estanzo
Projects
estanzo
The builder-reliability record for Indian real estate.
Explore
ProjectsPromotersDistrictsDirectors
About
How it worksData sourcesReport an error
Legal
DisclaimerPrivacyContact
Data as reported by UP-RERA. Estanzo reproduces public filings as-is with source links and does not verify, rate or endorse any builder or project.
Home › Projects

Projects

3,766 RERA-registered projects · as reported by UPRERA

Cards Table
District: Any ▾
AnyAgraAligarhAmrohaAyodhyaBahraichBandaBarabankiBareillyBastiBijnorBudaunBulandshahrChandauliEtahEtawahFirozabadGautam Budh NagarGhaziabadGondaGorakhpurHapurHardoiHathrasJaunpurJhansiKanpur NagarKushinagarLalitpurLucknowMathuraMauMeerutMirzapurMoradabadMuzaffarnagarPrayagrajRampurSaharanpurSambhalShahjahanpurSitapurSultanpurUnnaoVaranasi
Status: Any ▾
AnyRegisteredCompletedDe-registeredAbeyanceNCLTLapsedWithdrawn
Sort: Default ▾
DefaultMost delayedNewest registeredName A–Z
Showing 2,921–2,940 of 3,766
Registered
Saya Zion
Saya Buildcon Consortium Pvt. Ltd.·Gautam Budh Nagar
Units (plan)758
DeadlineJun 2019
Delay▲ 7 yr
Registered
SBI Enclave
U.P. Awas Evam Vikas Parishad·Lucknow
Units (plan)68
DeadlineJan 2021
Delay▲ 5 yr
Registered
SCC BLOSSOM BLOCK A AND B
SCC BUILDERS PVT. LTD.
‹1…146147148…189›
·
Noor Nagar, Raj Nagar Extension
Units (plan)189
DeadlineMar 2029
Delay—
Registered
SCC BLOSSOM (PMAY) COMMERCIAL BLOCK, NURSING HOME AND NURSERY SCHOOL
SCC BUILDERS PVT. LTD.·Ghaziabad
Units (plan)80
DeadlineNov 2025
Delay▲ 8 mo
Registered
SCC BLOSSOM (PMAY) PH-1 BLOCK X
SCC BUILDERS PVT. LTD.·Ghaziabad
Units (plan)252
DeadlineAug 2023
Delay▲ 2 yr
Registered
SCC BLOSSOM (PMAY) PH-2 BLOCK C AND BLOCK D
SCC BUILDERS PVT. LTD.·Ghaziabad
Units (plan)370
DeadlineSept 2026
Delay—
Registered
SCC SAPPHIRE PH-2 ( BLOCK-A)
SCC BUILDERS PVT. LTD.·Ghaziabad
Units (plan)154
DeadlineJun 2021
Delay▲ 5 yr
Registered
SCC SAPPHIRE PHASE-I BLOCK B,C,D & E
SCC BUILDERS PVT. LTD.·Ghaziabad
Units (plan)560
DeadlineDec 2018
Delay▲ 7 yr
Registered
SCC Sapphire Ph-II BLOCK - F
SHRINE BUILDTECH PVT. LTD.·Ghaziabad
Units (plan)176
DeadlineJun 2021
Delay▲ 5 yr
Registered
SDS RAHEJA RESIDENCY
S Raheja Infrastructure Pvt Ltd·Varanasi
Units (plan)143
DeadlineMar 2018
Delay▲ 8 yr
Registered
Sector-11 Commercial Scheme
Gorakhpur Industrial Development Authority·Sector-11
Units—
DeadlineSept 2029
Delay—
Registered
Sector-11 Residential Scheme
Gorakhpur Industrial Development Authority·Zero Point, Kalesar
Units—
DeadlineAug 2029
Delay—
Registered
SECTOR-1A, GREATER BAREILLY AWASIYA YOJNA
Bareilly Development Authority·MOHANPUR URF RAMNAGAR and ITAUA BENIRAM, GREATER BAREILLY AWASIYA YOJNA
Units—
DeadlineAug 2029
Delay—
Registered
SECTOR 1B GREATER BAREILLY
Bareilly Development Authority·MOHANPUR URF RAMNAGAR
Units—
DeadlineOct 2028
Delay—
Registered
Sector 1 RGN
Bareilly Development Authority·Bareilly
Units (plan)410
DeadlineApr 2021
Delay▲ 5 yr
Registered
SECTOR 2A, GREATER BAREILLY
Bareilly Development Authority·Bareilly
Units—
DeadlineAug 2028
Delay—
Registered
SECTOR 3 GREATER BAREILLY AWASIYA YOJNA
Bareilly Development Authority·NAWADIYA JHADA AND BALIPUR AHMADPUR, BAREILLY
Units—
DeadlineJun 2029
Delay—
Registered
Sector 3 RGN
Bareilly Development Authority·Bareilly
Units—
DeadlineSept 2021
Delay▲ 4 yr
Registered
SECTOR-4, GREATER BAREILLY AWASIYA YOJNA
Bareilly Development Authority·NAWADIYA JHADA AND BALIPUR AHAMDPUR
Units—
DeadlineJun 2029
Delay—
Registered
Sector 4 RGN
Bareilly Development Authority·Bareilly
Units—
DeadlineSept 2021
Delay▲ 4 yr