estanzo
ProjectsPromotersDistricts
Tools
Carpet area & loadingHow much of the area you are paying for is not inside the flat.Stamp duty & buying costStamp duty, registration, GST and every charge above the sticker price.Home loan EMIYour EMI, the total interest, and the month-by-month schedule.All tools
estanzo
The builder-reliability record for Indian real estate.
Explore
ProjectsPromotersDistrictsDirectors
Tools
Carpet area & loadingStamp duty & buying costHome loan EMIAll tools
About
How it worksData sourcesReport an error
Legal
DisclaimerPrivacyContact
Data as reported by UP-RERA, with a link to the source on every record. Estanzo does not verify, rate or endorse any builder or project.
Home › Projects

Projects

29 RERA-registered projects

District: Any ▾
Role on the project
Registered

SECTOR 5 GREATER BAREILLY AWASIYA YOJNA

Bareilly Development Authority·Village Ballipur Ahmadpur, District- Bareilly
DeadlineMar 2030
Registered

COMMERCIAL COMPLEX (BLOCK-A) AT SECTER-5 RAMGANGA NAGAR SCHEME, BAREILLY

Bareilly Development Authority·SECTOR-5
DeadlineDec 2026
Built (reported)92.87% · Q1 FY26
Registered

12›
Status: Any ▾
Deadline: Any ▾
Completion certificate: Any ▾
Construction: Any ▾
Density: Any ▾
Sort: Newest registered ▾
Showing 1-20 of 29
COMMERCIAL COMPLEX (BLOCK-C) AT SECTOR-5 RAMGANGA NAGAR SCHEME BAREILLY
Bareilly Development Authority·SECTOR-5
DeadlineDec 2026
Built (reported)91.96% · Q1 FY26
Registered

SECTOR 3 GREATER BAREILLY AWASIYA YOJNA

Bareilly Development Authority·NAWADIYA JHADA AND BALIPUR AHMADPUR, BAREILLY
DeadlineJun 2029
Built (reported)83.92% · Q1 FY26
Registered

SECTOR-4, GREATER BAREILLY AWASIYA YOJNA

Bareilly Development Authority·NAWADIYA JHADA AND BALIPUR AHAMDPUR
DeadlineJun 2029
Built (reported)77.81% · Q1 FY26
Registered

Multistoried Office Complex Sector-2 Ram Ganga Nagar Yojna

Bareilly Development Authority·RAMGANGA NAGAR YOJNA SECTOR-2 BAREILLY
DeadlineMay 2028
Built (reported)100% · Q1 FY26
Registered

SECTOR-1A, GREATER BAREILLY AWASIYA YOJNA

Bareilly Development Authority·MOHANPUR URF RAMNAGAR and ITAUA BENIRAM, GREATER BAREILLY AWASIYA YOJNA
DeadlineAug 2029
Built (reported)81.21% · Q1 FY26
Registered

SECTOR 1B GREATER BAREILLY

Bareilly Development Authority·MOHANPUR URF RAMNAGAR
DeadlineOct 2028
Built (reported)66.87% · Q1 FY26
Registered

SECTOR 2A, GREATER BAREILLY

Bareilly Development Authority·Bareilly
DeadlineAug 2028
Built (reported)95.89% · Q1 FY26
Registered

SECTOR-7 (PART-2) RAMGANGA NAGAR YOJNA

Bareilly Development Authority·Bareilly
DeadlineApr 2027
Built (reported)93.67% · Q1 FY26
Registered

SECTOR 5 (PART) RAMGANGA NAGAR SCHEME

Bareilly Development Authority·Bareilly
DeadlineDec 2026
Built (reported)99.29% · Q1 FY26
Registered

SHIPRA ENCLAVE SECTOR 8 RAMGANGA NAGAR AWASIYA YOJNA

Bareilly Development Authority·Bareilly
DeadlineApr 2027
Built (reported)99.3% · Q1 FY26
Registered

INDRAPRASTH ENCLAVE SECTOR 12 RAMGANGA NAGAR YOJNA

Bareilly Development Authority·Bareilly
DeadlineNov 2026
Built (reported)99.52% · Q1 FY26
Registered

RAMGANGA NAGAR YOJNA SECTOR 11 PANCHWATI ENCLAVE

Bareilly Development Authority·Bareilly
DeadlineJan 2027
Built (reported)98.77% · Q1 FY26
Registered

SARYU ENCLAVE SECTOR 10 RAMGANGA NAGAR AWASIYA YOJNA

Bareilly Development Authority·Bareilly
DeadlineJul 20263 months past
Built (reported)100% · Q1 FY26
Registered

SABARMATI ENCLAVE, SECTOR-1 (PART) RAMGANGA NAGAR YOJNA

Bareilly Development Authority·Bareilly
DeadlineNov 2026
Built (reported)100% · Q1 FY26
Registered

RGN Scheme Sector 1 (Vyom Khand) Brahmputra Enclave

Bareilly Development Authority·Bareilly
DeadlineDec 2026
Built (reported)100% · Q1 FY26
Registered

RGN Sector 4 Alakhnanda Enclave

Bareilly Development Authority·Bareilly
DeadlineAug 20263 months past
Built (reported)100% · Q1 FY26
Registered

Ramganga Nagar Scheme Sector-2 Salil Khand

Bareilly Development Authority·Bareilly
DeadlineJul 20263 months past
Built (reported)100% · Q1 FY26
RegisteredCC on record

Ramganga Nagar Scheme Antriksh Khand Part-2 (Sector-9)

Bareilly Development Authority·Bareilly
DeadlineJun 202340 months past