EWS PMAY

UPRERARegistered

EWS PMAY is a RERA-registered residential project by ATS Grand Realtors Private Limited in Ghaziabad (RERA ID UPRERAPRJ962888). Registered with a completion deadline of 31 Mar 2026.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Jan–Mar 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q2'24
—Q3'24
—Q4'24
—Q1'25
—Q2'25
100%Q3'25
97%Q4'25
100%Q1'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ962888
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGhaziabad Development Authority
Proposed start1 Nov 2019
Project duration77 months
AddressGhaziabad, Ghaziabad
TehsilGhaziabad
Applicant typeCompany
Applicant addressATS Tower Plot No -16 Sector 135 Noida 201305
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. valid to

    Permit revalidated

    202 MAP No-10/PMAY GDA/M.P./201820

  2. 2 building permits sanctioned

  3. Registered with RERA

  4. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  5. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  6. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  7. to

    Extension granted

  8. to

    Extension granted

  9. to

    Extension granted

  10. Completion certificate filed

  11. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered24 Oct 2019
Original completion31 Oct 2021
Revised completion31 Mar 2026
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary11 Jul 2025
Registration fee₹1,01,000
Sanctioning authorityGhaziabad Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors799 · 8 · 6 (units from plan)
Homes · commercial units789 · 10 (shops and offices filed in the same plan)
  • 1 BHK789 99%
  • SHOP10 1%
ConfigurationUnitsCarpet area
1 BHK78923
SHOP109-11
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Block 1 · 1 BHK410423
Block 2 · 1 BHK615023
Block 3 · 1 BHK66623
Block 4 · 1 BHK615023
Block 5 · 1 BHK66623
Block 6 · 1 BHK615023
Block 7 · 1 BHK66623
Block 8 · 1 BHK, SHOP4479-23
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Karan Singh
License CA/2012/55100
ATS Tower Plot No- 16 Sector 135 Noida 201301
Engineer
Kamal Kumar Sabharwal
HS-25, 2nd floor (level-3), Kailash Colony Market, New Delhi-110048
Contractor
Self
ATS Tower Plot No- 16 Sector 135 Noida 201301
Sr.Development work declared to RERA
1Demarcation of Plots
As/ Approved Building Plan
2Boundary Wall
RCC/ Brick work in Boundary Wall
3Road Work
WBM with Paver
4Footpaths
Anti Skid tile/Paver
5Water Supply Including Drinking Water Facilities
Ghaziabad Authority will supply water supply to entire society and that will further be supplied to dwelling units after filtration from centralized plant
6Sewer System
Sewage from all unit will be thru man hole system
7Drain
Drainage Thru network of pipe & catch basins to dispersion trenches with overflow to authority drain
8Parks
As/Approved Building Plan
9Tree Planting
As/Approved Building Plan
10Design For Electric Supply Including Street Lighting
Through LT & Sub -Distribution
11Community Buildings
NA
12Treatment and Disposal System of Sewage and Sullage water
Overflow to authority sewer line & connect with the authority STP for treatment
13Solid Waste Management And Disposal System
Solid Waste will be segregated & organic waste will treated thru OWC
14Water Conservation System
Dispersion trenches are proposed to harvest rain water
15Energy Management System Including Use of Renewable Energy
LED lights & solar panel for energy saving management
16Fire Protection And Fire Safety System
Integrated Fire Alarm system as per NBC
17Social Infrastructure And Other Public Amenities Including Public Health Services
Junior High School (Primary School With Anganbadi)
18Emergency Evacuation Services
Fire Escape staircase as per NBC
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 19 Apr 2024. 1 of them carries a revalidation, valid to 19 Apr 2027.

Sanctioned by Ghaziabad Development Authority · 19,110 sqm of land · an approved plan of 8 blocks and 799 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
202 Map No-10/PMAY GDA/M.P/201820 Apr 201919 Apr 202419 Apr 202731 Oct 2021—
202 MAP No-10/PMAY GDA/M.P./20182020 Apr 201919 Apr 202419 Apr 202728 Jan 202420 Apr 2019
valid to 19 Apr 2027
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 4 completion extensions for this project, the latest running to 31 Mar 2026.

#Granted fromExtended uptoNote
131 Oct 202130 Apr 2022Six months extension in view of force majeure caused by covid-19 pandemic
230 Apr 202229 Apr 2023—
329 Apr 202328 Jan 2024—
428 Jan 202431 Mar 2026—

Land & documents

17 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
3398294.18Khasra
3403981.87Khasra
3492148.95Khasra
3504684.8Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · 10259
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 10161
The registered deed by which the promoter bought the land.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New25 Sept 2019 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New25 Sept 2019 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New25 Sept 2019 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New25 Sept 2019 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New5 Oct 2019 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New5 Oct 2019 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New5 Oct 2019 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New5 Oct 2019 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New25 Sept 2019 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New25 Sept 2019 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New25 Sept 2019 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New25 Sept 2019 ↗

Quarterly progress reports

24 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

24 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2025-Q4.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q2100%CA ↗ · Arch ↗ · Eng ↗
2025-Q397%CA ↗ · Arch ↗ · Eng ↗
2025-Q4100%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2025-Q4. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameATS Grand Realtors Private Limited
RolePromoter · current
RERA IDUPRERAPRM76077
PANAAOCA3392A
CIN / TANU45309DL2016PTC298247
Name of chairmanGetamber Anand
Registered addressATS Tower Plot No -16 Sector 135 Noida 201305
RERA contact
Registered since2019
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Ghaziabad

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
ATS Grand Realtors Pvt Ltd PMAY RERA AccountBankKotak Mahindra BankBranchNoida-Sector 18A/C no.IFSCKKBK0000181
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)24 (Under Registration - 1 ) → 24 (Under Registration - 0 )
changed in Estanzo’s record
21 Sept 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 21 Sept 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about EWS PMAY

Is EWS PMAY RERA registered?

Yes. EWS PMAY is registered with UPRERA under registration number UPRERAPRJ962888, registered on 24 Oct 2019. Estanzo reproduces that filing; it does not verify the work behind it.

Has EWS PMAY been completed?

UPRERA still lists EWS PMAY as Registered, so it is not shown as completed here. A completion certificate dated 11 Jul 2025 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of EWS PMAY?

ATS Grand Realtors Private Limited is the promoter entity that filed EWS PMAY with UPRERA (promoter RERA ID UPRERAPRM76077). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted EWS PMAY more time to complete?

UPRERA's record carries 4 completion extensions for EWS PMAY, the latest running to 31 Mar 2026. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does EWS PMAY have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is EWS PMAY located?

EWS PMAY is registered in Ghaziabad, as filed with UPRERA.

What configurations are available in EWS PMAY?

The unit plan filed with UPRERA lists 1 BHK and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in EWS PMAY?

The approved unit plan filed with UPRERA runs from 9 to 23 m² of carpet area (about 99 to 246 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in EWS PMAY?

The approved unit plan describes 8 blocks and 799 units of which 789 are homes and 10 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is EWS PMAY?

About 169 units per acre: 799 planned units across 4.72 acres (19,110 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗