Timeline Bar

Registered29 Jul 2017
Promised31 Dec 2019
Today3 Aug 2026

Timeline

Promised completion31 Dec 2019
Revised completion31 Dec 2019
Actual completion
Possession delay79 mo delay

Registration & Cost Details

Registration fee (in ₹)₹49,500
Project cost (in ₹ Lakhs)₹13,000 Lakhs
Project duration79 months
Project categoryResidential
Locality
Original start date1 Feb 2013
Proposed start date30 Jun 2014

Inventory

Total units414
Unit TypeUnitsCarpet Area (sqm)
2 BHK10462.81–73.16
3 BHK26078.48–94.11
4 BHK50105.96

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile8588843548
Emailapv@ajnara.com
Coordinator9582006011
AddressRegd. Office -502, Sachdeva Corporate Tower, Plot No.17, Karkardooma Community Centre, Delhi-92

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
PLG/BP-2387GH/538730 Jun 201430 Jun 201931 Dec 201930 Jun 2024

Land Parcels

Khasra No.AreaPlot Type
GH-03, SEC - 16B, GREATER NOIDA53960Plot

Approved Unit Plan

Unit plan rows on file182
Total flats (sum of rows)414
BlocksTOWER N, TOWER O
Floor types2 BHK, 3 BHK, 4 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
1908828 Jul 2010

Frequently Asked Questions

What is the RERA registration number of Ajnara Homes (Phase-2 Tower N & O)?

The RERA registration number of Ajnara Homes (Phase-2 Tower N & O) is UPRERAPRJ4273, as recorded on the UP-RERA portal.

What is the RERA status of Ajnara Homes (Phase-2 Tower N & O)?

As reported by UP-RERA, the status of Ajnara Homes (Phase-2 Tower N & O) is "Registered".

Where is Ajnara Homes (Phase-2 Tower N & O) located?

As reported to UP-RERA, Ajnara Homes (Phase-2 Tower N & O) is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will Ajnara Homes (Phase-2 Tower N & O) be completed?

The latest completion date reported to UP-RERA for Ajnara Homes (Phase-2 Tower N & O) is 31 Dec 2019.

Is Ajnara Homes (Phase-2 Tower N & O) delayed?

Measured against the latest completion date reported to UP-RERA, Ajnara Homes (Phase-2 Tower N & O) is 79 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026