Projects in Gautam Budh Nagar

964 RERA-registered projects · as reported by UPRERA

Cards Table
District: Gautam Budh Nagar ▾
AnyAgraAligarhAmrohaAyodhyaBahraichBandaBarabankiBareillyBastiBijnorBudaunBulandshahrChandauliEtahEtawahFirozabadGautam Budh NagarGhaziabadGondaGorakhpurHapurHardoiHathrasJaunpurJhansiKanpur NagarKushinagarLalitpurLucknowMathuraMauMeerutMirzapurMoradabadMuzaffarnagarPrayagrajRampurSaharanpurSambhalShahjahanpurSitapurSultanpurUnnaoVaranasi
Status: Any ▾
AnyRegisteredCompletedDe-registeredAbeyanceNCLTLapsedWithdrawn
Sort: Default ▾
DefaultMost delayedNewest registeredName A–Z
✕ ClearShowing 781–800 of 964
Registered
SOLITAIRIAN CITY - (SOLI-)PHASE-3
Promoter not reported·Gautam Budh Nagar
Units (plan)704
DeadlineJul 2024
Delay▲ 2 yr
Registered
SPECTRUM METRO
Promoter not reported·Gautam Budh Nagar
Units (plan)1,267
DeadlineNov 2024
Delay▲ 21 mo
Registered
SPECTRUM METRO BLOCK- A and E
Promoter not reported·Gautam Budh Nagar
Units (plan)1,550
DeadlineOct 2024
Delay▲ 21 mo
Registered
spectrum@Metro ( Phase-1)
Promoter not reported·Gautam Budh Nagar
Units (plan)655
DeadlineJun 2021
Delay▲ 5 yr
Registered
Spectrum@metro (Phase-3)
Promoter not reported·Gautam Budh Nagar
Units (plan)502
DeadlineDec 2023
Delay▲ 2 yr
Registered
Spectrum@metro (Phase-4)
Promoter not reported·Gautam Budh Nagar
Units (plan)751
DeadlineDec 2023
Delay▲ 2 yr
Registered
spectrum@metro(Phase-2)
Promoter not reported·Gautam Budh Nagar
Units (plan)118
DeadlineJun 2022
Delay▲ 4 yr
Registered
SPEEDWAY AVENUE
Promoter not reported·Gautam Budh Nagar
Units (plan)309
DeadlineJul 2026
Delay▲ 1 mo
Registered
SPEEDWAY AVENUE
Promoter not reported·Gautam Budh Nagar
Units (plan)273
DeadlineFeb 2019
Delay▲ 7 yr
Registered
Sports Complex
Promoter not reported·Gautam Budh Nagar
Units—
DeadlineApr 2026
Delay▲ 4 mo
Default on QPR
SPORTS VILLAGE (PHASE-I)
Promoter not reported·Gautam Budh Nagar
Units (plan)896
DeadlineJun 2021
Delay▲ 5 yr
Default on QPR
SPORTS VILLAGE (PHASE-II, VILLA)
Promoter not reported·Gautam Budh Nagar
Units—
DeadlineJun 2021
Delay▲ 5 yr
Default on QPR
SPORTS VILLAGE (PHASE-III, Commercial)
Promoter not reported·Gautam Budh Nagar
Units (plan)104
DeadlineJun 2023
Delay▲ 3 yr
Registered
SPORTSHOME
Promoter not reported·Gautam Budh Nagar
Units (plan)183
DeadlineJun 2022
Delay▲ 4 yr
Registered
SPORTSHOME PHASE II
Promoter not reported·Gautam Budh Nagar
Units (plan)183
DeadlineJun 2024
Delay▲ 2 yr
Registered
Spring Elmas
Promoter not reported·Gautam Budh Nagar
Units (plan)654
DeadlineDec 2029
Delay—
Registered
SPRING HOMES
Promoter not reported·Gautam Budh Nagar
Units (plan)310
DeadlineDec 2026
Delay—
Registered
SPRING MEADOWS
Promoter not reported·Gautam Budh Nagar
Units (plan)1,410
DeadlineSept 2020
Delay▲ 5 yr
Registered
STELLAR 1422 PHASE II
Promoter not reported·Sector-142, Noida
Units (plan)21
DeadlineMar 2028
Delay—
Registered
Stellar One Phase 1
Promoter not reported·Gautam Budh Nagar
Units (plan)588
DeadlineSept 2020
Delay▲ 5 yr