3,839 RERA-registered projects · as reported by UPRERA

Cards Table
District: Any ▾
AnyAgraAligarhAmrohaAyodhyaBahraichBandaBarabankiBareillyBastiBijnorBudaunBulandshahrChandauliEtahEtawahFirozabadGautam Budh NagarGhaziabadGondaGorakhpurHapurHardoiHathrasJaunpurJhansiKanpur NagarKushinagarLalitpurLucknowMathuraMauMeerutMirzapurMoradabadMuzaffarnagarPrayagrajRampurSaharanpurSambhalShahjahanpurSitapurSultanpurUnnaoVaranasi
Status: Any ▾
AnyRegisteredCompletedDe-registeredAbeyanceNCLTLapsedWithdrawn
Sort: Default ▾
DefaultMost delayedNewest registeredName A–Z
Showing 1,681–1,700 of 3,839
Registered
JAIPURIA SUNRISE GREEN NH-24 BLOCK E
SMV AGENCIES PVT LTD·Ghaziabad
Units—
DeadlineDec 2018
Delay▲ 7 yr
Registered
JAIPURIA SUNRISE GREEN NH-24 BLOCK F
SMV AGENCIES PVT LTD·Ghaziabad
Units—
DeadlineDec 2018
Delay▲ 7 yr
Registered
Jaipuria Sunrise Greens
PARKVIEW CITY LIMITED·Agra
Units—
DeadlineDec 2017
Delay▲ 8 yr
Default on QPR
JAIPURIA SUNRISE GREENS BLOCK G AND H
SMV AGENCIES PVT LTD·Ghaziabad
Units—
DeadlineJun 2021
Delay▲ 5 yr
Registered
JAL VAYU TOWERS MEERUT
AIR FORCE NAVAL HOUSING BOARD·Meerut
Units (plan)491
DeadlineJul 2018
Delay▲ 8 yr
Registered
Janeshwar Enclave
Lucknow Development Authority·Lucknow
Units (plan)516
DeadlineDec 2018
Delay▲ 7 yr
Registered
JANHIT AWAS YOJNA-AFFORDAVAL HOMES
Promoter not reported·Gautam Budh Nagar
Units (plan)270
DeadlineNov 2019
Delay▲ 6 yr
Registered
JANHWI ENCLAVE, EWS FLATS, LUCKNOW
U.P. Awas Evam Vikas Parishad·Lucknow
Units (plan)32
DeadlineJun 2018
Delay▲ 8 yr
Registered
JANHWI ENCLAVE, LIG FLATS, LUCKNOW
U.P. Awas Evam Vikas Parishad·Lucknow
Units (plan)128
DeadlineJun 2018
Delay▲ 8 yr
Registered
JANVI AND BHAGIRATHI ENCLAVE SCHEME
Kanpur Development Authority·Kanpur Nagar
Units—
DeadlineOct 2018
Delay▲ 7 yr
Registered
Jashn Elevate Phase 1
Privue Builders Private Limited·Hasanpur, khewli
Units (plan)224
DeadlineFeb 2029
Delay—
Registered
Jashn Elevate Phase 2
Privue Builders Private Limited·Hasanpur Khewli, Lucknow
Units (plan)124
DeadlineFeb 2029
Delay—
Registered
Jashn Elevate Phase 3
Privue Builders Private Limited·Hasanpur Khewli
Units (plan)128
DeadlineNov 2031
Delay—
Registered
JASMINE GROVE
Savfab Developers Private Limited·Ghaziabad
Units (plan)549
DeadlineDec 2022
Delay▲ 3 yr
Registered
Jasmine Grove (Phase-II)
Savfab Developers Private Limited·Ghaziabad
Units—
DeadlineJun 2024
Delay▲ 2 yr
Registered
Jaypee Greens Aman, Noida
Jaypee Infratech Limited·Gautam Budh Nagar
Units (plan)4,228
DeadlineJun 2019
Delay▲ 7 yr
NCLT
Jaypee Greens Boomerang Residences, Noida
Jaiprakash Associates Limited·Gautam Budh Nagar
Units (plan)124
DeadlineDec 2021
Delay▲ 4 yr
NCLT
Jaypee Greens Bougainvilleas, SDZ, YEW
Jaiprakash Associates Limited·Gautam Budh Nagar
Units—
DeadlineDec 2014
Delay▲ 11 yr
NCLT
Jaypee Greens Country Homes-II, SDZ, YEW
Jaiprakash Associates Limited·Gautam Budh Nagar
Units—
DeadlineNov 2014
Delay▲ 11 yr
NCLT
Jaypee Greens Country Homes-I, SDZ, YEW
Jaiprakash Associates Limited·Gautam Budh Nagar
Units—
DeadlineNov 2011
Delay▲ 14 yr
‹1…848586…192›