estanzo
ProjectsPromotersDistricts
Tools
Carpet area & loadingHow much of the area you are paying for is not inside the flat.Stamp duty & buying costStamp duty, registration, GST and every charge above the sticker price.Home loan EMIYour EMI, the total interest, and the month-by-month schedule.All tools
estanzo
The builder-reliability record for Indian real estate.
Explore
ProjectsPromotersDistrictsDirectors
Tools
Carpet area & loadingStamp duty & buying costHome loan EMIAll tools
About
How it worksData sourcesReport an error
Legal
DisclaimerPrivacyContact
Data as reported by UP-RERA, with a link to the source on every record. Estanzo does not verify, rate or endorse any builder or project.
Home › Projects

Projects

21 RERA-registered projects

District: Any ▾
Role on the project
Registered2 complaints filed

Humming Retreat Phase-2

Paarth Infrabuild Private Limited·Lucknow
DeadlineOct 202512 months past
Built (reported)22.09% · Q3 FY25
Registered13 complaints filed

Humming Retreat Phase-1

Paarth Infrabuild Private Limited·Lucknow
DeadlineOct 202424 months past
12›
Status: Any ▾
Deadline: Any ▾
Completion certificate: Any ▾
Construction: Any ▾
Density: Any ▾
Sort: Newest registered ▾
Showing 1-20 of 21
Registered
3 complaints filed

Gardenia Residency Phase-2

Paarth Infrabuild Private Limited·Lucknow
DeadlineAug 202338 months past
Registered13 complaints filed

Canary Phase 2

Paarth Infrabuild Private Limited·Lucknow
DeadlineMar 202431 months past
Registered14 complaints filed

Gardenia Residency Phase 1

Paarth Infrabuild Private Limited·Lucknow
DeadlineAug 202514 months past
Built (reported)34.4% · Q2 FY25
Registered49 complaints filed

Goldfinch Phase 1

Paarth Infrabuild Private Limited·Lucknow
DeadlineDec 202158 months past
Registered27 complaints filed

Paarth Republic - EWS/LIG

Paarth Infrabuild Private Limited·Lucknow
DeadlineApr 202430 months past
Registered1 complaint filed

Paarth - Victory Walk Arcade

Paarth Infrabuild Private Limited·Lucknow
DeadlineNov 202511 months past
Built (reported)126.48% · Q3 FY25
RegisteredCC on record57 complaints filed

Aadyant Phase-1

Paarth Infrabuild Private Limited·Lucknow
DeadlineNov 201983 months past
RegisteredCC on record21 complaints filed

Aadyant Phase-2

Paarth Infrabuild Private Limited·Lucknow
DeadlineDec 201982 months past
Registered2 complaints filed

Aadyant Phase-3

Paarth Infrabuild Private Limited·Lucknow
DeadlineSept 201897 months past
Registered1 complaint filed

Aadyant Phase-4

Paarth Infrabuild Private Limited·Lucknow
DeadlineDec 201982 months past
Registered4 complaints filed

Aadyant Phase 5 (Revati B)

Paarth Infrabuild Private Limited·Lucknow
DeadlineJun 202252 months past
Registered13 complaints filed

Arka Phase 1 (EWS/LIG)

Paarth Infrabuild Private Limited·Lucknow
DeadlineDec 201982 months past
Registered76 complaints filed

Arka Phase-2

Paarth Infrabuild Private Limited·Lucknow
DeadlineDec 202158 months past
Registered24 complaints filed

Arka Phase-3

Paarth Infrabuild Private Limited·Lucknow
DeadlineAug 202250 months past
Registered7 complaints filed

Canary Phase 1

Paarth Infrabuild Private Limited·Lucknow
DeadlineMar 202431 months past
Registered28 complaints filed

NU Phase-1

Paarth Infrabuild Private Limited·Lucknow
DeadlineJun 20264 months past
Built (reported)16% · Q1 FY26
Registered38 complaints filed

Humming Phase-1

Paarth Infrabuild Private Limited·Lucknow
DeadlineMay 202429 months past
Registered4 complaints filed

Humming Phase-2

Paarth Infrabuild Private Limited·Lucknow
DeadlineFeb 202432 months past