Estanzo

Timeline Bar

Registered19 May 2021
Completed4 Mar 2024
Promised11 Feb 2026

Timeline

Promised completion11 Feb 2026
Revised completion11 Feb 2026
Actual completion4 Mar 2024
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹33,000
Project cost (in ₹ Lakhs)₹414 Lakhs
Project duration59 months
Project categoryCommercial
Locality
Original start date
Proposed start date1 Apr 2021

Inventory

Total units52
Unit TypeUnitsCarpet Area (sqm)
SHOP5211.87–122.38

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9670222298
Emailehil@eldecohousing.co.in
Coordinator9670222298
AddressShop No S-16, Second Floor, Eldeco Station 1, Site No.1, Faridabad sector 12, Faridabad 121007, Haryana India

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
197712 Feb 202111 Feb 202611 Feb 202610 Feb 2029

Land Parcels

Khasra No.AreaPlot Type
6386670Khasra

Approved Unit Plan

Unit plan rows on file23
Total flats (sum of rows)52
Total shops52
BlocksESA
Floor typesSHOP

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Eldeco Shaurya Arcade?

The RERA registration number of Eldeco Shaurya Arcade is UPRERAPRJ228336, as recorded on the UP-RERA portal.

What is the RERA status of Eldeco Shaurya Arcade?

As reported by UP-RERA, the status of Eldeco Shaurya Arcade is "Registered".

Where is Eldeco Shaurya Arcade located?

As reported to UP-RERA, Eldeco Shaurya Arcade is located at Sarojini Nagar, Lucknow, Uttar Pradesh.

Is Eldeco Shaurya Arcade completed?

As reported to UP-RERA, Eldeco Shaurya Arcade was completed on 4 Mar 2024.

Is Eldeco Shaurya Arcade delayed?

Measured against the latest completion date reported to UP-RERA, Eldeco Shaurya Arcade is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026