3,766 RERA-registered projects · as reported by UPRERA

Cards Table
District: Any ▾
AnyAgraAligarhAmrohaAyodhyaBahraichBandaBarabankiBareillyBastiBijnorBudaunBulandshahrChandauliEtahEtawahFirozabadGautam Budh NagarGhaziabadGondaGorakhpurHapurHardoiHathrasJaunpurJhansiKanpur NagarKushinagarLalitpurLucknowMathuraMauMeerutMirzapurMoradabadMuzaffarnagarPrayagrajRampurSaharanpurSambhalShahjahanpurSitapurSultanpurUnnaoVaranasi
Status: Any ▾
AnyRegisteredCompletedDe-registeredAbeyanceNCLTLapsedWithdrawn
Sort: Default ▾
DefaultMost delayedNewest registeredName A–Z
Showing 3,401–3,420 of 3,766
Registered
THE KUTUMB
Promoter not reported·SECTOR 5 ADITYA WORLD CITY
Units (plan)434
DeadlineSept 2029
Delay—
Registered
The Majesty
Promoter not reported·Itaua Beniram
Units—
DeadlineJun 2030
Delay—
Registered
THE MALL ROAD
Promoter not reported·Kazipura, Batawali Mustakam
Units—
DeadlineFeb 2028
Delay—
Default on QPR
The Merlin
Promoter not reported·Ghaziabad
Units (plan)257
DeadlineSept 2018
Delay▲ 7 yr
Registered
The Monarque
Promoter not reported·Sector 22D, Yamuna Expressway
Units (plan)314
DeadlineSept 2029
Delay—
Registered
The Nest
Promoter not reported·Sarojini Nagar, Lucknow
Units—
DeadlineAug 2027
Delay—
Registered
THE OASIS
Promoter not reported·Gautam Budh Nagar
Units—
DeadlineJun 2022
Delay▲ 4 yr
Registered
The Palm Estate
Promoter not reported·Naubasta
Units (plan)374
DeadlineFeb 2030
Delay—
Registered
THE PARK STREET
Promoter not reported·Gautam Budh Nagar
Units (plan)820
DeadlineSept 2021
Delay▲ 4 yr
Registered
THE PEAK
Promoter not reported·Kanpur Nagar
Units (plan)240
DeadlineSept 2024
Delay▲ 22 mo
Registered
The Peridona C-1 Jaypee Greens
Promoter not reported·Jaypee Greens, Sector 26 & 31, Greater Noida
Units (plan)341
DeadlineFeb 2030
Delay—
Registered
The Pinnacle
Promoter not reported·Uttardhauna
Units (plan)126
DeadlineOct 2030
Delay—
Registered
The Pitambra Town
Promoter not reported·Jhansi
Units—
DeadlineJul 2025
Delay▲ 12 mo
Registered
The Pitambra Town 1
Promoter not reported·Jhansi
Units—
DeadlineJul 2025
Delay▲ 12 mo
Registered
The Pitambra Town Phase II
Promoter not reported·Mouza Bhojla
Units—
DeadlineSept 2030
Delay—
Registered
The Platinum Mall
Promoter not reported·Meerut
Units (plan)139
DeadlineMar 2018
Delay▲ 8 yr
Registered
The Raas
Promoter not reported·Julhendi and Konhai
Units—
DeadlineAug 2030
Delay—
Registered
The Regency, Saharanpur
Promoter not reported·Saharanpur
Units (plan)74
DeadlineMar 2024
Delay▲ 2 yr
Registered
The Residences
Promoter not reported·Bareilly
Units—
DeadlineDec 2027
Delay—
Default on QPR
The Resident Tower
Promoter not reported·Gautam Budh Nagar
Units (plan)231
DeadlineOct 2024
Delay▲ 21 mo