FOREST WALK PHASE-1

UPRERARegistered

FOREST WALK PHASE-1 is a RERA-registered residential project by SRSD BUILDCON VENTURE LLP in DASNA, Ghaziabad (RERA ID UPRERAPRJ658961). Registered with a completion deadline of 30 Jun 2027.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
8%Q2'25
14%Q3'25
24%Q4'25
36%Q1'26
46%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ658961
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGhaziabad Development Authority
Proposed start9 May 2025
Project duration26 months
AddressKHASRA NO. 1839, 1840, 1841,1848,1849,1850,1854,1858,1859,1861,1861,1877,1879,1880,1881,1882,1883,1884,1885,1886,1887,1888,1889,1890,1891,1892,1893,NH-24, VILLAGE DASNA, NEAR EASTERN PERIPHERAL EXPRESSWAY, DASNA, Ghaziabad, Ghaziabad
TehsilGhaziabad
Applicant typeLimited Liability Partnership (LLP)
Applicant addressA-15, 4TH FLOOR, SECTOR-136, GAUTAM BUDDHA NAGAR, UTTAR PRADESH- 201301
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    GDA/LD/24-25/0612

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered27 Aug 2025
Original completion30 Jun 2027
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹2,02,500
Sanctioning authorityGhaziabad Development Authority

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
DESIGN FORUM INTERNATIONAL
License CA/2020/123819
K-7, KAILASH COLONY, NEW DELHI
Engineer
NNC DESIGN INTERNATIONAL
G-70, 2ND FLOOR, JASWANT PLAZA, NEAR KALINDI KUNJ, MAIN SARITA VIHAR ROAD, OKHLA, NEW DELHI- 110025
Contractor
SRSD BUILDCON VENTURE LLP
A-15, 4TH FLOOR, SECTOR-136, GAUTAM BUDDHA NAGAR, UTTAR PRADESH
Sr.Development work declared to RERA
1Demarcation of Plots
Total 99 Plots have been demarcated as per map approved by the Ghaziabad Development Authority.
2Boundary Wall
Boundary Wall is not applicable here this is the first phase of project falling within the total project land.
3Road Work
Total 1360 Running Meters Road to be built with Pavers Blocks
4Footpaths
Total 204 running Meter footpaths will be built up using Paver Blocks as per Design
5Water Supply Including Drinking Water Facilities
Water to be provided by the GDA and developer will make over head tank in at each villas.
6Sewer System
Main Sewer Line has been design under grounded as per GDA Plans and finally it will be connect to STP for treating the sewage. Sewerage Line to be connect to the Centralized STP.
7Drain
Drainage System will be underground and will be connected to the main sewer.
8Parks
Park Landscape has been design as per approved Plan
9Tree Planting
Tree Planting has been design as per GDA Plan.
10Design For Electric Supply Including Street Lighting
Single Feeder shall be taken from Paschimanchal Vidut Vitran Nigam Limited (PVVNL) and connected to the central substation and the entire project shall have street Light.
11Community Buildings
Not applicable
12Treatment and Disposal System of Sewage and Sullage water
STP facilities shall be installed centralized and all sewage will be connected to the centralized STP. The treated water shall be used for flushing, irrigation, car wash, pathways cleaning.
13Solid Waste Management And Disposal System
The Project shall have the waste segregation area which will be set up as per approved layout plan.
14Water Conservation System
Using Water efficient appliances, recycling water to use on Plants
15Energy Management System Including Use of Renewable Energy
Not Applicable
16Fire Protection And Fire Safety System
Not Applicable
17Social Infrastructure And Other Public Amenities Including Public Health Services
Not Applicable
18Emergency Evacuation Services
Not Applicable
19Other Miscellaneous Work
Other Miscellaneous work if any to compile with the As per approved Project Plan.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 8 May 2030.

Sanctioned by Ghaziabad Development Authority · 39,431 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
GDA/LD/24-25/06129 May 20258 May 20308 May 203330 Jun 2027
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

43 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
184132.92Khasra
1848547.63Khasra
184934.70Khasra
18501006.53Khasra
18541510.23Khasra
185851.22Khasra
1859462.01Khasra
1861773.08Khasra
1879586.59Khasra
1880978.35Khasra
1881190.21Khasra
1882806.74Khasra
18835518.92Khasra
1884544.85Khasra
18851690.20Khasra
18864815.76Khasra
18871375.93Khasra
18882485.09Khasra
18902618.01Khasra
18913678.31Khasra
18921645.59Khasra
18935681.82Khasra
1840K575.87Khasra
1839K1782.72Khasra
1877KHA38.28Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 8386
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
not reported—
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New4 Jul 2025 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New8 Aug 2025 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New4 Jul 2025 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New4 Jul 2025 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New4 Jul 2025 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New4 Jul 2025 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New22 Jul 2025 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New22 Jul 2025 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New22 Jul 2025 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New4 Jul 2025 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New22 Jul 2025 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New22 Jul 2025 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New26 Jul 2025 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New8 Aug 2025 ↗

Quarterly progress reports

5 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

5 quarterly progress reports are on file with UPRERA, covering 2025-Q1 to 2026-Q1.

QuarterConstructionCertificates
2025-Q18%CA ↗ · Arch ↗ · Eng ↗
2025-Q214%CA ↗ · Arch ↗ · Eng ↗
2025-Q324%CA ↗ · Arch ↗ · Eng ↗
2025-Q436%CA ↗ · Arch ↗ · Eng ↗
2026-Q146%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameSRSD BUILDCON VENTURE LLP
RolePromoter · current
RERA IDUPRERAPRM370526
PANAFCFS8812D
CIN / TANMRTS29114B
Registered addressA-15, 4TH FLOOR, SECTOR-136, GAUTAM BUDDHA NAGAR, UTTAR PRADESH- 201301
RERA contact
Registered since2025
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Ghaziabad

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
SRSD FOREST WALK PHASE-1 COLL ACCTBankHDFC BANK LIMITEDBranchRDC RAJNAGAR, GHAZIABADBranch addressD-44, RDC RAJNAGAR, GHAZIABAD, UTTAR PRADESH- 201001Branch districtGhaziabad, Uttar PradeshA/C no.IFSCHDFC0000153Branch emailATULR.KUMAR@HDFCBANK.COM
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
SRSD FOREST WALK PHASE 1 SEP ACCTBankHDFC BANK LIMITEDBranchRDC RAJNAGAR, GHAZIABADBranch addressD-44, RDC RAJNAGAR, GHAZIABAD, UTTAR PRADESH-201001Branch districtGhaziabad, Uttar PradeshA/C no.IFSCHDFC0000153
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
SRSD FOREST WALK PHASE -1 TRANS ACCTBankHDFC BANK LIMITEDBranchRDC RAJNAGAR, GHAZIABADBranch addressD-44, RDC RAJNAGAR, GHAZIABAD, UTTAR PRADESH- 201001Branch districtGhaziabad, Uttar PradeshA/C no.IFSCHDFC0000153
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

2 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about FOREST WALK PHASE-1

Is FOREST WALK PHASE-1 RERA registered?

Yes. FOREST WALK PHASE-1 is registered with UPRERA under registration number UPRERAPRJ658961, registered on 27 Aug 2025. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for FOREST WALK PHASE-1?

The completion date filed with UPRERA is 30 Jun 2027. No completion certificate is on record yet.

Who is the builder of FOREST WALK PHASE-1?

SRSD BUILDCON VENTURE LLP is the promoter entity that filed FOREST WALK PHASE-1 with UPRERA (promoter RERA ID UPRERAPRM370526). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does FOREST WALK PHASE-1 have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is FOREST WALK PHASE-1 located?

FOREST WALK PHASE-1 is registered in DASNA, Ghaziabad, as filed with UPRERA.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗