AVS HIGH STREET

UPRERARegistered

AVS HIGH STREET is a RERA-registered commercial project by NAKSHATR INFRATECH LLP in Uttar Pradesh (RERA ID UPRERAPRJ935006). Registered with a completion deadline of 13 Jul 2027.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q4'24
—Q1'25
—Q2'25
29.64%Q3'25
30.82%Q4'25
44.42%Q1'26
48.28%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ935006
Project categoryCommercial
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGhaziabad Development Authority
Proposed start15 Jul 2023
Project duration48 months
AddressHotel at kh. no 490,491,494,495,496,497, Noor Nagar Ghaziabad-201001
Applicant typePartnership Firm
Applicant addressP-52, Sector-23, Sanjay Nagar, Ghaziabad UTTAR PRADESH - 201001
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    HOTEL/04912/GDA/BP/21-22/0813/08052023

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered30 Dec 2023
Original completion
Revised completion13 Jul 2027
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹92,000
Sanctioning authorityGhaziabad Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors330 · 1 · 14 (units from plan)
Homes · commercial units219 · 111 (shops and offices filed in the same plan)
  • OTHER219 66%
  • SHOP111 34%
ConfigurationUnitsCarpet area
OTHER21926-63
SHOP11115-31
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
A · OTHER, SHOP1433015-63
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.The plan also files 316.34 m² for a OTHER, 516.36 m² for a OTHER, 256.87 m² for a OTHER and 8 other units like them, far outside the rest of that type, so the ranges above leave them out.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Gaurav Singla
License CA/2012/55623
First Floor, Shop No-87, Eros Mall, Indirapuram, Ghaziabad, Uttar Pradesh
Engineer
Rabi Akhtar
Ghaffar Manzil, Jamia Nagar, ND-25, Delhi
Contractor
Manoj Aggarwal
A-409, Logixtech Nova, sector-132, Noida, Uttar Pradesh-201304
Sr.Development work declared to RERA
1Demarcation of Plots
28.42;15.3"N 77.25"32.9"E
2Boundary Wall
CONSISTING HEIGHT (7FT) CONSISTING OF RCC AND BRICK WORK
3Road Work
All roads in the complex will be in combination of Trimix, concrete pavers of different colors, shape, thickness. roads will be laid over 0225mm water bound macadam.
4Footpaths
All Footpath in the Complex will be in combination of concrete pavers of different colors, shape and thickness of 65mm and 80mm laid over 150mm water bound macadam surface.
5Water Supply Including Drinking Water Facilities
Potable water supply from municipal water supply shall be collected in underground collection tank and pumped to overhead water tank. The supply of water to individual Units shall be from the said overhead water tanks.
6Sewer System
The Sewage will be collected through a soil pipeline arrangement, bends and inspection chambers leading to the sewage water treatment plant (STP) of the Project, and treated water will be used for irrigation and flushing purpose.
7Drain
Drains having a minimum width of 150 mm will be provided for collection and channelization of rain water ( Surface Run Off)
8Parks
Hard and Soft Landscape is done in park area with electrical lighting
9Tree Planting
The trees will be planted at all suitable locations of the project and along the boundary walls. The tree selection, flora and vegetation shall be as per the climatic conditions. Trees will be planted in a manner to ensure that there is no hindrance in the services/usage in the project.
10Design For Electric Supply Including Street Lighting
Street Light is directly operated BT solar panel installed on top floor of the building.
11Community Buildings
community building is not required on site as per GDA norms.
12Treatment and Disposal System of Sewage and Sullage water
Sewage shall be treated in Sewage Treatment Plant (STP) and thereafter treated water to be used for Flushing and irrigation.
13Solid Waste Management And Disposal System
Solid Waste to be collected from individual flats and stored in garbage room. Recyclable shall be processed in the compost machine to make compost. Non-recyclable waste shall be disposed of through approved agents.
14Water Conservation System
Rain water harvesting pit shall be provided for ground water recharging and overflow to be discharged in the municipal drains. Treated Sewage shall be used for irrigation and flushing.
15Energy Management System Including Use of Renewable Energy
Solar plant will be installed on top for conservation of electricity.
16Fire Protection And Fire Safety System
Sprinkler, Fire Doors, Yard Hydrants, smoke detector and fire alarm system will be provided as applicable.
17Social Infrastructure And Other Public Amenities Including Public Health Services
NOT APPLICABLE
18Emergency Evacuation Services
Fire tower is designed for evacuation services in building.
19Other Miscellaneous Work
Not Applicable
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 7 Jun 2028.

Sanctioned by Ghaziabad Development Authority · 8,134 sqm of land · an approved plan of 1 block and 330 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
HOTEL/04912/GDA/BP/21-22/0813/080520238 Jun 20237 Jun 20286 Jun 203114 Jul 2026
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 13 Jul 2027.

#Granted fromExtended uptoNote
113 Jul 2027—

Land & documents

18 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
4901093.33Khasra
491, 494, 495, 4966116.47Khasra
496KH130Khasra
497817.78Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 3289
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 10193
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 10189
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 3289
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Khatauni extract · 0000
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New24 Jul 2023 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New10 Jul 2023 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New10 Jul 2023 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New24 Jul 2023 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New10 Jul 2023 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New10 Jul 2023 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New10 Jul 2023 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New10 Jul 2023 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New24 Jul 2023 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New24 Jul 2023 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New10 Jul 2023 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New10 Jul 2023 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New10 Jul 2023 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New10 Jul 2023 ↗

Quarterly progress reports

13 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

13 quarterly progress reports are on file with UPRERA, covering 2023-Q2 to 2026-Q2.

QuarterConstructionCertificates
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q229.64%CA ↗ · Arch ↗ · Eng ↗
2025-Q330.82%CA ↗ · Arch ↗ · Eng ↗
2025-Q444.42%CA ↗ · Arch ↗ · Eng ↗
2026-Q148.28%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameNAKSHATR INFRATECH LLP
RolePromoter · current
RERA IDUPRERAPRM241468
PANAATFN2078G
CIN / TANMRTN06532B
Registered addressP-52, Sector-23, Sanjay Nagar, Ghaziabad UTTAR PRADESH - 201001
RERA contact
Registered since2023
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameAMIT KUMAR
RoleCo-promoter · current
RERA IDUPRERAPRM21727
Applicant typeIndividual
PANAADCV8074B
Registered address438/24 SUMAN VIHAR MUZAFFARNAGAR CITY , MUZAFFARNAGAR, UP -251002
RERA contact
Registered since2017
Legal nameAMAR NATH TYAGI
RoleCo-promoter
Applicant typeIndividual
Address339, NOOR NAGAR, GHAZIABAD, UTTAR PRADESH-201001
RERA contact
Legal nameBRAJESH
RoleCo-promoter
Applicant typeIndividual
AddressNoor Nagar, Sihani, Ghaziabad, Uttar Pradesh-201001
RERA contact
Legal nameSUDESH TYAGI
RoleCo-promoter
Applicant typeIndividual
Address341 NOOR NAGAR, SIHANI, GHAZIABAD, UTTAR PRADESH, 201001
RERA contact

Nearby projects

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
NAKSHATR INFRATECH LLP - COLLECTION ACCOUNT FOR AVS HIGH STREETBankKOTAK MAHINDRA BANKBranchRDC RAJ NAGAR GHAZIABADBranch addressRDC RAJ NAGAR GHAZIABADBranch districtGhaziabad, Uttar PradeshA/C no.IFSCKKBK0000677
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
NAKSHATR INFRATECH LLP - SEPARATE ACCOUNT FOR AVS HIGH STREETBankKOTAK MAHINDRA BANKBranchRDC RAJ NAGAR GHAZIABADBranch addressRDC RAJ NAGAR GHAZIABADBranch districtGhaziabad, Uttar PradeshA/C no.IFSCKKBK0000677Branch email0677_ghaziabad_referal at kotak.com
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
NAKSHATR INFRATECH LLP - RERA TRANSACTION ACCOUNT FOR AVS HIGH STREETBankKOTAK MAHINDRA BANKBranchRDC RAJ NAGAR GHAZIABADBranch addressRDC RAJ NAGAR GHAZIABADBranch districtGhaziabad, Uttar PradeshA/C no.IFSCKKBK0000677Branch email0677_ghaziabad_referal at kotak.com
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

3 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
18 Oct 2026
Revised completion date on file2026-07-14 → 2027-07-13
changed in Estanzo’s record
3 Sept 2026
Completion date promised at registration2026-07-14
no longer on the record
3 Sept 2026
When these facts last moved
Revised completion date on filechanged in Estanzo’s record · 3 Sept 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about AVS HIGH STREET

Is AVS HIGH STREET RERA registered?

Yes. AVS HIGH STREET is registered with UPRERA under registration number UPRERAPRJ935006, registered on 30 Dec 2023. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for AVS HIGH STREET?

The completion date filed with UPRERA is 13 Jul 2027. No completion certificate is on record yet.

Who is the builder of AVS HIGH STREET?

NAKSHATR INFRATECH LLP is the promoter entity that filed AVS HIGH STREET with UPRERA (promoter RERA ID UPRERAPRM241468). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted AVS HIGH STREET more time to complete?

UPRERA's record carries 1 completion extension for AVS HIGH STREET, the latest running to 13 Jul 2027. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does AVS HIGH STREET have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

What configurations are available in AVS HIGH STREET?

The unit plan filed with UPRERA lists OTHER and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in AVS HIGH STREET?

The approved unit plan filed with UPRERA runs from 15 to 63 m² of carpet area (about 165 to 682 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in AVS HIGH STREET?

The approved unit plan describes 1 block and 330 units of which 219 are homes and 111 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is AVS HIGH STREET?

About 164 units per acre: 330 planned units across 2.01 acres (8,134 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗