budh Nagar
Promised completion 31 Dec 2025 · Extended
Registered
Jaypee Greens Kensington Park Apartments, Noida UPRERA
UPRERAPRJ4954 · Gautam Budh Nagar
Promised completion 30 Dec 2025 · Extended
Registered
Jaypee Greens Kensington Park Plots, Agra UPRERA
UPRERAPRJ4986 · Agra
Promised completion 30 Sept 2021 · Extended
Abeyance
Jaypee Greens Klassic - A (Phase II), Noida UPRERA
UPRERAPRJ3901 · Gautam Budh Nagar
Promised completion 31 Mar 2019
Registered
Jaypee Greens Klassic Arcade, Noida UPRERA
UPRERAPRJ3912 · Gautam Budh Nagar
Promised completion 30 Apr 2018
Registered
Jaypee Greens Klassic Corporate, Noida UPRERA
UPRERAPRJ3618 · Gautam Budh Nagar
Promised completion 31 Dec 2018
Registered
Jaypee Greens Klassic - D, Noida UPRERA
UPRERAPRJ3683 · Gautam Budh Nagar
Promised completion 30 Sept 2026 · Extended
Registered
Jaypee Greens Kosmos - A (Phase II), Noida UPRERA
UPRERAPRJ3853 · Gautam Budh Nagar
Promised completion 29 Sept 2026 · Extended
Registered
Jaypee Greens Kosmos - B (Phase II), Noida UPRERA
UPRERAPRJ3900 · Gautam Budh Nagar
Promised completion 29 Sept 2026
Registered
Jaypee Greens Kosmos - C, Noida UPRERA
UPRERAPRJ3894 · Gautam Budh Nagar
Promised completion 29 Sept 2026 · Extended
Registered
Jaypee Greens Krescent Homes, Noida UPRERA
UPRERAPRJ3709 · Gautam Budh Nagar
Promised completion 31 Dec 2025 · Extended
Registered
Jaypee Greens Kube, Noida UPRERA
UPRERAPRJ3571 · Gautam Budh Nagar
Promised completion 30 Sept 2021 · Extended
Registered
Jaypee Greens Naturvue Apartments, Mirzapur UPRERA
UPRERAPRJ4875 · Gautam Budh Nagar
Promised completion 29 Mar 2023 · Extended
Abeyance
Jaypee Greens Orchards, Noida UPRERA
UPRERAPRJ3820 · Gautam Budh Nagar
Promised completion 31 Dec 2025 · Extended
Registered
Jaypee Greens Sunnyvale Homes, Mirzapur UPRERA
UPRERAPRJ5428 · Gautam Budh Nagar
Promised completion 30 Jun 2021 · Extended
Abeyance

Showing 20 of 27 projects on record. See all 27 projects

Promoters sharing a director

none matched

Linked by a director’s DIN, never by name alone. Each company is its own record.

No other promoter shares a director with Jaypee Infratech Limited on record. RERA lists its directors without a DIN, and names alone are never matched.

Filings for more time

27 filings
Extension filings27
Projects with at least one21 of 27
Longest single extension2,829 days - Jaypee Greens Kosmos - C, Noida
Latest extension runs to23 Jun 2028 - Jaypee Greens Wish Point, Noida
Permits carrying a revalidation27 across 16 projects

Directors & ownership

11 named by UPRERA
Chairman
SH. MANOJ GAUR
Director
Shri B. B. Tandon
Director
Shri B. K. Goswami
Director
Shri Lalit Bhasin
Director
Shri Rakesh Sharma
Director
Shri S. Balasubramanian
Director
Shri S. L. Mohan
Director
Shri Sameer Gaur
Director
Shri Sunil Kumar Sharma
Director
Smt. Rekha Dixit
Director
Smt. Salila George

Promoter timeline

18 Apr 2013 - 29 Sept 2026
  1. Extension filed
    new completion date on file 29 Sept 2026official source ↗
  2. Permit revalidated
    valid to 13 Feb 2030as recorded by UPRERA: 2023/05/31official source ↗
  3. Completion certificate filed
    official source ↗
  4. Permit revalidated
    valid to 31 Dec 2025as recorded by UPRERA: Noida/CAP/ 2014/ III - 249/ 713official source ↗
  5. Permit revalidated
    valid to 31 Dec 2025as recorded by UPRERA: Noida/CAP/ 2014/ III - 249/ 713official source ↗
  6. Permit revalidated
    valid to 31 Dec 2025as recorded by UPRERA: Noida/CAP/ 2014/ III - 249/ 713official source ↗
  7. Completion certificate filed
    official source ↗
  8. Completion certificate filed
    official source ↗
  9. Completion certificate filed
    official source ↗
  10. Completion certificate filed
    official source ↗
  11. Completion certificate filed
    official source ↗
  12. Completion certificate filed
    official source ↗
Show 79 earlier filings
  1. Permit revalidated
    valid to 7 Jan 2024as recorded by UPRERA: Noida/MVN/2024/III-249/1264official source ↗
  2. Completion certificate filed
    official source ↗
  3. Extension filed
    new completion date on file 29 Mar 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  4. Extension filed
    new completion date on file 29 Dec 2022as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  5. Extension filed
    new completion date on file 29 Dec 2022as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  6. Completion certificate filed
    official source ↗
  7. Extension filed
    new completion date on file 30 Sept 2022as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  8. Extension filed
    new completion date on file 31 Dec 2025official source ↗
  9. Extension filed
    new completion date on file 31 Dec 2025official source ↗
  10. Extension filed
    new completion date on file 31 Dec 2025official source ↗
  11. Extension filed
    new completion date on file 23 Jun 2028official source ↗
  12. Extension filed
    new completion date on file 29 Dec 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  13. Extension filed
    new completion date on file 29 Dec 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  14. Extension filed
    new completion date on file 29 Dec 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  15. Extension filed
    new completion date on file 29 Dec 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  16. Extension filed
    new completion date on file 30 Sept 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  17. Extension filed
    new completion date on file 30 Sept 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  18. Extension filed
    new completion date on file 30 Sept 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  19. Extension filed
    new completion date on file 30 Jun 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  20. Extension filed
    new completion date on file 31 Dec 2025official source ↗
  21. Extension filed
    new completion date on file 9 Oct 2027official source ↗
  22. Extension filed
    new completion date on file 30 Sept 2020as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  23. Extension filed
    new completion date on file 30 Sept 2020as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  24. Extension filed
    new completion date on file 30 Sept 2020as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  25. Permit revalidated
    valid to 22 Nov 2026as recorded by UPRERA: Noida/Sr. T.P./III-256/474official source ↗
  26. Permit revalidated
    valid to 28 Sept 2026as recorded by UPRERA: Noida/Sr. T.P./III-256/474official source ↗
  27. Extension filed
    new completion date on file 30 Dec 2025official source ↗
  28. Extension filed
    new completion date on file 30 Sept 2026official source ↗
  29. Completion certificate filed
    official source ↗
  30. Extension filed
    new completion date on file 29 Sept 2026official source ↗
  31. Extension filed
    new completion date on file 18 Jul 2026official source ↗
  32. Permit revalidated
    valid to 31 Dec 2025as recorded by UPRERA: Noida/CAP/ 2014/ III - 287/714official source ↗
  33. Extension filed
    new completion date on file 29 Sept 2026official source ↗
  34. Permit revalidated
    valid to 31 Dec 2025as recorded by UPRERA: Noida/ CAP/ III-283/645official source ↗
  35. Permit revalidated
    valid to 31 Dec 2025as recorded by UPRERA: Noida/ CAP/ III-260/642official source ↗
  36. Permit revalidated
    valid to 31 Dec 2025as recorded by UPRERA: Noida/ CAP/ III-260/642official source ↗
  37. Permit revalidated
    valid to 9 Oct 2027as recorded by UPRERA: Noida/CAP/III-261/577official source ↗
  38. Permit revalidated
    valid to 9 Oct 2027as recorded by UPRERA: Noida/CAP/III-261/577official source ↗
  39. Permit revalidated
    valid to 9 Oct 2027as recorded by UPRERA: Noida/CAP/III-259/576official source ↗
  40. Permit revalidated
    valid to 10 Oct 2027as recorded by UPRERA: Noida/CAP/III-263/493 & Noida/CAP/III-258/575official source ↗
  41. Project registered
    official source ↗
  42. Project registered
    official source ↗
  43. Project registered
    official source ↗
  44. Project registered
    official source ↗
  45. Project registered
    official source ↗
  46. Project registered
    official source ↗
  47. Project registered
    official source ↗
  48. Project registered
    official source ↗
  49. Project registered
    official source ↗
  50. Project registered
    official source ↗
  51. Project registered
    official source ↗
  52. Project registered
    official source ↗
  53. Project registered
    official source ↗
  54. Project registered
    official source ↗
  55. Project registered
    official source ↗
  56. Project registered
    official source ↗
  57. Project registered
    official source ↗
  58. Project registered
    official source ↗
  59. Project registered
    official source ↗
  60. Project registered
    official source ↗
  61. Project registered
    official source ↗
  62. Project registered
    official source ↗
  63. Project registered
    official source ↗
  64. Project registered
    official source ↗
  65. Project registered
    official source ↗
  66. Project registered
    official source ↗
  67. Project registered
    official source ↗
  68. Permit revalidated
    valid to 31 Dec 2025as recorded by UPRERA: Noida/CAP/2022/III-262/1216official source ↗
  69. Permit revalidated
    valid to 19 Mar 2027as recorded by UPRERA: Noida/CAP/III-262/524official source ↗
  70. Permit revalidated
    valid to 19 Mar 2027as recorded by UPRERA: Noida/CAP/III-262/524official source ↗
  71. Permit revalidated
    valid to 19 Mar 2027as recorded by UPRERA: Noida/CAP/III-262/524official source ↗
  72. Permit revalidated
    valid to 29 Sept 2026as recorded by UPRERA: Noida/Sr.T.P./III-254/472official source ↗
  73. Permit revalidated
    valid to 29 Sept 2026as recorded by UPRERA: Noida/Sr.T.P./III-254/472official source ↗
  74. Permit revalidated
    valid to 29 Sept 2026as recorded by UPRERA: Noida/Sr.T.P./III-254/472official source ↗
  75. Permit revalidated
    valid to 29 Sept 2026as recorded by UPRERA: Noida/Sr.T.P./III-254/472official source ↗
  76. Permit revalidated
    valid to 29 Sept 2026as recorded by UPRERA: Noida/Sr.T.P./III-254/472official source ↗
  77. Permit revalidated
    valid to 18 Jul 2026as recorded by UPRERA: Noida/CAP/III-253/919official source ↗
  78. Permit revalidated
    valid to 1 Jul 2022as recorded by UPRERA: CN/LFD-03/2014official source ↗
  79. Permit revalidated
    valid to 16 Apr 2023as recorded by UPRERA: Noida/ CAP/ III-283/645official source ↗

Quarterly reports filed, by financial year

FY 2020-21
52 reports across 13 projects
FY 2021-22
48 reports across 13 projects
FY 2022-23
40 reports across 10 projects
FY 2023-24
40 reports across 10 projects
FY 2024-25
40 reports across 10 projects
FY 2025-26
37 reports across 10 projects
FY 2026-27
7 reports across 7 projects
Counts the reports UPRERA publishes as filed.

Statuses published without a date

UPRERA publishes no date for these, and Estanzo will not supply one, so they sit beside the axis rather than on it.
A filing is not an outcome.

Common questions about Jaypee Infratech Limited

How many projects has Jaypee Infratech Limited registered with RERA?

Estanzo holds 27 projects on record with UPRERA, filed by Jaypee Infratech Limited (promoter RERA ID UPRERAPRM6253). This counts filings by this legal entity only - a builder brand may file through several entities.

Who are the directors of Jaypee Infratech Limited?

Jaypee Infratech Limited disclosed 11 directors or partners to UPRERA, listed on this page as published. Estanzo shows the names and roles from that filing only.

When was Jaypee Infratech Limited registered with RERA?

Jaypee Infratech Limited has been registered with UPRERA since 27 Jul 2017.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗