PALM OLYMPIA PH 2

UPRERARegistered

PALM OLYMPIA PH 2 is a RERA-registered residential project by Sam India Abhimanyu Housing in Gautam Budh Nagar (RERA ID UPRERAPRJ308567). Registered with a completion deadline of 30 Apr 2028.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q4'24
—Q1'25
—Q2'25
46%Q3'25
53%Q4'25
73%Q1'26
76%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ308567
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGreater Noida Authority
Proposed start1 Jul 2023
Project duration58 months
AddressGautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typePartnership Firm
Applicant addressPlot No Gh-02 Sector-16C Greater Noida (West) Greater Noida, Gautam Budha Nager UP 201308
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    PLG/BP SM-15OCT-2020 9110

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered22 Jul 2023
Original completion30 Apr 2028
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹1,70,500
Sanctioning authorityGreater Noida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors1,065 · 6 · 33 (units from plan)
Homes · commercial units937 · 128 (shops and offices filed in the same plan)
  • 3 BHK645 61%
  • 2 BHK288 27%
  • SHOP128 12%
  • PENTHOUSE4 <1%
ConfigurationUnitsCarpet area
3 BHK64574-100
PENTHOUSE4173-191
2 BHK28863
SHOP1284-95
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Palm Olympia Commercial · SHOP21284-95
Tower -C1 · 3 BHK, PENTHOUSE3017489-178
Tower -D1 · 2 BHK, 3 BHK3219063-74
Tower -D2 · 2 BHK, 3 BHK3219063-74
Tower -D3 · 2 BHK, 3 BHK3219363-74
Tower-B1 · 3 BHK, PENTHOUSE33190100-191
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Mr. Vishal Sharma
License CA-98/23261
B 421 New Friends Colony Delhi 110065
Engineer
Mr. V D Sharma
B 24 Sec 67 Noida Gautam Budh Nagar UP 210301
Contractor
Sam India Abhimanyu Housing
GH-02 Sec-16C Greater Noida West GautamBudh Nagar UP
Sr.Development work declared to RERA
1Demarcation of Plots
Plot area of palm Olympia phase-II is 33,050 Sq.mt and is part of Total Plot Area 101264 sq. mt at Gh-02, Sec- 16C, Greater Noida (West) U.P allotted by Greater Noida Authority. The Demarcation of total plot area and palm Olympia Phase-II plot is attached with layout plan.
2Boundary Wall
1500 mm high boundary wall shall be constructed with Rcc and brickwork as per structural design.
3Road Work
6 Mtr wide Rcc road with top finish with trimix/ interlocking block road with intermittent Tile/ Stone paving shall constructed wherever required subgrade with GSB shall be made as per design.
4Footpaths
1500 mm wide pathways finish with paver/ stone/ trimix footpath wherever required shall be provided. The thickness of tiles shall be 40mm (minimum).
5Water Supply Including Drinking Water Facilities
GNIDA Water supply shall be collected in the water reservoirs. Terrace Tanks shall be filled with pumps to give supply to the units/ flats. The tanks shall be constructed as per structural design. proper Air valve, Sluice Valve in chamber/s, scour valve, fire Hydrants/ out lets and fire tanks as per design requirement shall be provided.
6Sewer System
Rcc hume pipe of adequate size with manhole, chambers shall be provided. The sewer lines shall be laid in desired slopes as per available invert level.
7Drain
Rcc hume pipe with manhole, chambers with Rain Water Harvesting Shall be provided . The number of catch basin shall be provided as per design requirement based on run off.
8Parks
Landscape with civil work with masonry and stone, horticulture work and various types of plantation, shrubs shall be provided. Native plants shall be planted. Recreational sports area shall also be provided.
9Tree Planting
Tree Planting along parts of the road in project shall be provided. Avenue trees with ornamental designs shall be created.
10Design For Electric Supply Including Street Lighting
Pole light will be provided along with internal road side. Design for electric supply has been uploaded. HT and LT cables shall be laid from source to substation user ends. The lights shall be fixed as per requirement of use level as per guide lines.
11Community Buildings
Community Building shall be provided . It will be a common facility for all phases of palm Olympia project as per approved building plan. It will have health facilities and sports area.
12Treatment and Disposal System of Sewage and Sullage water
S.T.P shall be provided. It will be provided with collection tank. The treated water shall be used for irrigation purposes. surplus flow shall be discharged to the municipal drains.
13Solid Waste Management And Disposal System
Organic Waste convertor and collection bins shall be installed. Garbage collection area shall be marked.
14Water Conservation System
Adequate rain water harvesting pits are to be provided to allow the surface flow to percolate below in the earth.
15Energy Management System Including Use of Renewable Energy
Solar panels at roof top as per norms shall be provided . LED lights shall be used to conserve the energy.
16Fire Protection And Fire Safety System
As per approved fire drawing smoke detector fire alarm systems etc. Shall be installed. Fire tender path shall be constructed as per fire norms. Fire fighting system with fire pumps of adequate capacity and water storage tanks shall be provided.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Provided as per approved building plan .
18Emergency Evacuation Services
As per approved layout. Staircases shall be provided in basement/towers to exit in case of emergency/fir and/ or any natural calamity.
19Other Miscellaneous Work
Guard room, entrance and exit gates shall be provided as per approved layout plan for the whole project/ phases.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 30 Apr 2028.

Sanctioned by Greater Noida Authority · 33,050 sqm of land · an approved plan of 6 blocks and 1065 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
PLG/BP SM-15OCT-2020 91101 May 202330 Apr 202830 Apr 203330 Apr 2028
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

15 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
GH02, Sector 16C33050Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 23733
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · Details of All Approved Floor Plans
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · All Approved Floor Plans Part 1
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · All Approved Floor Plans Part 2
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New21 Jun 2023 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New21 Jun 2023 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New21 Jun 2023 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New21 Jun 2023 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New21 Jun 2023 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New21 Jun 2023 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New21 Jun 2023 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New21 Jun 2023 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New21 Jun 2023 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New21 Jun 2023 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New21 Jun 2023 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New21 Jun 2023 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New21 Jun 2023 ↗

Quarterly progress reports

13 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

13 quarterly progress reports are on file with UPRERA, covering 2023-Q2 to 2026-Q2.

QuarterConstructionCertificates
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q246%CA ↗ · Arch ↗ · Eng ↗
2025-Q353%CA ↗ · Arch ↗ · Eng ↗
2025-Q473%CA ↗ · Arch ↗ · Eng ↗
2026-Q176%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameSam India Abhimanyu Housing
RolePromoter · current
RERA IDUPRERAPRM236650
PANABUFS6733R
CIN / TANMRTS07329A
Registered addressPlot No Gh-02 Sector-16C Greater Noida (West) Greater Noida, Gautam Budha Nager UP 201308
RERA contact
Registered since2023
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
SIAH COLLECTION A/C FOR PALMOLYMPIA PH2BankHDFC BANK LTDBranchGAUR CITY 1Branch addressSHOP NO 4-9, GAUR CITY 1 AIG PARK, GEATER NOIDA WEST GAUTAM BUDDH NAGER-201009Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0005212
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
SIAH SEPARATE A/C FOR PALMOLYMPIA PH2BankHDFC BANK LTDBranchGAUR CITY 1Branch addressSHOP NO 4-9 GAUR CITY 1 AIG PARK, GEATER NOIDA WEST GAUTAM BUDDH NAGAR -201009Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0005212
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
SIAH TRANSACTION A/C FOR PALMOLYMPIA PH2BankHDFC BANK LTDBranchGAUR CIYT 1Branch addressSHOP NO 4-9 GAUR CITY 1 AIG PARK, GEATER NOIDA WEST GAUTAM BUDDH NAGAR -201009Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0005212
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

3 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
13 Oct 2026
Promoter’s complaints tally (all their projects)1 (Under Registration - 1 ) → 1 (Under Registration - 0 )
changed in Estanzo’s record
25 Sept 2026
Promoter’s complaints tally (all their projects)0 (Under Registration - 0 ) → 1 (Under Registration - 1 )
changed in Estanzo’s record
19 Sept 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 25 Sept 2026 · 2 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about PALM OLYMPIA PH 2

Is PALM OLYMPIA PH 2 RERA registered?

Yes. PALM OLYMPIA PH 2 is registered with UPRERA under registration number UPRERAPRJ308567, registered on 22 Jul 2023. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for PALM OLYMPIA PH 2?

The completion date filed with UPRERA is 30 Apr 2028. No completion certificate is on record yet.

Who is the builder of PALM OLYMPIA PH 2?

Sam India Abhimanyu Housing is the promoter entity that filed PALM OLYMPIA PH 2 with UPRERA (promoter RERA ID UPRERAPRM236650). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does PALM OLYMPIA PH 2 have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is PALM OLYMPIA PH 2 located?

PALM OLYMPIA PH 2 is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in PALM OLYMPIA PH 2?

The unit plan filed with UPRERA lists 3 BHK, PENTHOUSE, 2 BHK and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in PALM OLYMPIA PH 2?

The approved unit plan filed with UPRERA runs from 4 to 191 m² of carpet area (about 42 to 2,054 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in PALM OLYMPIA PH 2?

The approved unit plan describes 6 blocks and 1,065 units of which 937 are homes and 128 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is PALM OLYMPIA PH 2?

About 130 units per acre: 1,065 planned units across 8.17 acres (33,050 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗