Estanzo

Timeline Bar

Registered31 Jul 2017
Promised9 Oct 2022
Today3 Aug 2026

Timeline

Promised completion9 Oct 2022
Revised completion9 Oct 2022
Actual completion
Possession delay46 mo delay

Registration & Cost Details

Registration fee (in ₹)₹10,000
Project cost (in ₹ Lakhs)₹4,723 Lakhs
Project duration88 months
Project categoryCommercial
Locality
Original start date3 Jan 2016
Proposed start date3 Jan 2016

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9899987377
Emailavdeshinfotech@gmail.com
Coordinator9899987377
AddressPlot No. 6A, Tech Zone IV, Greater Noida West, Gautam Budh Nagar-201306

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
PLG(BP-3532)6808

Revalidated: PLG/BP-3532/6726 (10 Oct 2017)

10 Nov 20159 Nov 2020

Revalidated upto: 9 Oct 2022

9 Oct 202221 Dec 2024

Land Parcels

Khasra No.AreaPlot Type
PLOT NO. 6A, TECH ZONE IV,GREATER NOIDA WEST41087Plot

Frequently Asked Questions

What is the RERA registration number of Urbainia Trinity NX (phase III)?

The RERA registration number of Urbainia Trinity NX (phase III) is UPRERAPRJ6307, as recorded on the UP-RERA portal.

What is the RERA status of Urbainia Trinity NX (phase III)?

As reported by UP-RERA, the status of Urbainia Trinity NX (phase III) is "Registered".

Where is Urbainia Trinity NX (phase III) located?

As reported to UP-RERA, Urbainia Trinity NX (phase III) is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will Urbainia Trinity NX (phase III) be completed?

The latest completion date reported to UP-RERA for Urbainia Trinity NX (phase III) is 9 Oct 2022.

Is Urbainia Trinity NX (phase III) delayed?

Measured against the latest completion date reported to UP-RERA, Urbainia Trinity NX (phase III) is 46 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026