A R DOMAIN

UPRERARegistered

A R DOMAIN is a RERA-registered residential project by A R BUILDTECH PVT LTD in VILLAGE - MORTA, PARGANA - JALALABAD, Ghaziabad (RERA ID UPRERAPRJ699935). Registered with a completion deadline of 26 Mar 2028.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q2'25
0%Q3'25
1.37%Q4'25
4.68%Q1'26
6.22%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ699935
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGhaziabad Development Authority
Proposed start6 Apr 2025
Project duration36 months
AddressKHASRA NO - 1093 , KHATA NO - 847, VILLAGE - MORTA, PARGANA - JALALABAD, Ghaziabad, Ghaziabad
TehsilGhaziabad
Applicant typeCompany
Applicant addressT-22-03-01, CWG VILLAGE , DELHI-110092
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    Group Housing/04287/GDA/BP/21-22/1168/06012023

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered29 May 2025
Original completion26 Mar 2028
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹45,500
Sanctioning authorityGhaziabad Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors183 · 3 · 17 (units from plan)
Homes · commercial units176 · 7 (shops and offices filed in the same plan)
  • 3 BHK150 82%
  • 4 BHK22 12%
  • SHOP7 4%
  • 2 BHK4 2%
ConfigurationUnitsCarpet area
3 BHK15083-127
2 BHK463
4 BHK22146
SHOP710-15
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
COMMERCIAL AND COMMUNITY · SHOP1710-15
TOWER-A · 3 BHK, 2 BHK, 4 BHK, OTHER178863-146
TOWER-B · 3 BHK, 2 BHK, 4 BHK, OTHER178863-146
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
VISHAL MITTAL
License CA/1998/23185
B-34, SECTOR-67, NOIDA
Engineer
VIKAS KUMAR GARG
52, SECTOR-5, VAISHALI, GHAZIABAD,-201010
Contractor
A R BUILDTECH PVT LTD
T-22-03-01, CWG VILLAGE, DELHI-110092
Sr.Development work declared to RERA
1Demarcation of Plots
DEMARCATION OF THE PLOT IS DONE AS PER APPROVED BUILDING PLAN. LAND IS IN OUR POSSESSION.
2Boundary Wall
PERMANENT BOUNDARY WALL WILL BE CONSTRUCTED AS PER DESIGN IN RCC / BRICK WORK.
3Road Work
INTERNAL ROADS AS PER THE ARCHITECTS PLAN WILL BE CONSTRUCTED WITH RCC FINISH/PAVERS.
4Footpaths
AS PER ARCHITECTS PLAN.
5Water Supply Including Drinking Water Facilities
WATER SUPPLY WILL BE DONE WITH CPVC/PVC PIPES AS PER DRAWING OF OUR CONSULTANT . TANKS WILL BE CONSTRUCTED FOR UNINTERRUPTED SUPPLY OF WATER.
6Sewer System
SEWER SYSTEM IN BUILDING WILL BE WITH PVC PIPES AND UNDERGROUND SEWER SYSTEM WILL BE WITH RCC PIPES. AS PER DRAWING OF OUR CONSULTANT
7Drain
WASTE DRAIN AND RAINWATER SYSTEM WIIL BE CONSTRUCTED USING PVC PIPE TO OUTER DRAIN .
8Parks
PARK WILL BE DEVELOPED AS PER LANDSCAPING PLAN.
9Tree Planting
TREE PLANTING WILL BE DONE AS PER LANSCAPE PLAN.
10Design For Electric Supply Including Street Lighting
THE ELECTRIC SUPPLY ALONG WITH POWER BACKUP WILL BE PROVIDED AS PER MEP CONSULTANT/ARCHITECT.
11Community Buildings
SHOPS ,COMMUNITY HALL AND MULTIPURPOSE HALL WILL BE CONSTRUCTED.
12Treatment and Disposal System of Sewage and Sullage water
TREATMENT THROUGH S.T.P AND OVERFLOW TO THE MUNICIPAL SEWERAGE LINE.
13Solid Waste Management And Disposal System
SOLID WASTE WILL BE SEGREGATED AND ORGANIC WASTE WILL BE TREATED THROUGH OWC.
14Water Conservation System
RAINWATER HARVESTING PITS WILL BE CONSTRUCTED AS PER DRAWING.
15Energy Management System Including Use of Renewable Energy
AS PER DESIGN AND REQUIREMENT
16Fire Protection And Fire Safety System
AS PER NBC REQUIREMENT AND FIRE APPROVAL
17Social Infrastructure And Other Public Amenities Including Public Health Services
NA
18Emergency Evacuation Services
AS PER APPROVED PLAN
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 26 Mar 2028.

Sanctioned by Ghaziabad Development Authority · 8,038 sqm of land · an approved plan of 3 blocks and 183 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
Group Housing/04287/GDA/BP/21-22/1168/0601202327 Mar 202326 Mar 202826 Mar 203126 Mar 2028
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗

Land & documents

22 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
10932277Khasra
10932276Khasra
10934552Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · 4108
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 4107
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 3071
The registered deed by which the promoter bought the land.
PDF ↗
Khatauni extract · 1430-1435
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New12 May 2025 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New5 Apr 2025 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New5 Apr 2025 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New5 Apr 2025 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New5 Apr 2025 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New5 Apr 2025 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New5 Apr 2025 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New24 Apr 2025 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New12 May 2025 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New5 Apr 2025 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New5 Apr 2025 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New5 Apr 2025 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New5 Apr 2025 ↗

Quarterly progress reports

5 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

5 quarterly progress reports are on file with UPRERA, covering 2025-Q1 to 2026-Q1.

QuarterConstructionCertificates
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q20%CA ↗ · Arch ↗ · Eng ↗
2025-Q31.37%CA ↗ · Arch ↗ · Eng ↗
2025-Q44.68%CA ↗ · Arch ↗ · Eng ↗
2026-Q16.22%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameA R BUILDTECH PVT LTD
RolePromoter · current
RERA IDUPRERAPRM21610
PANAADCA4441P
CIN / TANU74140DL1999PTC099837
Name of chairmanRAM AVTAR SHARMAASHA SHARMA
Registered addressT-22-03-01, CWG VILLAGE , DELHI-110092
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Ghaziabad

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
A. R. BUILDTECH PVT LTD COLLECTION AC FOR A R DOMAINBankAXIS BANK LTDBranchVASUNDHARA BRANCHBranch addressGROUND FLOOR , KUMAR RESIDENCY PLAZA, PLOT NO. ML 1, SECTOR-11, VASUNDHARA, GHAZIABAD-201012Branch districtGhaziabad, Uttar PradeshA/C no.IFSCUTIB0001812Branch emailvasundhara.branchhead@axisbank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
A.R. BUILDTECH PVT LTD SEPARATE AC FOR A R DOMAINBankAXIS BANK LTDBranchVASUNDHARA BRANCHBranch addressGROUND FLOOR, KUMAR RESIDENCY PLAZA, PLOT NO. ML 1 , SECTOR-11, VASUNDHARA, GHAZIABAD-201012Branch districtGhaziabad, Uttar PradeshA/C no.IFSCUTIB0001812
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
A . R. BUILDTECH PVT LTD TRANSACTION AC FOR A R DOMAINBankAXIS BANK LTDBranchVASUNDHARA BRANCHBranch addressGROUND FLOOR, KUMAR RESIDENCY PLAZA, PLOT NO. ML 1, SECTOR-11, VASUNDHARA, GHAZIABAD-201012Branch districtGhaziabad, Uttar PradeshA/C no.IFSCUTIB0001812
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

20 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Filed document
viewprojects · 21
Proforma of Agreement for Sale
newly filed with RERA
15 Oct 2026
Filed document
viewprojects · 20
ENGINEERS CERTIFICATE
newly filed with RERA
15 Oct 2026
Filed document
viewprojects · 19
ARCHITECT CERTIFICATE
newly filed with RERA
15 Oct 2026
Filed document
viewprojects · 18
CA CERTIFICATE
newly filed with RERA
15 Oct 2026
Filed document
viewprojects · 17
Affidavit (Form-B)
newly filed with RERA
15 Oct 2026
Filed document
viewprojects · 16
Development Work Plan
newly filed with RERA
15 Oct 2026
Filed document
viewprojects · 15
Electricity Supply Plan
newly filed with RERA
15 Oct 2026
Filed document
viewprojects · 14
Water Supply Plan
newly filed with RERA
15 Oct 2026
Filed document
viewprojects · 13
Waste Disposal Plan
newly filed with RERA
15 Oct 2026
Filed document
viewprojects · 12
Proforma of Conveyance Deed
newly filed with RERA
15 Oct 2026
Filed document
viewprojects · 11
Proforma of Allotment Letter
newly filed with RERA
15 Oct 2026
Filed document
viewprojects · 10
Proforma of Application Form
newly filed with RERA
15 Oct 2026
Filed document
viewprojects · 9
Commencement Certificate
newly filed with RERA
15 Oct 2026
Filed document
viewprojects · 8
Details of Encumbrances
newly filed with RERA
15 Oct 2026
Filed document
viewprojects · 7
Other
newly filed with RERA
15 Oct 2026
Filed document
viewprojects · 6
Other
newly filed with RERA
15 Oct 2026
Filed document
viewprojects · 5
Other
newly filed with RERA
15 Oct 2026
Filed document
viewprojects · 4
Development Work Plan
newly filed with RERA
15 Oct 2026
Filed document
viewprojects · 3
Proforma of Completion Certificate(Occupancy)
newly filed with RERA
15 Oct 2026
Filed document
viewprojects · 2
Other Plan(If Any)
newly filed with RERA
15 Oct 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about A R DOMAIN

Is A R DOMAIN RERA registered?

Yes. A R DOMAIN is registered with UPRERA under registration number UPRERAPRJ699935, registered on 29 May 2025. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for A R DOMAIN?

The completion date filed with UPRERA is 26 Mar 2028. No completion certificate is on record yet.

Who is the builder of A R DOMAIN?

A R BUILDTECH PVT LTD is the promoter entity that filed A R DOMAIN with UPRERA (promoter RERA ID UPRERAPRM21610). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does A R DOMAIN have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is A R DOMAIN located?

A R DOMAIN is registered in VILLAGE - MORTA, PARGANA - JALALABAD, Ghaziabad, as filed with UPRERA.

What configurations are available in A R DOMAIN?

The unit plan filed with UPRERA lists 3 BHK, 2 BHK, 4 BHK, OTHER and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in A R DOMAIN?

The approved unit plan filed with UPRERA runs from 10 to 146 m² of carpet area (about 108 to 1,569 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in A R DOMAIN?

The approved unit plan describes 3 blocks and 183 units of which 176 are homes and 7 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is A R DOMAIN?

About 92 units per acre: 183 planned units across 1.99 acres (8,038 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗