Eldeco South Block at Eldeco Shaurya is a RERA-registered residential project by ELDECO Housing and Industries Ltd. in Lucknow (RERA ID UPRERAPRJ641397). RERA status: Completed on 21 Oct 2022. UP-RERA flags this project "Default on QPR": it has not filed its mandatory quarterly progress report(s).
RERA status as reported: Completed.Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ641397 |
| Project category | Residential |
| Registration type | New |
| RERA status | Completed |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Lucknow Industrial Development Authority |
| Proposed start | 20 Jan 2019 |
| Project duration | 92 months |
| Address | Sarojini Nagar, Lucknow |
| Tehsil | Sarojini Nagar |
| Applicant type | Company |
| Applicant address | Shop No S-16, Second Floor, Eldeco Station 1, Site No.1, Faridabad sector 12, Faridabad 121007, Haryana India |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Building permit sanctioned
718
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Registered with RERA
Completion certificate filed
- to
Extension granted
“Six months extension in view of force majeure caused by covid-19 pandemic”
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 5 Mar 2019 |
| Original completion | 25 Feb 2026 |
| Revised completion | 24 Aug 2026 |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | 21 Oct 2022 |
| Registration fee | ₹20,000 |
| Sanctioning authority | Lucknow Industrial Development Authority |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots Site well demarcated with project boundary and surrounding roads fully constructed. |
| 2 | Boundary Wall two side constructed with road on one side. |
| 3 | Road Work 9 meter road network to be developed as per approval. 4.8 meter. carriageway with side footpaths proposed. |
| 4 | Footpaths CC/paver footpaths with space for drainage/services to be constructed. |
| 5 | Water Supply Including Drinking Water Facilities OHT constructed and water supply line to be laid as per design with 20mm connection to each villa. |
| 6 | Sewer System CC pipes to be laid connecting to main sewer line of the Township |
| 7 | Drain KC/U-drain along main roads with proper slope. |
| 8 | Parks All parks to have green cover with walking pavements and plantation. |
| 9 | Tree Planting 4.5 to 6 meter high trees along main roads. |
| 10 | Design For Electric Supply Including Street Lighting Complete street lighting with 7.5 meter high light poles |
| 11 | Community Buildings Club functional and is part of Township |
| 12 | Treatment and Disposal System of Sewage and Sullage water STP constructed and is part of Township |
| 13 | Solid Waste Management And Disposal System Already in place as part of Township |
| 14 | Water Conservation System Required Rain Water Harvesting have been proposed. |
| 15 | Energy Management System Including Use of Renewable Energy Solar back up to 25% street lighting proposed |
| 16 | Fire Protection And Fire Safety System With fire hydrants in main water supply line |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services NA |
| 18 | Emergency Evacuation Services Ext to 18 meter roads via 9 meter road |
| 19 | Other Miscellaneous Work NA |
Registered agents
37 agents
Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.
| Sr. | Agent | RERA registration |
|---|---|---|
| 1 | 360 REALTORS LLP | UPRERAAGT10868 |
| 2 | AMIT AGARWAL | UPRERAAGT11945 |
| 3 | ANIL KUMAR VERMA | UPRERAAGT14346 |
| 4 | ARTI TIWARI | UPRERAAGT14234 |
| 5 | ASA FINCAP ADVISORS LLP | UPRERAAGT10926 |
| 6 | bhupendra kumar singh | UPRERAAGT11056 |
| 7 | BIPIN CHANDRA PANT | UPRERAAGT13687 |
| 8 | Brijendra Singh | UPRERAAGT10496 |
| 9 | DAIWIK REALTORS | UPRERAAGT12075 |
| 10 | DEVENDRA VERMA | UPRERAAGT14290 |
| 11 | GOLDEN STAR REAL ESTATES | UPRERAAGT10303 |
| 12 | INDIABULLS INVESTMENT ADVISORS LIMITED | UPRERAAGT10238 |
| 13 | INVESTORS CARE INFRATECH PVT LTD | UPRERAAGT13542 |
| 14 | INVESTORS CLINIC INFRATECH PRIVATE LIMITED | UPRERAAGT10052 |
| 15 | KAUSHTUBH REALTY PRIVET LIMITED | UPRERAAGT13025 |
| 16 | Mr. Janardan Agarwal | UPRERAAGT10555 |
| 17 | OPAL PROPERTY SOLUTIONS PRIVATE LIMITED | UPRERAAGT13636 |
| 18 | Prem Prakash Khare | UPRERAAGT13677 |
| 19 | Rajni Dawra | UPRERAAGT13519 |
| 20 | REALTYSTRUCTURE INFRATECH PRIVATE LIMITED | UPRERAAGT10144 |
| 21 | REETA MAURYA C/O SHIVA ASSOCIATE | UPRERAAGT13650 |
| 22 | RELIVE SOLUTIONS PVT. LTD. | UPRERAAGT10078 |
| 23 | SANJEEV KUMAR BANKA | UPRERAAGT10894 |
| 24 | SDR INFRA BUILD PVT LTD | UPRERAAGT11062 |
| 25 | SHAH MOHSIN KAMAL | UPRERAAGT14208 |
| 26 | SHREE SAI ASSOCIATES | UPRERAAGT11846 |
| 27 | SHREE SHRADDHA PROPERTIES | UPRERAAGT10301 |
| 28 | SILVER EDGE REAL ESTATE SOLUTION | UPRERAAGT12168 |
| 29 | Smart InfraReality Private Limited | UPRERAAGT10057 |
| 30 | SMC Real Estate Advisors Private Limited | UPRERAAGT10113 |
| 31 | SQUARE YARDS CONSULTING PRIVATE LIMITED | UPRERAAGT10119 |
| 32 | Vajrakaya Buildwell Private Limited | UPRERAAGT12913 |
| 33 | VANDANA AGARWAL | UPRERAAGT13353 |
| 34 | Varun Properties Inc. | UPRERAAGT11985 |
| 35 | VIMLESH PRATAP SINGH | UPRERAAGT11674 |
| 36 | VIRENDRA KUMAR DEWAN | UPRERAAGT13205 |
| 37 | VISHESH SRIVASTAVA | UPRERAAGT11416 |
Permits & extensions
1 permit
An approval and the date it runs to - not proof the work matching it was done.
1 sanctioning permit is on record with UPRERA, valid to 26 Feb 2023.
Sanctioned by Lucknow Industrial Development Authority · 2,921 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| 718 | 27 Feb 2018 | 26 Feb 2023 | 25 Feb 2026 | 25 Feb 2026 |
| Document | File |
|---|---|
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | no file published |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | no file published |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | no file published |
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
UPRERA’s record carries 1 completion extension for this project, running to 24 Aug 2026.
| # | Granted from | Extended upto | Note |
|---|---|---|---|
| 1 | 25 Feb 2026 | 24 Aug 2026 | Six months extension in view of force majeure caused by covid-19 pandemic |
Land & documents
20 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 848 | 2530 | Khasra |
| 627 | 4049.75 | Khasra |
| Sale deed · 14715 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 15144 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 4048 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 19201 The registered deed by which the promoter bought the land. | PDF ↗ |
| Registry document · 63 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | not reported | — |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | not reported | — |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | not reported | — |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | not reported | — |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | not reported | — |
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | New | 14 Feb 2019 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 18 Feb 2019 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 18 Feb 2019 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | New | 18 Jan 2019 ↗ |
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | New | 18 Jan 2019 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 18 Jan 2019 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 18 Jan 2019 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 18 Jan 2019 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 19 Jan 2019 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 19 Jan 2019 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 19 Feb 2019 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 19 Feb 2019 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 19 Feb 2019 ↗ |
Quarterly progress reports
14 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
14 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2023-Q2.
| Quarter | Construction | Certificates |
|---|---|---|
| 2020-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | ELDECO Housing and Industries Ltd. |
| Role | Promoter · current |
| RERA ID | UPRERAPRM21 |
| PAN | AAACE4554G |
| CIN / TAN | L45202UP1985PLC099376 |
| Name of chairman | Mr Pankaj Bajaj |
| Registered address | Shop No S-16, Second Floor, Eldeco Station 1, Site No.1, Faridabad sector 12, Faridabad 121007, Haryana India |
| RERA contact | |
| Registered since | 2017 |
| Legal name | SWARG CONSTRUCTIONS PRIVATE LIMITED |
| Role | Co-promoter |
| Applicant type | Company |
| Address | Eldeco Corporate Chamber 1, 2nd Floor, Vibhuti Khand, Gomti Nagar, Lucknow-226010 |
| RERA contact |
| Legal name | SAMARPIT CONSTRUCTIONS PRIVATE LIMITED |
| Role | Co-promoter |
| Applicant type | Company |
| Address | Eldeco Corporate Chamber 1, 2nd Floor, Vibhuti Khand, Gomti Nagar, Lucknow 226010 |
| RERA contact |
Nearby projects
Lucknow
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | ELDECO HOUSING AND INDUSTRIES LTDBankICICI BankBranchIndira Nagar,A/C no.IFSCICIC0000591 |
What has changed on this record
1 movement
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026.
| Field | What moved | Observed |
|---|---|---|
| Promoter’s complaints tally (all their projects) | 17 (Under Registration - 1 ) → 17 (Under Registration - 0 ) changed in Estanzo’s record | 23 Aug 2026 |
| Promoter’s complaints tally (all their projects) | changed in Estanzo’s record · 23 Aug 2026 |
What to verify and what to ask
2 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
- No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.
Common questions about Eldeco South Block at Eldeco Shaurya
Is Eldeco South Block at Eldeco Shaurya RERA registered?
Yes. Eldeco South Block at Eldeco Shaurya is registered with UPRERA under registration number UPRERAPRJ641397, registered on 5 Mar 2019. Estanzo reproduces that filing; it does not verify the work behind it.
Has Eldeco South Block at Eldeco Shaurya been completed?
UPRERA lists Eldeco South Block at Eldeco Shaurya as completed, with a completion certificate dated 21 Oct 2022, against a filed deadline of 24 Aug 2026.
Who is the builder of Eldeco South Block at Eldeco Shaurya?
ELDECO Housing and Industries Ltd. is the promoter entity that filed Eldeco South Block at Eldeco Shaurya with UPRERA (promoter RERA ID UPRERAPRM21). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Why does Eldeco South Block at Eldeco Shaurya show "default on QPR"?
UPRERA flags this project as in default on quarterly progress reporting - the promoter has not filed one or more mandatory quarterly progress reports. The flag is the authority's, not Estanzo's.
Has UPRERA granted Eldeco South Block at Eldeco Shaurya more time to complete?
UPRERA's record carries 1 completion extension for Eldeco South Block at Eldeco Shaurya, the latest running to 24 Aug 2026. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.
Does Eldeco South Block at Eldeco Shaurya have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is Eldeco South Block at Eldeco Shaurya located?
Eldeco South Block at Eldeco Shaurya is registered in Lucknow, as filed with UPRERA.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗