Estanzo

Timeline Bar

Registered31 Jul 2017
Promised21 Dec 2022
Today3 Aug 2026

Timeline

Promised completion21 Dec 2022
Revised completion21 Dec 2022
Actual completion
Possession delay43 mo delay

Registration & Cost Details

Registration fee (in ₹)₹19,500
Project cost (in ₹ Lakhs)₹9,413 Lakhs
Project duration90 months
Project categoryCommercial
Locality
Original start date3 Jan 2016
Proposed start date3 Jan 2016

Inventory

Total units520
Unit TypeUnitsCarpet Area (sqm)
1 BHK6830.549–31.299
OTHER4526.97–1045.65

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9899987377
Emailavdeshinfotech@gmail.com
Coordinator9899987377
AddressPlot No. 6A, Tech Zone IV, Greater Noida West, Gautam Budh Nagar-201306

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
PLG(BP-3532)6808

Revalidated: PLG/BP-3532/6726 (10 Oct 2017)

10 Nov 20159 Nov 2020

Revalidated upto: 22 Dec 2022

21 Dec 202222 Dec 2022

Land Parcels

Khasra No.AreaPlot Type
Plot No. 6 A, Tech Zone IV, Greater Noida West41087Plot

Approved Unit Plan

Unit plan rows on file91
Total flats (sum of rows)520
BlocksA1, B, B1, C1, Centre Bldg A1, Centre Bldg B1, D, E, F, J
Floor types1 BHK, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Urbainia Trinity NX (phase II)?

The RERA registration number of Urbainia Trinity NX (phase II) is UPRERAPRJ6259, as recorded on the UP-RERA portal.

What is the RERA status of Urbainia Trinity NX (phase II)?

As reported by UP-RERA, the status of Urbainia Trinity NX (phase II) is "Registered".

Where is Urbainia Trinity NX (phase II) located?

As reported to UP-RERA, Urbainia Trinity NX (phase II) is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will Urbainia Trinity NX (phase II) be completed?

The latest completion date reported to UP-RERA for Urbainia Trinity NX (phase II) is 21 Dec 2022.

Is Urbainia Trinity NX (phase II) delayed?

Measured against the latest completion date reported to UP-RERA, Urbainia Trinity NX (phase II) is 43 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026