Registered27 Jul 2017
Completed1 Feb 2020
Promised30 Jun 2022

Timeline

Promised completion30 Jun 2022
Revised completion30 Jun 2022
Actual completion1 Feb 2020
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹1,16,500
Project cost (in ₹ Lakhs)₹24,427 Lakhs
Project duration121 months
Project categoryResidential
Locality
Original start date13 Dec 2012
Proposed start date13 Dec 2012

Inventory

Total units614
Unit TypeUnitsCarpet Area (sqm)
1 BHK17133.78–49.06
2 BHK32639.63–80.38
3 BHK10197.51–111.23
SHOP1625.26–198.22

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9873973439
Emailsecretarial@eldecoproperties.com
Coordinator9818799307
AddressS-16, Second Floor, Eldeco Station 1, Site No. 1, Sector 12, Faridabad, Haryana-121007

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
NOIDA/MU.VA.NI./III-161/58913 Dec 201212 Dec 201730 Jun 202211 Dec 2022

Land Parcels

Khasra No.AreaPlot Type
00358330.65Plot

Approved Unit Plan

Unit plan rows on file397
Total flats (sum of rows)614
Total shops16
BlocksEdge, Inspire-1, Inspire-2, Inspire-3, Inspire-4
Floor types1 BHK, 2 BHK, 3 BHK, SHOP

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
15629 May 2007

Frequently Asked Questions

What is the RERA registration number of ELDECO AAMANTRAN(INSPIRE & EDGE?

The RERA registration number of ELDECO AAMANTRAN(INSPIRE & EDGE is UPRERAPRJ1916, as recorded on the UP-RERA portal.

What is the RERA status of ELDECO AAMANTRAN(INSPIRE & EDGE?

As reported by UP-RERA, the status of ELDECO AAMANTRAN(INSPIRE & EDGE is "Registered".

Where is ELDECO AAMANTRAN(INSPIRE & EDGE located?

As reported to UP-RERA, ELDECO AAMANTRAN(INSPIRE & EDGE is located at NOIDA, Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

Is ELDECO AAMANTRAN(INSPIRE & EDGE completed?

As reported to UP-RERA, ELDECO AAMANTRAN(INSPIRE & EDGE was completed on 1 Feb 2020.

Is ELDECO AAMANTRAN(INSPIRE & EDGE delayed?

Measured against the latest completion date reported to UP-RERA, ELDECO AAMANTRAN(INSPIRE & EDGE is on time.