3,766 RERA-registered projects · as reported by UPRERA

Cards Table
District: Any ▾
AnyAgraAligarhAmrohaAyodhyaBahraichBandaBarabankiBareillyBastiBijnorBudaunBulandshahrChandauliEtahEtawahFirozabadGautam Budh NagarGhaziabadGondaGorakhpurHapurHardoiHathrasJaunpurJhansiKanpur NagarKushinagarLalitpurLucknowMathuraMauMeerutMirzapurMoradabadMuzaffarnagarPrayagrajRampurSaharanpurSambhalShahjahanpurSitapurSultanpurUnnaoVaranasi
Status: Any ▾
AnyRegisteredCompletedDe-registeredAbeyanceNCLTLapsedWithdrawn
Sort: Default ▾
DefaultMost delayedNewest registeredName A–Z
Showing 3,361–3,380 of 3,766
Default on QPR
THE COURTYARD
Promoter not reported·Jhansi
Units (plan)39
DeadlineDec 2021
Delay▲ 4 yr
Registered
THE COURTYARD SHANTIPURAM
Promoter not reported·Prayagraj
Units (plan)165
DeadlineMar 2027
Delay—
Registered
The Crescent
Promoter not reported·Prayagraj
Units (plan)37
DeadlineMar 2024
Delay▲ 2 yr
Registered
THE DOWNTOWN
Promoter not reported·Gautam Budh Nagar
Units (plan)17,00,160
DeadlineJun 2023
Delay▲ 3 yr
Registered
THE ELEMENT - PHASE -I
Promoter not reported·Ghaziabad
Units (plan)112
DeadlineMar 2028
Delay—
Registered
THE ELITE
Promoter not reported·Gomti Nagar Extension
Units (plan)100
DeadlineSept 2030
Delay—
Registered
THE ELORA COMMERCIAL SPACE AND STUDIOS
Promoter not reported·VILLAGE MEENAPUR , PARGANA- NIGOHA
Units (plan)180
DeadlineMay 2028
Delay—
Registered
The Elysium
Promoter not reported·Yamuna Expressway Industrial Development Area
Units (plan)2,454
DeadlineAug 2028
Delay—
Registered
THE ESTATES
Promoter not reported·NOOR NAGAR
Units—
DeadlineFeb 2030
Delay—
Registered
THE EXPRESS PARK VIEW II- LOW RISE APARTMENTS
Promoter not reported·Gautam Budh Nagar
Units (plan)310
DeadlineJan 2025
Delay▲ 18 mo
Registered
The Flagship Phase 1
Promoter not reported·Gautam Budh Nagar
Units (plan)716
DeadlineNov 2027
Delay—
Registered
THE FLAGSHIP PHASE 2
Promoter not reported·Gautam Budh Nagar
Units (plan)580
DeadlineNov 2027
Delay—
Registered
The Flagship Phase 3
Promoter not reported·Sector-140A
Units (plan)288
DeadlineNov 2027
Delay—
Registered
THE FLAGSHIP PHASE 4
Promoter not reported·NOIDA
Units (plan)229
DeadlineNov 2027
Delay—
Registered
The Flagship Phase 5
Promoter not reported·Sector 140A, NOIDA
Units (plan)169
DeadlineNov 2027
Delay—
Registered
The G
Promoter not reported·Bajidpur
Units (plan)234
DeadlineJul 2029
Delay—
Registered
THE GALLERIA
Promoter not reported·Lucknow
Units (plan)157
DeadlineNov 2026
Delay—
Registered
THE GALLERIA 1
Promoter not reported·Lucknow
Units (plan)157
DeadlineSept 2027
Delay—
Registered
THE GOLDEN GATE
Promoter not reported·Ghaziabad
Units (plan)228
DeadlineMar 2024
Delay▲ 2 yr
Registered
THE GOLDEN PALMS (TOWER A,B,L,M,N)
Promoter not reported·Gautam Budh Nagar
Units—
DeadlineMar 2018
Delay▲ 8 yr