Panchsheel Buildtech Pvt. Ltd. (RERA ID: UPRERAPRM6558) is a company registered with UP-RERA since 2017. It has 18 projects on record with Estanzo.
One legal entity’s record; a brand may register through several. Complaint counts are allegations, with no outcome attached.
Projects by this promoter
18 on record
Filings for more time
30 filings
| Extension filings | 30 |
| Projects with at least one | 12 of 18 |
| Longest single extension | 1,099 days - PANCHSHEEL GREENS - II (TOWER - D1,D2& E5) |
| Latest extension runs to | 30 Nov 2026 - PANCHSHEEL GREENS - II (TOWER - D1,D2& E5) |
| Permits carrying a revalidation | 9 across 6 projects |
Directors & ownership
4 named by UPRERA
Promoter timeline
25 Nov 2014 - 30 Oct 2025
- Completion certificate filedofficial source ↗
- Extension filednew completion date on file 30 Nov 2026official source ↗
- Completion certificate filedofficial source ↗
- Completion certificate filedofficial source ↗
- Completion certificate filedofficial source ↗
- Extension filednew completion date on file 30 Sept 2025official source ↗
- Extension filednew completion date on file 20 Sept 2024official source ↗
- Extension filednew completion date on file 30 Nov 2026official source ↗
- Completion certificate filedofficial source ↗
- Completion certificate filedofficial source ↗
- Completion certificate filedofficial source ↗
- Extension filednew completion date on file 20 Sept 2024official source ↗
Show 58 earlier filings
- Extension filednew completion date on file 28 Feb 2025official source ↗
- Extension filednew completion date on file 27 Nov 2024official source ↗
- Extension filednew completion date on file 20 Jan 2024official source ↗
- Extension filednew completion date on file 24 Jul 2023official source ↗
- Completion certificate filedofficial source ↗
- Extension filednew completion date on file 29 May 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 28 Feb 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 28 Feb 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 28 Feb 2023official source ↗
- Permit revalidatedvalid to 24 Jul 2023as recorded by UPRERA: 570/INI/Z-4/22official source ↗
- Permit revalidatedvalid to 24 Jul 2023as recorded by UPRERA: 570/INI/Z-4/22official source ↗
- Completion certificate filedofficial source ↗
- Extension filednew completion date on file 27 Feb 2023official source ↗
- Extension filednew completion date on file 27 Nov 2023official source ↗
- Extension filednew completion date on file 24 Jul 2023official source ↗
- Permit revalidatedvalid to 24 Nov 2024as recorded by UPRERA: PLG/BP-3089(S)4316official source ↗
- Permit revalidatedvalid to 24 Nov 2024as recorded by UPRERA: PLG/BP-3089(S)4316official source ↗
- Extension filednew completion date on file 28 Feb 2022as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 28 Feb 2022as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 29 May 2022official source ↗
- Extension filednew completion date on file 27 Feb 2022official source ↗
- Extension filednew completion date on file 28 Nov 2022official source ↗
- Extension filednew completion date on file 29 May 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 28 Feb 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 28 Feb 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 1 Jan 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 29 Dec 2020as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Completion certificate filedofficial source ↗
- Extension filednew completion date on file 29 Sept 2020as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Completion certificate filedofficial source ↗
- Extension filednew completion date on file 31 Mar 2020official source ↗
- Extension filednew completion date on file 30 Jun 2020official source ↗
- Completion certificate filedofficial source ↗
- Completion certificate filedofficial source ↗
- Extension filednew completion date on file 24 Nov 2019official source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Permit revalidatedvalid to 8 Jan 2025as recorded by UPRERA: 272/ZONE-5/2015official source ↗
- Permit revalidatedvalid to 21 Sept 2024as recorded by UPRERA: 390/ZONE-4/14-15official source ↗
- Permit revalidatedvalid to 21 Dec 2023as recorded by UPRERA: 390/ZONE-4/14-15official source ↗
- Permit revalidatedvalid to 21 Sept 2024as recorded by UPRERA: 390/ZONE - 4/14-15official source ↗
- Permit revalidatedvalid to 7 Dec 2026as recorded by UPRERA: BP-3089/GH/FTS-8857official source ↗
Quarterly reports filed, by financial year
Common questions about Panchsheel Buildtech Pvt. Ltd.
How many projects has Panchsheel Buildtech Pvt. Ltd. registered with RERA?
Estanzo holds 18 projects on record with UPRERA, filed by Panchsheel Buildtech Pvt. Ltd. (promoter RERA ID UPRERAPRM6558). This counts filings by this legal entity only - a builder brand may file through several entities.
Who are the directors of Panchsheel Buildtech Pvt. Ltd.?
Panchsheel Buildtech Pvt. Ltd. disclosed 4 directors or partners to UPRERA, listed on this page as published. Estanzo shows the names and roles from that filing only.
When was Panchsheel Buildtech Pvt. Ltd. registered with RERA?
Panchsheel Buildtech Pvt. Ltd. has been registered with UPRERA since 28 Jul 2017.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗