civitech Santoni

UPRERARegistered

civitech Santoni is a RERA-registered commercial project by Civitech Buildcon Private Limited in Gautam Budh Nagar (RERA ID UPRERAPRJ364474). Registered with a completion deadline of 9 Apr 2028.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q4'24
—Q1'25
—Q2'25
91%Q3'25
24%Q4'25
22%Q1'26
30%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ364474
Project categoryCommercial
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGreater Noida Authority
Proposed start1 Jul 2023
Project duration58 months
AddressDadri, Gautam Budh Nagar
TehsilDadri
Applicant typeCompany
Applicant addressB-199 UGF, Yojna Vihar Delhi-110092
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    PLG/BP/SM-30-sept-2022;15716

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered31 Jul 2023
Original completion9 Apr 2028
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹1,61,000
Sanctioning authorityGreater Noida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors747 · 1 · 35 (units from plan)
Homes · commercial units452 · 295 (shops and offices filed in the same plan)
  • OTHER452 61%
  • SHOP295 39%
ConfigurationUnitsCarpet area
OTHER45227-386
SHOP2953-589
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
CIVITECH SANTONI · OTHER, SHOP357473-1,584
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.The plan also files 3,780.82 m² for a OTHER, 965.41 m² for a OTHER, 909 m² for a OTHER and 1 other unit like them, far outside the rest of that type, so the ranges above leave them out.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Amit Kumar
License CA/98/22706
1st Floor , B-99, Sector-63, NOIDA- 201301 Gautambudh Nagar-UP
Engineer
VMS Consultants Private Limited
83/84 sakhar Bhawan, 230 Nariman Point Mumbai-400021
Contractor
Civitech Buildcon Private Limited
H-71, Civitech House, Sector-63, NOIDA-201301, Gautambudh Nagar-UP
Sr.Development work declared to RERA
1Demarcation of Plots
demarcation of plot by bench mark in consultation with surveyor for plot corners as per lease plan issued by GNIDA . 23 feet high sheet fencing will be provided
2Boundary Wall
boundary wall by RCC and grills, ambient lighting
3Road Work
RCC, trimix or floor tiles or cobbles stones or interlocking tiles , kerb stone for fire tender route of 7.5 meter wide around the mall and 9 meter wide near the tower
4Footpaths
floor tiles or cobble or interlocking tiles ,well lighted footpath will be provided
5Water Supply Including Drinking Water Facilities
695 KLD is the total water requirement including fresh water of 241 KLD and treated water of 450 KLD .
6Sewer System
STP for treatment of sewerage and sullage waste is proposed. The technology proposed to be used for the purpose is MBBR with PSF /ACF and ozone in tertiary treatment . moving bed bio reactor is an attached growth process, where the bio mass grows on media.
7Drain
natural typology of plot /by gravity for storm water line will be laid down. bio soils , landscape feature and other sustainable urban drainage system (SUDS) will be used.
8Parks
landscape area of 4176.718 sqm is proposed .
9Tree Planting
85 number of tress are proposed and will be planted as per landsscap plan. 50 percent plant will be ever green .
10Design For Electric Supply Including Street Lighting
total power requirement is 6554 KVA including street lighting building lighting etc.,
11Community Buildings
public toilets for visitors are proposed inside the mall with fitting and fixtures.
12Treatment and Disposal System of Sewage and Sullage water
proposed STP capacity is 380 KLD.
13Solid Waste Management And Disposal System
Saprate wet and dry bins will be provided in common area and ground floor to facilitate sagarigation of waste . solid waste will be sagrigated in vet garbage and inert materials .
14Water Conservation System
the capacity of tank and recharge pit is designed to retain run- off at least fifteen minutes of rainfall at peak intensity. 4 numbers of rain water harvesting pits are proposed .
15Energy Management System Including Use of Renewable Energy
concept of passive solar design that menimises energy consumption is building by using design elements such as building orientation , landscaping , efficient building envelop , appropriate fenestration , increase day lighting disgine and thermal mask etc., shall be incorporated in the building.
16Fire Protection And Fire Safety System
fire protection and fire safety system are proposed like fire piping system , fire water static system fire pumping system fire hydrant system automatic sprinkler system automatic fire detection system fire alarm water curtain system and parking area , hand held fire extinguisher
17Social Infrastructure And Other Public Amenities Including Public Health Services
separate toilets for specially abled persons, baby feeding room , driver room with toilet in parking and staff toilet at different level are proposed
18Emergency Evacuation Services
stair cases are provided in building, distance between stair cases and width are proposed considering maximum occupancy of the floor as per NBC and local fie norms. rams are provided inside the building for the basement.
19Other Miscellaneous Work
facility of sick room and doctor room is proposed inside the building .
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 9 Apr 2028.

Sanctioned by Greater Noida Authority · 15,089 sqm of land · an approved plan of 1 block and 747 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
PLG/BP/SM-30-sept-2022;1571610 Apr 20239 Apr 202810 Apr 203010 Apr 2030
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

18 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
C-1B, Sector-16B, Greater Noida15089Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 33543
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Allotment letter from the authority · Commercial/2019/2834
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New28 Jul 2023 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New15 Jun 2023 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New15 Jun 2023 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New7 Jul 2023 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New15 Jun 2023 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New15 Jun 2023 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New15 Jun 2023 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New15 Jun 2023 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New28 Jul 2023 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New15 Jun 2023 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New14 Jul 2023 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New15 Jun 2023 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New15 Jun 2023 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New15 Jun 2023 ↗

Quarterly progress reports

13 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

13 quarterly progress reports are on file with UPRERA, covering 2023-Q2 to 2026-Q2.

QuarterConstructionCertificates
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q291%CA ↗ · Arch ↗ · Eng ↗
2025-Q324%CA ↗ · Arch ↗ · Eng ↗
2025-Q422%CA ↗ · Arch ↗ · Eng ↗
2026-Q130%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameCivitech Buildcon Private Limited
RolePromoter · current
RERA IDUPRERAPRM192249
PANAAECC5011A
CIN / TANU70100DL2010PTC210428
Name of chairmanSubodh Goel
Registered addressB-199 UGF, Yojna Vihar Delhi-110092
RERA contact
Registered since2022
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
CIVITECH BUILDCON PRIVATE LIMITED(CBPL) COLLECTION ACCOUNT FOR PROJECT CIVITECH SANTONIBankHDFC BANK LTD.BranchSECTOR-62 NOIDABranch addressSECTOR-62, NOIDA -201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0002649Branch emailashish.malhotra(at)hdfcbank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
CIVITECH BUILDCON PRIVATE LIMITED (CBPL) SEPARATE ACCOUNT FOR CIVITECH SANTONIBankHDFC BANK LTDBranchSECTOR-62, NOIDABranch addressSECTOR-62, NOIDA, 201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0002649Branch emailashish.malhotra(at)hdfcbank.com
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
CIVITECH BUILDCON PRIVATE LIMITED (CBPL)TRANSACTION ACCOUNT FOR PROJECT CIVITECH SANTONIBankHDFC BANK LTD.BranchSECTOR-62, NOIDABranch addressSECTOR-62, NOIDA, 201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0002649Branch emailashish.malhotra(at)hdfcbank.com
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
15 Oct 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about civitech Santoni

Is civitech Santoni RERA registered?

Yes. civitech Santoni is registered with UPRERA under registration number UPRERAPRJ364474, registered on 31 Jul 2023. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for civitech Santoni?

The completion date filed with UPRERA is 9 Apr 2028. No completion certificate is on record yet.

Who is the builder of civitech Santoni?

Civitech Buildcon Private Limited is the promoter entity that filed civitech Santoni with UPRERA (promoter RERA ID UPRERAPRM192249). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does civitech Santoni have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is civitech Santoni located?

civitech Santoni is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in civitech Santoni?

The unit plan filed with UPRERA lists OTHER and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in civitech Santoni?

The approved unit plan filed with UPRERA runs from 3 to 589 m² of carpet area (about 32 to 6,338 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in civitech Santoni?

The approved unit plan describes 1 block and 747 units of which 452 are homes and 295 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is civitech Santoni?

About 200 units per acre: 747 planned units across 3.73 acres (15,089 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗