Registered22 Dec 2020
Completed3 Jun 2024
Promised31 Jul 2025

Timeline

Promised completion31 Jul 2025
Revised completion31 Jul 2025
Actual completion3 Jun 2024
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹48,500
Project cost (in ₹ Lakhs)₹199 Lakhs
Project duration60 months
Project categoryResidential
Locality
Original start date
Proposed start date14 Aug 2020

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeIndividual
Mobile7007636985
Emailgurdeepchawla81@gmail.com
Coordinator7007636985
AddressSarv Nagar, C.P. Mission Compound nearJar Pahad, Jhansi

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
493/J.D.A.-TALPAT MANCHITRA-(2020-2021)13 Aug 202012 Aug 202531 Jul 202512 Aug 2028

Land Parcels

Khasra No.AreaPlot Type
6088638Khasra

Frequently Asked Questions

What is the RERA registration number of The Pitambra Town?

The RERA registration number of The Pitambra Town is UPRERAPRJ774076, as recorded on the UP-RERA portal.

What is the RERA status of The Pitambra Town?

As reported by UP-RERA, the status of The Pitambra Town is "Registered".

Where is The Pitambra Town located?

As reported to UP-RERA, The Pitambra Town is located at Jhansi, Jhansi, Uttar Pradesh.

Is The Pitambra Town completed?

As reported to UP-RERA, The Pitambra Town was completed on 3 Jun 2024.

Is The Pitambra Town delayed?

Measured against the latest completion date reported to UP-RERA, The Pitambra Town is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026